INSP - Final | 1/15/1998 | 1/16/1998 | 1/16/1998 | A | PASS |
|
|
|
01/16/98 338 - ###-#### DELORES FNL -OK FINAL signed the occ req perm col
|
Permanent Occupancy | | 1/16/1998 | 1/16/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/14/1998 | 1/15/1998 | 1/15/1998 | A | PASS |
Joe Tawney
|
|
|
01/15/98 406 - ###-#### Linda ###-#### Dolores REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 12/18/1997 | 12/18/1997 | 12/19/1997 | P | FAIL |
Joe Tawney
|
|
|
12/18/97 406 - REINSP FOR FINAL FAIL SUPR SIGNAL EMERG LIGHTS PAINT CUR
|
INSP - Temporary occupancy | 12/5/1997 | 12/5/1997 | 12/8/1997 | P | PART |
|
|
|
12/05/97 338 - CHURCH ok for temp occ entire building perm to be ready o (wednsday
|
INSP - Final | 11/14/1997 | 11/17/1997 | 11/17/1997 | A | PART |
|
|
|
partial\\temp occ for the upper level only per Joe T. the fire guy
|
INSP - Final | 11/14/1997 | 11/14/1997 | 11/14/1997 | P | PART |
|
|
|
MADE OK FOR THE UPPER LEVEL ONLY PER JOE TAWNEY REQ
|
INSP-Final Inspection | 11/14/1997 | 11/14/1997 | 11/14/1997 | P | PART |
Joe Tawney
|
|
|
11/14/97 406 - partial OK FOR TEMP OCC OF 2ND FLOOR ONLY
|
INSP-Final Inspection | 11/12/1997 | 11/13/1997 | 11/13/1997 | P | FAIL |
Joe Tawney
|
|
|
11/13/97 406 - TEMP OCC. EARLY PM REINSP FOR FINAL 2ND FLR FAIL ALARM SYST & EMERG LIGHTING
|
INSP - Temporary occupancy | 11/12/1997 | 11/13/1997 | 11/12/1997 | P | PASS |
|
|
|
made ok signed the occ req card
|
INSP - Temporary occupancy | 11/10/1997 | 11/12/1997 | 11/12/1997 | P | CANC |
|
|
|
cancelled by the ctr.
|
INSP-Final Inspection | 11/10/1997 | 11/12/1997 | 11/12/1997 | A | FAIL |
Joe Tawney
|
|
|
11/12/97 406 - FINAL ON UPPER FLOOR FAIL ALARM SYSTEMS AND S/F DAMPERS &
|
INSP-Sprinkler Rough-in/Hydro | 11/10/1997 | 11/12/1997 | 11/12/1997 | A | PART |
Joe Tawney
|
|
|
11/12/97 406 - OK ON HYDRO TESTS FOR WET AND DRY SYSTEMS
|
INSP - Temporary occupancy | 11/10/1997 | 11/10/1997 | 11/10/1997 | P | CANC |
Tom Arcoraci
|
|
|
|
INSP-Final Inspection | 11/7/1997 | 11/10/1997 | 11/10/1997 | A | NR |
Joe Tawney
|
|
|
11/10/97 406 - 1 ST FLOOR FINAL ON 1ST FLOOR NOT READY
|
INSP - Temporary occupancy | 11/7/1997 | 11/7/1997 | 11/7/1997 | P | CANC |
|
|
|
AS LATE AS POSSIBLE/ FOR TOP FLOOR per contractor, he called kim
|
INSP - Framing/Rough-in | 10/21/1997 | 10/21/1997 | 10/21/1997 | P | PASS |
|
|
|
MADE OKiling
|
INSP - Framing/Rough-in | 10/10/1997 | 10/10/1997 | 10/10/1997 | P | NR |
|
|
|
10/10/97 338 - out of time
|
INSP - Framing/Rough-in | 8/29/1997 | 8/29/1997 | 8/29/1997 | P | PART |
|
|
|
08/29/97 338 - RE-INSPECTION OK TO FILL CONCEALED AREAS WITH INSULATION SPRINKLE
|
INSP - Framing/Rough-in | 8/28/1997 | 8/28/1997 | 8/28/1997 | P | NH |
|
|
|
/ / 338 - NO ONE ON SITE DONE BY 301
|
INSP-Conference | 8/26/1997 | 8/27/1997 | 8/27/1997 | P | PASS |
Joe Tawney
|
|
|
08/27/97 406 - CONF ON SPKLR COVERAGE & HANDRAILS IN BAPTISMAL FONT
|
INSP - Framing/Rough-in | 8/14/1997 | 8/15/1997 | 8/15/1997 | A | PART |
|
|
|
08/15/97 338 - FIRE WALL CEILING ok first layer
|
INSP-Sprinkler Rough-in/Hydro | 8/13/1997 | 8/14/1997 | 8/15/1997 | A | CANC |
Joe Tawney
|
|
|
08/14/97 406 - first layer of fire ceiling INSPECTION SHOULD BE FOR STRUCTURAL
|
INSP - Conference | 8/4/1997 | 8/5/1997 | 8/5/1997 | A | PASS |
|
|
|
08/05/97 338 - fire caulking and ceiling system
|
