Permanent Occupancy | | 4/11/1997 | 4/11/1997 | | DONE |
|
|
|
|
INSP - Final | 3/24/1997 | 3/24/1997 | 3/24/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - FINAL REINSP OK FOR PERM OCC
|
INSP - Final | 3/20/1997 | 3/20/1997 | 3/20/1997 | P | NR |
Joe Tawney
|
|
|
03/20/97 406 - 3 p.m. NOT READY FOR INSPECTION
|
INSP - Final | 3/21/1997 | 3/21/1997 | 3/19/1997 | P | FAIL |
|
|
|
03/21/97 338 - OTH-OTHER AGENCIES NOT APPROVED fire & p/z required
|
INSP-Sprinkler Rough-in/Hydro | 3/17/1997 | 3/19/1997 | 3/19/1997 | P | NR |
Joe Tawney
|
|
|
03/19/97 406 - FINAL INSP NOT READY
|
INSP-Sprinkler Rough-in/Hydro | 3/17/1997 | 3/17/1997 | 3/17/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR HYDRO TEST
|
INSP - Conference | 3/13/1997 | 3/13/1997 | 3/13/1997 | P | PASS |
Joe Tawney
|
|
|
03/13/97 406 - DAN ###-#### PRE FINAL CONF DISCUSSED EXITS, SIGNS,HDWRE, EXTINGUISHERS. ALSO EMERG LIGHTS NOTED FDC TOO CLOSE TO WALL MTD CONTROL VLV
|
INSP - Conference | 3/12/1997 | 3/13/1997 | 3/12/1997 | P | PASS |
|
|
|
03/13/97 338 - made ok
|
INSP-Supply line flush | 2/27/1997 | 2/28/1997 | 2/28/1997 | A | PART |
Joe Tawney
|
|
|
02/28/97 406 - OK ON UNDERGROUND FLUSH
|
INSP - Framing/ Rough-in | 2/19/1997 | 2/19/1997 | 2/19/1997 | | NR |
|
|
|
/ / 338 - str is ok but ele and plmg ae not signed off
|
INSP - Framing/Rough-in | 2/19/1997 | 2/19/1997 | 2/19/1997 | P | NR |
|
|
|
02/19/97 338 - rescheduled til tomorrow a.m.
|
INSP - Framing/Rough-in | 1/24/1997 | 1/27/1997 | 1/26/1997 | A | PASS |
|
|
|
01/27/97 338 - ROOF FRAMING FOR THE SECOND FLOORING MADE OK STILL PUD DECK CONNECTIONS
|
INSP - Conference | 1/26/1997 | 1/26/1997 | 1/26/1997 | | NR |
|
|
|
/ / 338 - NOT READY CALLED TO POST PONE THE INSP
|
INSP - Flatwork | 1/2/1997 | 1/3/1997 | 1/1/1997 | A | PASS |
|
|
|
01/03/97 338 - PANEL ERRECTIONS making good progress with special inspec
|
INSP - Masonry | 12/16/1996 | 12/16/1996 | 12/16/1996 | P | PASS |
|
|
|
12/16/96 333 - CONCRETE INSP...PANELS #24 - 25 - 2I6 & 4 STRUCTURAL COLUMNS....... special insp ok
|
INSP - Wall cover | 12/11/1996 | 12/12/1996 | 12/12/1996 | A | PASS |
|
|
|
12/12/96 338 - STRUC. CONCRETE/PANEL 27,28,31,32,33,34,35, special insp
|
INSP - Masonry | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
|
|
|
11/25/96 338 - STRUCTURAL PANEL 13 THRU 23
|
INSP - Flatwork | 11/12/1996 | 11/13/1996 | 11/13/1996 | A | PASS |
|
|
|
11/13/96 338 - WALL PANELS 1 THRU 12
|
INSP - Footings | 10/22/1996 | 10/22/1996 | 10/22/1996 | P | PASS |
|
|
|
10/22/96 338 - madeok r-bar placed in the first 3/4 of the footing area. special insp continuous during the pour
|
INSP - Footings | 10/18/1996 | 10/18/1996 | 10/21/1996 | A | NR |
|
|
|
10/18/96 338 -
|
INSP - Conference | 10/14/1996 | 10/15/1996 | 10/15/1996 | A | PASS |
|
|
|
10/15/96 338 - APPROX 9AM? (BRIAN AT ###-####)
|