INSP - Final | 11/16/1998 | 11/17/1998 | 11/17/1998 | A | PASS |
|
|
|
11/17/98 338 - MADE OK L/C ISSUED # 015891
|
INSP - Final | 11/17/1998 | 11/17/1998 | 11/17/1998 | | PASS |
|
|
|
/ / 338 - MADE OK FOR FINAL, SIGNED THE PERM COL OF THE OCC REQ CARD A
|
INSP - Final | 11/17/1998 | 11/17/1998 | 11/17/1998 | | PASS |
|
|
|
/ / 338 - MADE OK FOR FINAL, SIGNED THE PERM COL OF THE OCC REQ CARD A
|
INSP-Final Inspection | 11/16/1998 | 11/16/1998 | 11/16/1998 | P | PASS |
Joe Tawney
|
|
|
11/16/98 406 - ###-#### cecil sched. at 1:30 REINSP OK FOR CERT OF COMPL ON SHELL
|
INSP-Final Inspection | 10/29/1998 | 10/29/1998 | 10/29/1998 | | FAIL |
Joe Tawney
|
|
|
10/29/98 406 - CECIL- ###-#### FN FIRE-PER JOE WILL MEET AT 8 REINSP FAIL ALARM SYSTEM PACKAGE & NFPA 72
|
INSP - Occup. violation notice | 10/12/1998 | 10/12/1998 | 10/12/1998 | | FAIL |
|
|
|
/ / 338 - RECIEVED BY FRED A HOWE FOR KREISENBECK CECIL CALLED LATER T
|
INSP - Final | 11/6/1997 | 11/6/1997 | 11/6/1997 | P | PART |
|
|
|
11/06/97 333 - temp ok
|
INSP-Final Inspection | 11/5/1997 | 11/6/1997 | 11/6/1997 | A | PART |
Joe Tawney
|
|
|
11/06/97 406 - REIN OK FOR TEMP OCC ON SHELL ALARM SUBMITTAL FRT ELEVATOR GEN TIME DELAY
|
INSP-Final Inspection | 11/3/1997 | 11/4/1997 | 11/4/1997 | P | FAIL |
Joe Tawney
|
|
|
11/04/97 406 - FINAL NOT COMPLETED RESUME 11/5/97
|
INSP-Final Inspection | 10/28/1997 | 10/30/1997 | 10/30/1997 | A | NR |
Joe Tawney
|
|
|
10/30/97 406 - FINAL NOT READY DIG DIALER NOT INSTALLED
|
INSP - Framing/Rough-in | 10/23/1997 | 10/24/1997 | 10/24/1997 | P | PART |
|
|
|
CEILING GRID made ok
|
INSP - Framing/Rough-in | 10/17/1997 | 10/20/1997 | 10/20/1997 | A | PART |
|
|
|
CEILING GRID AND FIRE PENETRATION verbal corrections written down on the on prelim punch lists.
|
INSP-Sprinkler Rough-in/Hydro | 10/2/1997 | 10/2/1997 | 10/2/1997 | P | PART |
Joe Tawney
|
|
|
10/02/97 406 - st. als/ bld #5 OK ON HYDRO TEST FOR SPKLR SYSTEM STILL NEED HYDRO TEST ON STANDPIPES
|
INSP - Conference | 9/3/1997 | 9/3/1997 | 9/3/1997 | | PASS |
|
|
|
/ / 338 - ok to use 2'-8" door from the first floor lobby to the north a required exit door will be market NOT AN EXIT
|
INSP - Footings | 8/12/1997 | 8/12/1997 | 8/11/1997 | P | PASS |
|
|
|
08/12/97 338 -
|
INSP-Supply line flush | 7/23/1997 | 7/24/1997 | 7/24/1997 | A | PART |
Joe Tawney
|
|
|
07/24/97 406 - SUPPLY LINE FLUSH AT 11 A.M. OK ON UNDERGROUND FLUSH
|
INSP - Conference | 7/21/1997 | 7/21/1997 | 7/21/1997 | | PASS |
|
|
|
/ / 338 - 2-hr shaft
|
INSP - Framing/Rough-in | 7/18/1997 | 7/21/1997 | 7/21/1997 | P | PART |
|
|
|
07/22/97 338 - madeok partial 2-hr shaft
|
INSP-Supply line flush | 7/17/1997 | 7/21/1997 | 7/21/1997 | A | NR |
Joe Tawney
|
|
|
07/21/97 406 - HE called you and set up an appt for 11 am UNDERGROUND FLUSH NOT READY
|
INSP - Framing/Rough-in | 7/11/1997 | 7/11/1997 | 7/14/1997 | P | CANC |
Tom Arcoraci
|
|
|
bld #5
|
INSP - Framing/Rough-in | 7/11/1997 | 7/11/1997 | 7/11/1997 | | PART |
|
|
|
07/14/97 333 - 1hr at stairs ok to cover
|
INSP - Framing/Rough-in | 7/7/1997 | 7/7/1997 | 7/7/1997 | P | FAIL |
|
|
|
07/07/97 338 - c/n misc drywall problems in the shaft wall systems they
|
INSP - Framing/Rough-in | 6/27/1997 | 6/30/1997 | 7/1/1997 | A | PASS |
|
|
|
06/30/97 338 - Nacho??? (i think)###-#### mice frame to this point ok pager
|
INSP - Framing/Rough-in | 6/20/1997 | 6/23/1997 | 6/23/1997 | A | PART |
|
|
|
06/23/97 338 - partial at the ele core and the stair cores mise perimete
|
INSP - Framing/Rough-in | 6/9/1997 | 6/9/1997 | 6/9/1997 | P | PASS |
|
|
|
06/09/97 338 - misc framing to this point is ok in the core area misc st
|
