INSP - Final | 3/25/1999 | 3/26/1999 | 3/26/1999 | A | PASS |
|
|
|
L.C. #16385 issued 3-26-99 - 338
|
INSP-Final Inspection | 3/24/1999 | 3/25/1999 | 3/25/1999 | A | PASS |
Rick Jackson
|
|
|
RON ###-#### occ approved
|
INSP-Final Inspection | 3/24/1999 | 3/24/1999 | 3/24/1999 | P | CANC |
Rick Jackson
|
|
|
###-#### RON//FINAL FIRE rescheduled for 3/25
|
INSP-Final Inspection | 10/29/1998 | 10/30/1998 | 11/2/1998 | P | PART |
Rick Jackson
|
|
|
ron cell ###-#### fn insp
|
INSP - Final | 10/29/1998 | 10/30/1998 | 10/30/1998 | A | PASS |
|
|
|
10/30/98 333 - ok to sign for perm
|
INSP - Final | 10/21/1998 | 10/22/1998 | 10/23/1998 | P | FAIL |
|
|
|
10/22/98 333 - RON ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 10/21/1998 | 10/22/1998 | 10/22/1998 | P | FAIL |
Rick Jackson
|
|
|
RON ###-#### door hold-opens didn't release on alarm; sprinkler issues
|
INSP-Conference | 10/12/1998 | 10/12/1998 | 10/12/1998 | P | PART |
Rick Jackson
|
|
|
fire pump room requires sprinklering and remove combustibles from above gridded ceiling
|
INSP - Wall cover | 10/8/1998 | 10/9/1998 | 10/9/1998 | A | FAIL |
Jim Storey
|
|
|
10/09/98 301 - RON ###-#### CEILING COVER CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 10/8/1998 | 10/9/1998 | 10/9/1998 | A | FAIL |
Jim Storey
|
|
|
10/09/98 301 - RON ###-#### TRY TO BE THERE WITH STRUCTURAL INSPECTOR CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Sprinkler Rough-in/Hydro | 10/9/1998 | 10/9/1998 | 10/9/1998 | A | FAIL |
Rick Jackson
|
|
|
sway bracing not done; combustibles above drop ceiling; needs head in bathroom by dressing rooms; smoke detector within 3 feet of diffuser
|
INSP-Sprinkler Rough-in/Hydro | 10/9/1998 | 10/9/1998 | 10/9/1998 | A | FAIL |
Rick Jackson
|
|
|
combustibles above in corridors; head needed in bathroom; sway bracing needed; smoke detector too close to diffuser;
|
INSP - Framing/Rough-in | 6/29/1998 | 6/29/1998 | 6/29/1998 | P | PASS |
|
|
|
06/29/98 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 3/17/1998 | 3/18/1998 | 3/18/1998 | A | PART |
|
|
|
03/18/98 333 - framing ok BASEMENT CT SIMILATOR ROOM--RON ###-####
|
INSP - Final | 2/27/1998 | 3/2/1998 | 3/2/1998 | P | PART |
|
|
|
03/02/98 333 - card signed for tempRON ###-####--MSTI
|
INSP-Final Inspection | 2/26/1998 | 2/27/1998 | 2/27/1998 | A | PASS |
Rick Jackson
|
|
|
PLEASE MEET RON AT 10:00--###-####--MSTI alarms, mag-hold opens, dampers all operational
|
INSP-Sprinkler Rough-in/Hydro | 2/26/1998 | 2/26/1998 | 2/26/1998 | A | PASS |
Rick Jackson
|
|
|
hydro completed/rough-in okay
|
INSP - Framing/Rough-in | 2/12/1998 | 2/13/1998 | 2/13/1998 | A | PART |
|
|
|
02/13/98 333 - RON ###-####-CEILING GRID RICK WILL BE SCHEDULED TO GO OUT ALSO YOU MIGHT WANT TO GET WITH HIM. ceilings ok to cover dampers ok
|
INSP-Final Inspection | 2/12/1998 | 2/13/1998 | 2/13/1998 | A | PASS |
Rick Jackson
|
|
|
RON ###-####-###-####-KIM WILL BE GOING OUT ALSO-FIRE DAMPERS smoke/fire dampers operated correctly.
|
INSP-Sprinkler Rough-in/Hydro | 2/13/1998 | 2/13/1998 | 2/13/1998 | A | FAIL |
Rick Jackson
|
|
|
additional hangers needed in south/west end. comm. lines strapped to sprinkler piping.
|
INSP - Framing/Rough-in | 2/2/1998 | 2/3/1998 | 2/3/1998 | P | PASS |
|
|
|
02/03/98 333 - SCLG-OK SUSPENDED CEILING
|
INSP - Framing/Rough-in | 1/14/1998 | 1/14/1998 | 1/14/1998 | | PASS |
|
|
|
/ / 333 - phase 2frame ok 1st floor
|
INSP - Carpentry | 10/16/1997 | 10/16/1997 | 10/16/1997 | A | PART |
Carl Dependahl
|
|
|
GYP AT 4HR WALL...GOT FASTENER SCHED. FOR 4-LAYER GYP...301 WILL INSP AT PM.
|
INSP - Framing/Rough-in | 10/15/1997 | 10/16/1997 | 10/16/1997 | P | PART |
Jim Storey
|
|
|
10/16/97 301 - 4 hr gyp atchment ok work in progess.
