INSP - Final | 5/2/1997 | 5/5/1997 | 5/5/1997 | A | PASS |
Jim Sly
|
|
|
05/02/97 316 - OK
|
INSP - Final | 5/2/1997 | 5/2/1997 | 5/2/1997 | P | NH |
Jim Sly
|
|
|
05/02/97 316 - Reinspect No one or occup card on site.....
|
INSP - Final | 3/31/1997 | 4/1/1997 | 4/1/1997 | P | CANC |
Jim Sly
|
|
|
04/01/97 316 - Builder Cancelled
|
INSP - Final | 3/31/1997 | 3/31/1997 | 3/31/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC
|
INSP - Final | 1/27/1997 | 1/28/1997 | 1/28/1997 | P | PART |
Jim Sly
|
|
|
01/28/97 316 - C/N...Repair draftstop, fireblk, weatherstrip crawlspace Temp. Occ.
|
INSP - Final | 1/27/1997 | 1/28/1997 | 1/28/1997 | A | PART |
Joe Tawney
|
|
|
OK FOR TEMP OCC EMERG LIGHTS IN BOTH STAIRWELLS RELOCATE FIRE HYD TO ENTRANCE ON MCMILLAN 911 SIGN ON BELL STRIPE AND SIGN CURBS TO MAINTAIN FIRE LANES
|
INSP-Sprinkler Rough-in/Hydro | 1/24/1997 | 1/27/1997 | 1/27/1997 | A | PASS |
|
|
|
BOB - ###-#### ug hydro, fdc hydro, wet & dry pipe sys hydro. Looks like dry pipe is less than 500 gal so no trip test required. no accelerator either.
|
INSP-Supply line flush | 1/21/1997 | 1/21/1997 | 1/21/1997 | | PASS |
|
|
|
OK ON UNDERGROUND SUPPLY LINE FLUSH
|
INSP - Ceiling grid | 1/16/1997 | 1/17/1997 | 1/17/1997 | A | PASS |
Jim Sly
|
|
|
01/16/97 316 - OK
|
INSP-Sprinkler Rough-in/Hydro | 1/16/1997 | 1/16/1997 | 1/16/1997 | | PASS |
|
|
|
OK TO COVER ALL SPKLR PIPING
|
INSP - Temporary occupancy | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
|
|
|
Art Y. insp. for temp. occ - Bonded for Undrgrd Sprklr/landscaping/tsh encl @ $24,596.00
|
INSP-Sprinkler Rough-in/Hydro | 12/30/1996 | 12/30/1996 | 12/30/1996 | | PASS |
Joe Tawney
|
|
|
/ / 406 - OK TO COVER DRY SYSTEM IN OVERHEAD ROOF AREA
|
INSP-Sprinkler Rough-in/Hydro | 12/24/1996 | 12/26/1996 | 12/26/1996 | A | FAIL |
Joe Tawney
|
|
|
12/26/96 406 - ROUGH IN INSP OF ATTIC DRY SYSTEM FAILED RELOCATE ONE HEAD ADD HEADS AT FIRE STOP UNCOVER OR ADD HEADS AT ROOF HIPS ON EAST & WEST SIDES OF BLDG
|
INSP-Sprinkler Rough-in/Hydro | 12/23/1996 | 12/24/1996 | 12/24/1996 | A | CANC |
|
|
|
12/24/96 40Y - INSP CANCELLED TO BE RESCHED FOR 11/26/96
|
INSP - Framing/Rough-in | 12/23/1996 | 12/23/1996 | 12/23/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - Inspection of all chases for fireblock.
|
INSP - Framing/Rough-in | 12/19/1996 | 12/20/1996 | 12/20/1996 | A | PART |
Jim Sly
|
|
|
12/19/96 316 - Inspection of exterior walls and partition walls for cove inspection of chase fireblocking and drafstop...Part.
|
INSP - Framing/Rough-in | 12/17/1996 | 12/17/1996 | 12/17/1996 | P | NR |
Jim Sly
|
|
|
12/17/96 316 - C/N Misc fireblock, truss, and trade rough in insp....
|
INSP - Conference | 12/13/1996 | 12/13/1996 | 12/13/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - Review truss engineering.
|
INSP - Carpentry | 12/9/1996 | 12/10/1996 | 12/10/1996 | A | PART |
Jim Sly
|
|
|
12/09/96 316 - WALL COVER IN BASEMENT...OK to insulate.
|
INSP - Conference | 12/9/1996 | 12/9/1996 | 12/9/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - Partial frame insp for basment....walk thru main floor.
|
INSP - Wall cover | 12/2/1996 | 12/2/1996 | 12/2/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - Roof Nailing ...Sheathing OK.
|
INSP - Footings | 10/23/1996 | 10/24/1996 | 10/24/1996 | A | PASS |
Jim Sly
|
|
|
10/23/96 316 - Interior Footings...OK.
|
INSP - Footings | 10/18/1996 | 10/21/1996 | 10/21/1996 | A | PASS |
Jim Sly
|
|
|
10/18/96 316 - Footings OK pending special insp OK.
|
INSP - Foundation | 10/9/1996 | 10/10/1996 | 10/10/1996 | A | PASS |
Jim Sly
|
|
|
10/09/96 316 - BASEMENT Foundation OK pending special inspection OK.
|
INSP - Footings | 10/8/1996 | 10/8/1996 | 10/8/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - OK...Pending special inspection OK.
|
INSP - Footings | 10/7/1996 | 10/7/1996 | 10/7/1996 | P | PASS |
Jim Sly
|
|
|
Footings OK pending approval Special Inspection.
|
INSP - Site Preparation | 10/3/1996 | 10/3/1996 | 10/3/1996 | P | PASS |
Jim Sly
|
|
|
10/03/96 316 - OK pending special inspector soil reports.
|