INSP - Resubmittals | 8/5/1997 | 8/5/1997 | 8/5/1997 | | PASS |
|
|
|
/ / 338 - approved doon ceiling assy
|
INSP - Foundation | 7/30/1997 | 7/31/1997 | 7/31/1997 | A | PASS |
|
|
|
07/31/97 338 - foundation wall inspectionmade ok with sp insp approval
|
INSP - Foundation | 7/29/1997 | 7/29/1997 | 7/29/1997 | P | PASS |
|
|
|
07/29/97 338 - made ok with sp insp
|
INSP - Conference | 7/25/1997 | 7/25/1997 | 7/25/1997 | | PASS |
|
|
|
/ / 338 - podium questions made them fill solid with insulation or spr
|
INSP - Framing/Rough-in | 7/24/1997 | 7/25/1997 | 7/25/1997 | A | PASS |
|
|
|
07/25/97 338 - the pulpit and platform area conf with sub ctr about req the insp.
|
INSP - Footings | 7/23/1997 | 7/24/1997 | 7/24/1997 | P | PASS |
|
|
|
07/24/97 338 - CONCRETE COL. ì
|
INSP - Foundation | 7/22/1997 | 7/22/1997 | 7/22/1997 | P | PART |
Tom Arcoraci
|
|
|
07/22/97 408 - special inspector on site report pending
|
INSP - Framing/Rough-in | 7/18/1997 | 7/18/1997 | 7/17/1997 | P | PART |
|
|
|
07/18/97 338 -
|
INSP-Sprinkler Rough-in/Hydro | 7/16/1997 | 7/17/1997 | 7/17/1997 | A | PART |
Joe Tawney
|
|
|
07/16/97 406 - UNDERGROUND FLUSH OK SPKLR ROUGH IN OK TO COVER EXCEPT IN JOIST AREAS.
|
INSP - Wall cover | 7/11/1997 | 7/14/1997 | 7/14/1997 | A | PASS |
|
|
|
07/14/97 338 - concrete walls this is to pour and backfill retaining wal ramps and stairs
|
INSP - Foundation | 7/9/1997 | 7/9/1997 | 7/9/1997 | P | PASS |
|
|
|
07/10/97 338 - FOUNDATION WALL RE-FORCEMENT MASN-REBAR OK
|
INSP - Footings | 7/8/1997 | 7/8/1997 | 7/8/1997 | P | PASS |
|
|
|
07/08/97 338 - FTG -OK FOOTING MASN-REBAR OK
|
INSP-Sprinkler Rough-in/Hydro | 6/23/1997 | 6/24/1997 | 6/24/1997 | A | PART |
Joe Tawney
|
|
|
CARMEN POLING - ###-#### ROUGH IN ON WET SYSTEM OK TO COVER
|
INSP - Foundation | 6/11/1997 | 6/12/1997 | 6/12/1997 | A | PASS |
|
|
|
06/12/97 338 - FND. WALL made ok with sp insp approval
|
INSP - Conference | 6/4/1997 | 6/5/1997 | 6/5/1997 | P | NR |
|
|
|
06/05/97 338 - no call from super to set appmt time will reschedule for
|
INSP - Foundation | 6/4/1997 | 6/5/1997 | 6/5/1997 | A | PASS |
|
|
|
06/05/97 338 - made ok with sp insp approval
|
INSP-Conference | 6/4/1997 | 6/5/1997 | 6/5/1997 | A | PASS |
Joe Tawney
|
|
|
06/05/97 406 - DISCUSSED EXIT SIGN LOCATION AND TOLD CONTRACTOR THAT ALA MAKE SUBMITTAL ON SYSTEM
|
INSP - Conference | 6/3/1997 | 6/3/1997 | 6/3/1997 | | PASS |
|
|
|
/ / 338 - conf with plan review on the ele vator shaft
|
INSP - Framing/ Rough-in | 6/3/1997 | 6/3/1997 | 6/3/1997 | | PASS |
|
|
|
/ / 338 - floor framing
|
INSP - Framing/Rough-in | 6/3/1997 | 6/3/1997 | 6/3/1997 | P | CANC |
|
|
|
06/03/97 338 - postponed til 06-04-97
|
INSP - Conference | 5/16/1997 | 5/16/1997 | 5/16/1997 | | PASS |
|
|
|
/ / 338 - met with arch on the fire rated construction etc
|
INSP - Footings | 5/16/1997 | 5/16/1997 | 5/16/1997 | P | PASS |
|
|
|
05/16/97 338 - made ok r-bar placed sp insp made ok
|
INSP - Framing/Rough-in | 5/15/1997 | 5/16/1997 | 5/16/1997 | A | NR |
|
|
|
05/16/97 338 - misc rated wall questions only
|
INSP - Carpentry | 5/14/1997 | 5/15/1997 | 5/15/1997 | A | PASS |
|
|
|
05/15/97 338 - misc framing questions
|
INSP - Conference | 5/15/1997 | 5/15/1997 | 5/15/1997 | | PASS |
|
|
|
/ / 338 - with Wayne thallus on rated doors said planreview ok,d dors jambs per1949 code ???