INSP - Miscellaneous | 6/9/1997 | 6/9/1997 | 6/9/1997 | | PASS |
|
|
|
/ / 338 - resubmittals on the shell and main core areas
|
INSP - Carpentry | 5/30/1997 | 5/30/1997 | 5/30/1997 | P | PASS |
|
|
|
05/30/97 338 -
|
INSP - Conference | 5/30/1997 | 5/30/1997 | 5/30/1997 | | PASS |
|
|
|
/ / 338 - must follow the approved plan with the fireblocking in the w in the north srairwell no execptions
|
INSP - Conference | 5/30/1997 | 5/30/1997 | 5/30/1997 | | PASS |
|
|
|
/ / 338 - must follow the approved plan with the fireblocking in the w in the north srairwell no execptions
|
INSP - Framing/Rough-in | 5/28/1997 | 5/29/1997 | 5/29/1997 | A | PART |
|
|
|
05/29/97 338 - partial framing north stairwell framing questions at the
|
INSP - Framing/Rough-in | 5/23/1997 | 5/27/1997 | 5/27/1997 | A | NR |
|
|
|
05/27/97 338 - partial framing 1st floor core area not ready for cover
|
INSP - Carpentry | 5/5/1997 | 5/6/1997 | 5/6/1997 | A | PASS |
|
|
|
05/06/97 338 -
|
INSP - Conference | 5/1/1997 | 5/5/1997 | 5/5/1997 | A | PASS |
|
|
|
05/05/97 338 - ###-####
|
INSP - Conference | 3/19/1997 | 3/19/1997 | 3/18/1997 | P | PASS |
|
|
|
03/19/97 338 - CONF ON FRAMING ok to but 1-side drywall at the bottom of fire caulk seal in the anular space will field verify.
|
INSP - Conference | 3/7/1997 | 3/10/1997 | 3/9/1997 | A | PART |
|
|
|
03/10/97 338 - on the fire proofing
|
INSP - Masonry | 2/14/1997 | 2/14/1997 | 2/14/1997 | P | PASS |
|
|
|
02/14/97 338 - 3RD FLOOR POUR. READY TO POUR ON MONDAY WEATHER PRO IN PL INSP
|
INSP - Conference | 2/5/1997 | 2/5/1997 | 2/6/1997 | | PASS |
|
|
|
02/05/97 338 - made ok
|
INSP - Conference | 2/5/1997 | 2/5/1997 | 2/5/1997 | P | PASS |
|
|
|
02/05/97 338 - made ok sp insp made ok weather pro in place
|
INSP - Flatwork | 1/27/1997 | 1/28/1997 | 1/28/1997 | A | PASS |
|
|
|
01/28/97 338 - 2ND FLR.POUR made ok 2nd half
|
INSP - Masonry | 1/24/1997 | 1/27/1997 | 1/26/1997 | A | PASS |
|
|
|
01/27/97 338 - POURING 2ND FLR DECK. (I DIDN'T KNOW WHAT TO PUT THIS UN GAVE OK TO POUR 2ND HALF OF THIS DECK WITH THE SPEC INSP BLESSING
|
INSP - Foundation | 1/16/1997 | 1/17/1997 | 1/17/1997 | A | PASS |
|
|
|
01/17/97 338 - fnd.rebar made ok wp in place
|
INSP - Foundation | 1/14/1997 | 1/15/1997 | 1/16/1997 | P | PASS |
|
|
|
01/16/97 338 - WILL POUR IN THE AM south west at the dock
|
INSP - Conference | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
|
|
|
/ / 338 - DETAILS C3&C4 ON A7.0 SHAFT WALL DETAILS THERE IS NO DETAIL SHAFT
|
INSP - Foundation | 12/10/1996 | 12/10/1996 | 12/10/1996 | | PASS |
|
|
|
/ / 338 - made ok by 316
|
INSP - Footings | 12/6/1996 | 12/9/1996 | 12/9/1996 | A | PASS |
|
|
|
12/09/96 338 - FOOTING REBAR r-bar placed weather prot ok
|
INSP - Foundation | 12/3/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
|
|
|
12/04/96 338 - REBAR r-bar placed spec insp made ok
|
INSP - Footings | 11/26/1996 | 11/27/1996 | 11/27/1996 | P | PASS |
|
|
|
11/27/96 338 - footing rebar early pm SPEC INSP MADE OK
|
INSP - Foundation | 11/21/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
|
|
|
RE-BAR FOOTING/FOUNDATION/ placed made ok spec insp
|
INSP - Footings | 11/14/1996 | 11/18/1996 | 11/19/1996 | P | PASS |
|
|
|
11/19/96 338 - SPECIAL INSP MADE OK
|
INSP - Foundation | 11/12/1996 | 11/13/1996 | 11/13/1996 | A | PASS |
|
|
|
11/13/96 338 - ok to pour with the special insp blessing
|
INSP - Conference | 11/5/1996 | 11/6/1996 | 11/6/1996 | A | PASS |
|
|
|
11/06/96 338 - STARTING PROJECT. LOOKS GOOD WILL SCHEDULE PRE JOB CONFERENCE WHEN THE SUBS ARE ALL HIRED
|
INSP - Footings | 11/7/1996 | 11/8/1996 | 1/3/1980 | A | PASS |
|
|
|
11/08/96 338 - LATE A.M. FORMS SET R-BAR PLACED OK BY SPECIAL INSP
|