INSP - Final | 9/25/1996 | 9/25/1996 | 9/25/1996 | P | PASS |
|
|
|
09/25/96 333 - card signed for final perm
|
Permanent Occupancy | | 9/25/1996 | 9/25/1996 | | DONE |
|
|
|
|
INSP - Final | 9/24/1996 | 9/24/1996 | 9/24/1996 | P | FAIL |
|
|
|
09/24/96 333 - not ready
|
INSP - Final | 9/23/1996 | 9/23/1996 | 9/23/1996 | P | FAIL |
|
|
|
09/23/96 333 - #401 CORR-CORREC-CALL FOR REINSP WHEN COMPLETED old corrections not made
|
INSP - Final | 9/18/1996 | 9/19/1996 | 9/19/1996 | P | FAIL |
|
|
|
Firecaulking still required in corridor penetrations.
|
INSP - Final | 9/16/1996 | 9/17/1996 | 9/17/1996 | P | PART |
|
|
|
LATE AFTERNOON. CN issued ok for temp. occ.. Routed to Cathy.
|
INSP - Final | 9/13/1996 | 9/16/1996 | 9/17/1996 | A | PASS |
|
|
|
all items complete 9/25/96 09/16/96 405 - SUITE 400 - MIKE MURIE - ###-#### alarm test and final temp occ isssued...smoke seals missing on doors
|
INSP - Final | 9/16/1996 | 9/16/1996 | 9/16/1996 | | NR |
|
|
|
/ / 405 - not ready...alarms not working
|
INSP - Final | 8/28/1996 | 8/28/1996 | 8/28/1996 | | FAIL |
|
|
|
/ / 405 - b occ in multi-use high rise advised cont he will need alarm plans. also needs f/s damper on penetration of wall to adjacent suite w fresh air duct. noted on plans but arch said not required.
|
INSP - Framing/Rough-in | 8/26/1996 | 8/27/1996 | 8/27/1996 | A | PASS |
|
|
|
08/27/96 333 - corridor walls ok
|
INSP - Framing/Rough-in | 6/19/1996 | 6/19/1996 | 6/19/1996 | P | PASS |
|
|
|
|
INSP - Conference | 6/5/1996 | 6/5/1996 | 6/5/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - LEFT CORRECTION NOTICE TELLING H.V.A.C. CONTRACTOR TO SUBMIT DRAWINGS TO THE CITY FOR REVIEW AND APPROVAL BEFORE ANY INSPECTIONS CAN DONE.
|
INSP - Framing/Rough-in | 4/8/1996 | 4/8/1996 | 4/8/1996 | P | CANC |
Wes Worcester
|
|
|
wrong permit number entered
|