|
INSP - Foundation | 5/14/1997 | 5/14/1997 | 5/13/1997 | P | FAIL |
|
|
|
05/14/97 338 - r-bar placed sp insp on site pouring grout sand/cement m required
|
INSP - Conference | 4/18/1997 | 4/18/1997 | 4/18/1997 | P | PASS |
|
|
|
04/18/97 338 -
|
INSP - Foundation | 4/17/1997 | 4/17/1997 | 4/17/1997 | P | PASS |
|
|
|
04/17/97 338 - REBAR FOR RETAINING WALL FDN -OK FOUNDATION
|
INSP - Footings | 4/14/1997 | 4/14/1997 | 4/14/1997 | P | PASS |
|
|
|
04/14/97 338 - REBAR FOR A RAMP MADE OK
|
INSP - Flatwork | 3/20/1997 | 3/20/1997 | 3/19/1997 | P | PASS |
|
|
|
03/20/97 338 - SLAB -- WIRE MESH insp not required
|
INSP - Footings | 3/17/1997 | 3/18/1997 | 3/17/1997 | A | PASS |
|
|
|
03/18/97 338 - MADE OK WITH SP INSP APPROVAL
|
INSP - Footings | 3/13/1997 | 3/14/1997 | 3/12/1997 | A | NR |
|
|
|
03/14/97 338 - LATE A.M.
|
INSP - Foundation | 3/6/1997 | 3/7/1997 | 3/5/1997 | A | PASS |
|
|
|
03/07/97 338 - arch will confirm the verbal corrections ok t5o pour with
|
INSP - Footings | 2/24/1997 | 2/25/1997 | 2/25/1997 | A | PASS |
|
|
|
02/25/97 338 - r-bar placed FTG -OK FOOTING
|
INSP - Footings | 2/24/1997 | 2/24/1997 | 2/24/1997 | P | NR |
|
|
|
02/24/97 338 -
|
INSP - Foundation | 1/30/1997 | 1/30/1997 | 1/29/1997 | P | PASS |
|
|
|
01/30/97 338 - to recieve letter from the arch on plaacement of reinforc penetrations
|
INSP - Foundation | 1/21/1997 | 1/21/1997 | 1/20/1997 | P | PASS |
|
|
|
01/21/97 338 - ARCH INSP MADE OK
|
INSP - Footings | 1/15/1997 | 1/15/1997 | 1/15/1997 | P | PASS |
|
|
|
01/15/97 338 - EARLY PM made ook weather pro and r-bar placxede also ins
|
INSP - Foundation | 1/13/1997 | 1/14/1997 | 1/14/1997 | A | PASS |
|
|
|
01/14/97 338 - WEARHR PRO AND R-BAR ARE IN PLACE
|
INSP - Footings | 1/10/1997 | 1/13/1997 | 1/13/1997 | A | NR |
|
|
|
01/13/97 338 - footing rebar NOT READY
|
INSP - Footings | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
|
|
|
/ / 338 - FTG -OK FOOTING
|
INSP - Foundation | 1/8/1997 | 1/9/1997 | 1/9/1997 | A | NR |
|
|
|
01/08/97 338 - not ready cancell till tomorrow by the contractor he must
|