Permit Information
Permit NumberBLD96-02302
StatusFinaled
Name ST. ALPHONSUS MED. OFF.BLD.#5
Site Address 900 N LIBERTY
Project NameST ALS OFFICE #5
Customer Number 
ePlanReviewNo
Description
( ST. ALPHONSUS MEDICAL OFFICE BUILDING #5 - SHELL AND CORE ) TO CONSTRUCT A NEW 57,540 SQ. FT., FOUR STORY, STEEL FRAMED OFFICE BUILDING WITH CONCRETE FLOOR DECKS AND METAL STUD EXTERIOR WALLS WITH EXTERIOR INSULATION FINISH SYSTEM. THIS BUILDING WILL BE FULLY FIRE SPRINKLED. THIS PERMIT IS TO COMPLETE THE SHELL AND CORE ONLY. THERE WILL BE NO OCCUPANCY PERMITTED UNDER THIS PERMIT. SEPARATE TENANT IMPROVEMENT PERMITS WILL BE REQUIRED TO FINISH THIS BUILDING. THIS PERMIT WILL ALSO INCLUDE RELATED SITE IMPROVEMENTS. ALL CONSTRUTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR#97-96/CU#-51-96/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final11/16/199811/17/199811/17/1998APASS
Details
11/17/98 338 - MADE OK L/C ISSUED # 015891
INSP - Final11/17/199811/17/199811/17/1998 PASS
Details
/ / 338 - MADE OK FOR FINAL, SIGNED THE PERM COL OF THE OCC REQ CARD A
INSP - Final11/17/199811/17/199811/17/1998 PASS
Details
/ / 338 - MADE OK FOR FINAL, SIGNED THE PERM COL OF THE OCC REQ CARD A
INSP-Final Inspection11/16/199811/16/199811/16/1998PPASS
DetailsJoe Tawney
11/16/98 406 - ###-#### cecil sched. at 1:30 REINSP OK FOR CERT OF COMPL ON SHELL
INSP-Final Inspection10/29/199810/29/199810/29/1998 FAIL
DetailsJoe Tawney
10/29/98 406 - CECIL- ###-#### FN FIRE-PER JOE WILL MEET AT 8 REINSP FAIL ALARM SYSTEM PACKAGE & NFPA 72
INSP - Occup. violation notice10/12/199810/12/199810/12/1998 FAIL
Details
/ / 338 - RECIEVED BY FRED A HOWE FOR KREISENBECK CECIL CALLED LATER T
INSP - Final11/6/199711/6/199711/6/1997PPART
Details
11/06/97 333 - temp ok
INSP-Final Inspection11/5/199711/6/199711/6/1997APART
DetailsJoe Tawney
11/06/97 406 - REIN OK FOR TEMP OCC ON SHELL ALARM SUBMITTAL FRT ELEVATOR GEN TIME DELAY
INSP-Final Inspection11/3/199711/4/199711/4/1997PFAIL
DetailsJoe Tawney
11/04/97 406 - FINAL NOT COMPLETED RESUME 11/5/97
INSP-Final Inspection10/28/199710/30/199710/30/1997ANR
DetailsJoe Tawney
10/30/97 406 - FINAL NOT READY DIG DIALER NOT INSTALLED
INSP - Framing/Rough-in10/23/199710/24/199710/24/1997PPART
Details
CEILING GRID made ok
INSP - Framing/Rough-in10/17/199710/20/199710/20/1997APART
Details
CEILING GRID AND FIRE PENETRATION verbal corrections written down on the on prelim punch lists.
INSP-Sprinkler Rough-in/Hydro10/2/199710/2/199710/2/1997PPART
DetailsJoe Tawney
10/02/97 406 - st. als/ bld #5 OK ON HYDRO TEST FOR SPKLR SYSTEM STILL NEED HYDRO TEST ON STANDPIPES
INSP - Conference9/3/19979/3/19979/3/1997 PASS
Details
/ / 338 - ok to use 2'-8" door from the first floor lobby to the north a required exit door will be market NOT AN EXIT
INSP - Footings8/12/19978/12/19978/11/1997PPASS
Details
08/12/97 338 -
INSP-Supply line flush7/23/19977/24/19977/24/1997APART
DetailsJoe Tawney
07/24/97 406 - SUPPLY LINE FLUSH AT 11 A.M. OK ON UNDERGROUND FLUSH
INSP - Conference7/21/19977/21/19977/21/1997 PASS
Details
/ / 338 - 2-hr shaft
INSP - Framing/Rough-in7/18/19977/21/19977/21/1997PPART
Details
07/22/97 338 - madeok partial 2-hr shaft
INSP-Supply line flush7/17/19977/21/19977/21/1997ANR
DetailsJoe Tawney
07/21/97 406 - HE called you and set up an appt for 11 am UNDERGROUND FLUSH NOT READY
INSP - Framing/Rough-in7/11/19977/11/19977/14/1997PCANC
DetailsTom Arcoraci
bld #5
INSP - Framing/Rough-in7/11/19977/11/19977/11/1997 PART
Details
07/14/97 333 - 1hr at stairs ok to cover
INSP - Framing/Rough-in7/7/19977/7/19977/7/1997PFAIL
Details
07/07/97 338 - c/n misc drywall problems in the shaft wall systems they
