INSP - Final | 7/30/1997 | 7/30/1997 | 7/30/1997 | P | PASS |
Bob Archibald
|
|
|
cn made ok
|
Permanent Occupancy | | 7/30/1997 | 7/30/1997 | | DONE |
|
|
|
|
INSP - Final | 7/24/1997 | 7/25/1997 | 7/25/1997 | A | FAIL |
Jim Storey
|
|
|
07/25/97 301 - c/n pending for occ. doors in gym
|
INSP-Final Inspection | 7/7/1997 | 7/10/1997 | 7/10/1997 | A | FAIL |
|
|
|
alarms still not zoned , air pressure monitor not wired correctly
|
INSP - Conference | 7/8/1997 | 7/8/1997 | 7/8/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - dead bolts on exit doors of restrooms approved by state of i and as per architect drawings in spec. book submitted.
|
INSP-Sprinkler Rough-in/Hydro | 7/1/1997 | 7/2/1997 | 7/2/1997 | A | PASS |
Joe Tawney
|
|
|
07/01/97 406 - AT 9 A.M. WITNESTED TRIP TESTS OF 2 DP SYSTEMS AFTER SPLIT OF 1 SYST EACH SYST NOW LESS THAN 750 GAL. ALSO PICKED UP REVISED PLANS AND REV CA
|
INSP-Final Inspection | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | FAIL |
|
|
|
TIME GOT WORSE, 1:30 TO 2:00.....ALARMS STILL NOT COMPLETE
|
INSP-Final Inspection | 6/13/1997 | 6/13/1997 | 6/13/1997 | P | FAIL |
|
|
|
sprinklers failed 60 sec test (75). alll signals are alarm, low air not set, need as builts for docs
|
INSP - Conference | 6/10/1997 | 6/10/1997 | 6/10/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - NWP -GENERAL INSPECTION - NO WORK IN PROGRESS
|
INSP-Sprinkler Rough-in/Hydro | 6/6/1997 | 6/6/1997 | 6/6/1997 | P | PASS |
|
|
|
HYDRO on above ground
|
INSP-Conference | 4/15/1997 | 4/15/1997 | 4/15/1997 | A | PASS |
|
|
|
meet w/ power plus, TED, DISCUSSED DUCT DETECTOR LOCATIONS, TOLD REMOTE INDICATORS WILL BE REQUIRED, TOLD TO MOVE SMOKE DETECTORS TO WITHIN 5 FT OF DOORS ON HOLD OPENS. LOOKED AT PLANS, TOLD WILL NEED AS BUILTS WITH ALL CALCULATIONS FOR FINAL
|
INSP-Sprinkler Rough-in/Hydro | 4/2/1997 | 4/3/1997 | 4/3/1997 | A | PART |
|
|
|
underground hydro ok
|
INSP-Supply line flush | 4/2/1997 | 4/3/1997 | 4/3/1997 | A | PASS |
|
|
|
8:30 am, FEW ROCKS, FAIRLY CLEAN, GOOD FLOW
|
INSP-Sprinkler Rough-in/Hydro | 3/27/1997 | 3/27/1997 | 3/27/1997 | A | PART |
|
|
|
hallway coverage, overbuilds along halls completed, media center complete, only place lacking is overbuilds at each corner of meia center away from gym
|
INSP-Conference | 3/21/1997 | 3/21/1997 | 3/21/1997 | A | PART |
|
|
|
phone conf w/ gus, CM. Mel Fletcher wants ceiling space above halls sprinkled since actual gap is 8" instead of 6" in many places. Will discuss w/ Fetcher. Plans called for 6" but sprinkler main and ML beams forced to 8".
