Permanent Occupancy | | 5/28/1997 | 5/28/1997 | | DONE |
|
|
|
|
INSP - Final | 5/12/1997 | 5/12/1997 | 5/12/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC
|
INSP - Final | 5/9/1997 | 5/12/1997 | 5/11/1997 | A | PART |
|
|
|
05/12/97 338 - verbal c/n for the main structure need approved ramp for need ele signoff for the pump canopy OTH-OTHER AGENCIES NOT APPROVED ok for temp occ only signed the temp col the occ rec form
|
INSP-Final Inspection | 5/8/1997 | 5/9/1997 | 5/9/1997 | A | FAIL |
Joe Tawney
|
|
|
05/09/97 406 - FINAL FAIL MAN FLUSH BOLTS EMERG LIGHT WIRING LANDING AT INST & TEST OF SMOKE DET IN AC UNIT
|
INSP - Framing/Rough-in | 4/3/1997 | 4/4/1997 | 4/4/1997 | A | PASS |
Carl Dependahl
|
|
|
04/04/97 340 - FRAME REINSPECT, C/N OK
|
INSP - Conference | 4/3/1997 | 4/3/1997 | 4/3/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - W/ CONT RE C/N OF 4-3-97
|
INSP - Framing/Rough-in | 4/2/1997 | 4/3/1997 | 4/3/1997 | A | FAIL |
Carl Dependahl
|
|
|
04/03/97 340 - C/N, NEED HD BOLTS, FIREBLOCKS. OK TO INS
|
INSP - Framing/Rough-in | 4/2/1997 | 4/2/1997 | 4/1/1997 | P | NR |
|
|
|
04/02/97 338 - not ready OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Foundation | 3/7/1997 | 3/7/1997 | 3/5/1997 | P | PASS |
|
|
|
03/07/97 338 - FDN -OK FOUNDATION
|
INSP - Footings | 3/5/1997 | 3/6/1997 | 3/5/1997 | A | PASS |
|
|
|
03/06/97 338 - JACKSON'S FOOD STORES FTG -OK FOOTING
|
INSP - Misc. complaint | 10/14/1996 | 10/15/1996 | 10/15/1996 | A | PASS |
|
|
|
10/15/96 338 - PERMIT NOT PICKED UP. CHECK OUT. did this the other day
|
INSP - Stop Work Order | 10/10/1996 | 10/11/1996 | 10/11/1996 | A | PASS |
|
|
|
10/11/96 338 - THEY HAVE NOT PICKED UP OR PAID FOR THIS PERMIT. THERE HA MECHANICAL INSPECTIONS DONE. DIX there has been no work as of this time that should be retained against t permit # they have decided to wait until spring to do the work.
|