INSP - Framing/Rough-in6/27/19976/30/19977/1/1997APASS
Details
06/30/97 338 - Nacho??? (i think)###-#### mice frame to this point ok pager
INSP - Framing/Rough-in6/20/19976/23/19976/23/1997APART
Details
06/23/97 338 - partial at the ele core and the stair cores mise perimete
INSP - Framing/Rough-in6/9/19976/9/19976/9/1997PPASS
Details
06/09/97 338 - misc framing to this point is ok in the core area misc st
INSP - Miscellaneous6/9/19976/9/19976/9/1997 PASS
Details
/ / 338 - resubmittals on the shell and main core areas
INSP - Carpentry5/30/19975/30/19975/30/1997PPASS
Details
05/30/97 338 -
INSP - Conference5/30/19975/30/19975/30/1997 PASS
Details
/ / 338 - must follow the approved plan with the fireblocking in the w in the north srairwell no execptions
INSP - Conference5/30/19975/30/19975/30/1997 PASS
Details
/ / 338 - must follow the approved plan with the fireblocking in the w in the north srairwell no execptions
INSP - Framing/Rough-in5/28/19975/29/19975/29/1997APART
Details
05/29/97 338 - partial framing north stairwell framing questions at the
INSP - Framing/Rough-in5/23/19975/27/19975/27/1997ANR
Details
05/27/97 338 - partial framing 1st floor core area not ready for cover
INSP - Carpentry5/5/19975/6/19975/6/1997APASS
Details
05/06/97 338 -
INSP - Conference5/1/19975/5/19975/5/1997APASS
Details
05/05/97 338 - ###-####
INSP - Conference3/19/19973/19/19973/18/1997PPASS
Details
03/19/97 338 - CONF ON FRAMING ok to but 1-side drywall at the bottom of fire caulk seal in the anular space will field verify.
INSP - Conference3/7/19973/10/19973/9/1997APART
Details
03/10/97 338 - on the fire proofing
INSP - Masonry2/14/19972/14/19972/14/1997PPASS
Details
02/14/97 338 - 3RD FLOOR POUR. READY TO POUR ON MONDAY WEATHER PRO IN PL INSP
INSP - Conference2/5/19972/5/19972/6/1997 PASS
Details
02/05/97 338 - made ok
INSP - Conference2/5/19972/5/19972/5/1997PPASS
Details
02/05/97 338 - made ok sp insp made ok weather pro in place
INSP - Flatwork1/27/19971/28/19971/28/1997APASS
Details
01/28/97 338 - 2ND FLR.POUR made ok 2nd half
INSP - Masonry1/24/19971/27/19971/26/1997APASS
Details
01/27/97 338 - POURING 2ND FLR DECK. (I DIDN'T KNOW WHAT TO PUT THIS UN GAVE OK TO POUR 2ND HALF OF THIS DECK WITH THE SPEC INSP BLESSING
INSP - Foundation1/16/19971/17/19971/17/1997APASS
Details
01/17/97 338 - fnd.rebar made ok wp in place
INSP - Foundation1/14/19971/15/19971/16/1997PPASS
Details
01/16/97 338 - WILL POUR IN THE AM south west at the dock
INSP - Conference1/13/19971/13/19971/13/1997 PASS
Details
/ / 338 - DETAILS C3&C4 ON A7.0 SHAFT WALL DETAILS THERE IS NO DETAIL SHAFT
INSP - Foundation12/10/199612/10/199612/10/1996 PASS
Details
/ / 338 - made ok by 316
INSP - Footings12/6/199612/9/199612/9/1996APASS
Details
12/09/96 338 - FOOTING REBAR r-bar placed weather prot ok
INSP - Foundation12/3/199612/4/199612/4/1996PPASS
Details
12/04/96 338 - REBAR r-bar placed spec insp made ok
INSP - Footings11/26/199611/27/199611/27/1996PPASS
Details
11/27/96 338 - footing rebar early pm SPEC INSP MADE OK
INSP - Foundation11/21/199611/22/199611/22/1996APASS
Details
RE-BAR FOOTING/FOUNDATION/ placed made ok spec insp
INSP - Footings11/14/199611/18/199611/19/1996PPASS
Details
11/19/96 338 - SPECIAL INSP MADE OK
INSP - Foundation11/12/199611/13/199611/13/1996APASS
Details
11/13/96 338 - ok to pour with the special insp blessing
INSP - Conference11/5/199611/6/199611/6/1996APASS
Details
11/06/96 338 - STARTING PROJECT. LOOKS GOOD WILL SCHEDULE PRE JOB CONFERENCE WHEN THE SUBS ARE ALL HIRED
INSP - Footings11/7/199611/8/19961/3/1980APASS
Details
11/08/96 338 - LATE A.M. FORMS SET R-BAR PLACED OK BY SPECIAL INSP