INSP - Letter of compliance | | | 12/19/1996 | | PASS |
|
|
|
ISSUED #12384 C OF C BY 301 THIS DATE.
|
INSP - Final | 12/18/1996 | 12/18/1996 | 12/18/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL
|
INSP - Final | 12/17/1996 | 12/18/1996 | 12/18/1996 | P | PASS |
|
|
|
|
INSP - Fire Dept. Request | 12/6/1996 | 12/6/1996 | 12/6/1996 | | PASS |
|
|
|
/ / 405 - sprinkler relo rough in
|
INSP - Framing/Rough-in | 11/25/1996 | 11/26/1996 | 11/26/1996 | A | NR |
Jim Storey
|
|
|
11/25/96 301 - OTH-OTHER AGENCIES NOT APPROVED ele n/r
|
INSP - Framing/Rough-in | 11/12/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Jim Storey
|
|
|
11/12/96 301 - FRAM-OK FRAMING Fweld & STRUCTURAL WELDING ok 1/4 bo plates
|
INSP - Foundation | 10/21/1996 | 10/22/1996 | 10/22/1996 | A | PASS |
Jim Storey
|
|
|
10/21/96 301 - FND.REBAR. GATE 54..EARLY A.M. FDN -OK FOUNDATION
|
INSP - Footings | 10/18/1996 | 10/18/1996 | 10/18/1996 | P | PEND |
Jim Storey
|
|
|
MAKE A U-TURN BY TOWER AND YOU WILL BE THERE PENDING S.I. REPORT
|
INSP - Conference | 10/11/1996 | 10/14/1996 | 10/14/1996 | A | PASS |
Jim Storey
|
|
|
10/12/96 301 - PRE-CONSTRUCTION INSPECTION GEN -GENERAL INSPECTION WORK ON EXAVATION IN PROGESS
|