|
INSP - Carpentry | 10/15/1997 | 10/15/1997 | 10/15/1997 | P | NR |
Carl Dependahl
|
|
|
333 AREA NW CORNER 1ST FL MSTI; CHK GYP LAYERS AT 4 HR WALL SECTION...nr, need recall insp.
|
INSP - Framing/Rough-in | 10/14/1997 | 10/15/1997 | 10/15/1997 | A | PART |
Carl Dependahl
|
|
|
four hour wall exterior...333 AREA. NW CORNER 1ST FL EXT WALL. NEED TO SEE ATTACHMENT OF MULTI-LAYER GYPSUM.
|
INSP-Final Inspection | 8/7/1997 | 8/7/1997 | 8/7/1997 | P | PASS |
|
|
|
1PM, RON all phase 1 items complete
|
INSP - Occupancy Sign-off | 7/30/1997 | 7/31/1997 | 7/31/1997 | A | PART |
|
|
|
07/31/97 333 - first phase ok for temp
|
INSP-Final Inspection | 7/30/1997 | 7/31/1997 | 7/31/1997 | A | FAIL |
|
|
|
ELEV RECAL DOES NOT WORK
|
INSP - Temporary occupancy | 7/22/1997 | 7/23/1997 | 7/23/1997 | A | FAIL |
|
|
|
07/23/97 333 - cn not made
|
INSP-Final Inspection | 7/23/1997 | 7/23/1997 | 7/23/1997 | P | PART |
|
|
|
C.N ISSUED WITH ITEMS TO BE RESOLVED, OK FOR EMPLOYEES ONLY
|
INSP-Final Inspection | 7/21/1997 | 7/22/1997 | 7/23/1997 | P | FAIL |
|
|
|
REINSPECT, ALARM TWESTING, C/N ISSUED
|
INSP-Final Inspection | 7/18/1997 | 7/21/1997 | 7/21/1997 | A | NR |
|
|
|
NOT READY YET
|
INSP - Temporary occupancy | 7/17/1997 | 7/18/1997 | 7/18/1997 | P | FAIL |
|
|
|
07/17/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 7/16/1997 | 7/18/1997 | 7/18/1997 | A | FAIL |
|
|
|
ALARM TESTING, SPRINKLER TESTING, EXITING alarms not complete, list of other items left
|
INSP-Sprinkler Rough-in/Hydro | 7/16/1997 | 7/16/1997 | 7/16/1997 | A | PASS |
|
|
|
FINISH FLRS B&1, SHELL ONLY 2-P, NEED FDC FOR STANDPIPE FOR FINAL, ALL HYDRO TESTED
|
INSP-Sprinkler Rough-in/Hydro | 6/16/1997 | 6/16/1997 | 6/16/1997 | P | PART |
|
|
|
electrical room, marv wants heads moved ok to relo to center under beam
|
INSP-Sprinkler Rough-in/Hydro | 5/30/1997 | 5/30/1997 | 5/30/1997 | A | PART |
|
|
|
ALLOWED EXTENSIONS TO NW TOWER HOSE CONN AT 2.5 INCH, CHECKED FOR SPACING/ OBSTRUCTIONS. PROBLEMS WITH DECORATIVE SOFFITS NOTED. WILL RECHECK AT HYDRO.
|
INSP-Conference | 5/6/1997 | 5/8/1997 | 5/8/1997 | A | PASS |
|
|
|
9 am mtg w/ simplex at eidam assoc, 815 park, st 230 on alarm plans G Eidam to revise floor plans, simplex to follow with ness revs to schematic
|
INSP-Sprinkler Rough-in/Hydro | 5/7/1997 | 5/7/1997 | 5/7/1997 | P | PART |
|
|
|
basement hydro ( not tied to riser), told stan ok to tie cross connection in on 2nd flr of stairwell ( base of standpipe)
|
INSP-Sprinkler Rough-in/Hydro | 4/30/1997 | 4/30/1997 | 4/30/1997 | P | PART |
|
|
|
clarified correction notice on alarm system w/ st lukes staff ( ron & D Maloney), walked through sprinkler issues w/ shilo & st lukes, will resubmit proposed changes to fdc/piv locations. Want to appeal sprinkling under drive under canopy. want to route dry standpipe on 2nd floor.
|
INSP-Conference | 4/11/1997 | 4/10/1997 | 4/10/1997 | P | PART |
|
|
|
PICKED UP PLANS AND REVIEWED, STILL MISSING FLOOR PLANS AND PRODUCT DATA SHEETS TO COMPLETE REVIEW
|
INSP-Conference | 4/10/1997 | 4/10/1997 | 4/10/1997 | A | NR |
|
|
|
meeting at simplex office to review alarm plan correction list - T. Kyle PLANS NOT READY AT SCHEDULED TIME OF 11 AM,
|
INSP-Conference | 3/27/1997 | 3/31/1997 | 3/31/1997 | P | PASS |
|
|
|
alarm plan review, return to ron w/ correction list, 2 pgs, resubmittal required
|
INSP-Conference | 3/27/1997 | 3/26/1997 | 3/26/1997 | P | PART |
|
|
|
meeting w/ maurer, ron, and maloney on exiting issues and phased const.
|
INSP - Wall cover | 3/25/1997 | 3/26/1997 | 3/25/1997 | A | PASS |
|
|
|
03/26/97 333 - INTERIOR WALLS FRAM-OK FRAMING
|
INSP - Wall cover | 2/25/1997 | 2/26/1997 | 2/25/1997 | A | PASS |
|
|
|
02/26/97 333 - EXTERIOR WALLS PENTHOUSE LEVEL ok
|
INSP - Wall cover | 2/13/1997 | 2/14/1997 | 2/14/1997 | A | PART |
|
|
|
02/14/97 333 - partial frame
|