|
INSP - Ceiling grid | 3/18/1997 | 3/19/1997 | 3/19/1997 | A | PART |
Jim Storey
|
|
|
03/19/97 301 - SCLG-OK SUSPENDED CEILING
|
INSP-Sprinkler Rough-in/Hydro | 3/19/1997 | 3/18/1997 | 3/18/1997 | P | PASS |
|
|
|
approved plan to sprinkle exposed comb const above media center w/ heads along walls only
|
INSP-Sprinkler Rough-in/Hydro | 3/17/1997 | 3/17/1997 | 3/17/1997 | A | PASS |
|
|
|
check media center exposed combustible construction, concealed space, need to extend foil wrap or sprinkle. hall lid ok using 96 nfpa 13 w/ new exceptions
|
INSP - Ceiling grid | 3/10/1997 | 3/11/1997 | 3/11/1997 | A | PART |
Jim Storey
|
|
|
03/11/97 301 - SCLG-OK SUSPENDED CEILING south wing
|
INSP-Sprinkler Rough-in/Hydro | 2/19/1997 | 2/20/1997 | 2/20/1997 | A | PART |
|
|
|
issued c/n on MECHANICAL SPACE ABOVE KITCHEN. and RISER Access issues
|
INSP-Conference | 2/14/1997 | 2/14/1997 | 2/14/1997 | P | PART |
|
|
|
CONF ON RISER LOCATION OPTIONS
|
INSP-Sprinkler Rough-in/Hydro | 2/12/1997 | 2/13/1997 | 2/13/1997 | A | PART |
|
|
|
ROUGH IN CAFETERIA AND GYM, PROBLEM WITH RISER ROOM LOCATION
|
INSP - Framing/Rough-in | 1/29/1997 | 1/30/1997 | 1/30/1997 | A | PASS |
Jim Storey
|
|
|
01/30/97 301 - FRAM-OK FRAMING OCC SEPECTION
|
INSP-Sprinkler Rough-in/Hydro | 1/24/1997 | 1/28/1997 | 1/29/1997 | P | PART |
|
|
|
AREAS E & F ok to cover 1st floor w/ conditions for access to areas not complete...c/n with condition noted
|
INSP - Framing/Rough-in | 1/17/1997 | 1/21/1997 | 1/21/1997 | A | PASS |
Jim Storey
|
|
|
01/21/97 301 - C WING OK
|
INSP - Wall cover | 1/15/1997 | 1/15/1997 | 1/15/1997 | P | PASS |
Jim Storey
|
|
|
01/15/97 301 - roof nailling at gym roof and fire rated ply in place as
|
INSP - Framing/Rough-in | 1/8/1997 | 1/9/1997 | 1/9/1997 | A | PART |
Jim Storey
|
|
|
01/09/97 301 - conf. re insp. for 1/10/97
|
INSP - Roof | 1/2/1997 | 1/3/1997 | 1/3/1997 | A | PART |
Wes Worcester
|
|
|
will finish this pm
|
INSP - Roof | 12/31/1996 | 12/31/1996 | 12/31/1996 | A | PART |
Wes Worcester
|
|
|
East and Northeast roof sections ok
|
INSP - Roof | 12/30/1996 | 12/30/1996 | 12/30/1996 | P | NR |
Wes Worcester
|
|
|
still putting on roof....will walk Tues am
|
INSP - Roof | 12/27/1996 | 12/30/1996 | 12/30/1996 | A | NR |
Wes Worcester
|
|
|
ROOF NAILING said he called for pm....will reschedule
|
INSP - Conference | 11/22/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
Wes Worcester
|
|
|
picked up address and permit #
|
INSP - Conference | 11/21/1996 | 11/21/1900 | 11/21/1996 | | FAIL |
|
|
|
conference w/Bob & George @ earlier conversation w/Gus
|
INSP - Conference | 11/14/1996 | 11/14/1996 | 11/14/1996 | | FAIL |
|
|
|
super had stated that he would call in w/approximate time and place for next lift and a conference for coordination
|
INSP - Conference | 11/12/1996 | 11/12/1996 | 11/12/1996 | | PART |
|
|
|
stopped in again to get on scheduled lifts and so we could make computer entries to coincide w/progress
|
INSP - Masonry | 11/6/1996 | 11/6/1996 | 11/6/1996 | | NR |
|
|
|
stopped by to look at project, not plaving grout at that time, asked super to call in for conference.
|
INSP - Flatwork | 10/28/1996 | 10/28/1996 | 10/28/1996 | | FAIL |
|
|
|
notified super that mesh was not being imbedded in concrete. Special insp was reg'd according to super as pour was 3000 + concrete
|
INSP - Conference | 10/15/1996 | 10/15/1996 | 10/15/1996 | | PASS |
|
|
|
/ / 405 - issued letter on requirements
|
INSP - Conference | 10/14/1996 | 10/14/1996 | 10/14/1996 | | PASS |
|
|
|
/ / 405 - discussed alarm and sprinkler requirements for project
|
INSP-Final Inspection | 7/24/1997 | 7/24/1997 | 7/24/1996 | A | PASS |
|
|
|
alarms completed-main bldg
|