Permit Information
Permit NumberBLD96-02403
StatusFinaled
Name ED ZIMMER
Site Address 833 W DIAMOND ST
Project NameECCO ELECTRONIC
Customer Number 
ePlanReviewNo
Description
TO BUILD A NEW 49,565 SQ.FT., TWO STORY, OFFICE AND MANUFACTURING BUILDING CONSTRUCTED OF MASONRY AND STEEL EXTERIOR WALLS, BUTLER MANUFACTURING CO. STEEL BUILDING FRAME, ROOF JOISTS AND METAL ROOF DECK, CONCRETE SLAB FIRST FLOOR, TJI FLOOR JOIST AND PLYWOOD SECOND FLOOR AND WOOD AND STEEL INTERIOR WALLS. THIS BUILDING IS FULLY FIRE SPRINKLED AND USED FOR ALLOWABLE AREA INCREASES. THE SECOND FLOOR IS UNFINISHED SPACE AND WILL REQUIRE A TENANT IMPROVEMENT PERMIT TO FINISH AND OCCUPY. THIS PERMIT ALSO INCLUDES ALL RELATED SITE IMPROVEMENTS. ( FIRST FLOOR 40,335 SQ. FT., SECOND FLOOR 9230 SQ. FT.) DR#65-96/PC#496-96/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final8/29/19978/29/19978/29/1997 PASS
DetailsJim Storey
/ / 301 - FNL -OK FINAL
INSP-Final Inspection8/29/19978/29/19978/29/1997PPASS
DetailsRick Jackson
Permanent Occupancy 8/29/19978/29/1997 DONE
Details
INSP - Final8/26/19978/27/19978/27/1997PNR
DetailsJim Storey
08/27/97 301 - i gave floyd his for 8/26/97 all other trades finaled. ca CORR-CORREC-CALL FOR REINSP WHEN COMPLETED HI JIM.....I FAILED THEM TUESDAY PM, ALARM ZONES STILL NOT RIGHT
INSP-Final Inspection8/26/19978/26/19978/26/1997PFAIL
Details
cathy has card to sign off. ALARM RESPONCE STILL WRONG ( 5/23 CORRECTION LIST) FD CALLED FOR EVERYTHING... TO CORRECT ASAP
INSP - Final5/29/19975/29/19975/29/1997 PASS
DetailsJim Storey
/ / 301 - TCO -TEMP C OF O ISSUED CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Final5/23/19975/27/19975/27/1997PNR
DetailsJim Storey
05/27/97 301 -
INSP-Final Inspection5/23/19975/23/19975/23/1997PPART
Details
supervisorys still tranmit as alarms, need nfpa 72
INSP-Final Inspection5/21/19975/21/19975/21/1997PFAIL
Details
address not visible, piv not monitored, all signals transmit as fire alarms, panel troubles do not transmit, 1 head too close to unit heater for temp rating
INSP-Final Inspection5/12/19975/12/19975/12/1997PFAIL
Details
c/n issued, lots of details to wrap up, advised egress control devices must have auto, manual, fire alarm and power out release
INSP - Framing/Rough-in5/9/19975/9/19975/9/1997PPASS
DetailsJim Storey
05/09/97 301 - FRAM-OK FRAMING Resubmital wall
INSP - Framing/Rough-in4/24/19974/25/19974/25/1997APASS
DetailsJim Storey
04/25/97 301 - ceiling wall SCLG-OK SUSPENDED CEILING and draft stop ok
INSP-Sprinkler Rough-in/Hydro4/24/19974/25/19974/25/1997APASS
Details
hydro test, todd will call when pressurized replaced test orifice w/ correct size
INSP-Sprinkler Rough-in/Hydro4/24/19974/24/19974/24/1997APART
Details
correction list given to herb on missing sprinklers. also gave notice that approved plans do not allow storage over 12 ft. sprinklers designed for 16 ft, no racks over 8 ft since no seismic was provided
INSP-Sprinkler Rough-in/Hydro4/23/19974/23/19974/23/1997PPART
Details
herb dock area not complete, need to check 2nd floor storage
INSP - Conference4/21/19974/21/19974/21/1997 PART
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Carpentry4/3/19974/2/19974/3/1997 PASS
DetailsJim Storey
sheer nailling on walls
INSP - Framing/Rough-in4/1/19974/1/19974/1/1997PPASS
DetailsJim Storey
sheer nailling ok mezanine fr ok
INSP - Framing/Rough-in3/25/19973/25/19973/25/1997PPART
DetailsJim Storey
03/25/97 301 - INTER STUD WALLS ALL BUT SHEER OK
INSP - Footings3/11/19973/12/19973/12/1997PPASS
DetailsJim Storey
03/12/97 301 - covered by si. recieved eifs submital and approved system
INSP - Foundation12/12/199612/13/199612/13/1996APASS
DetailsJim Storey
12/13/96 301 - CALLED IN A FLOOR POUR FDN -OK FOUNDATION hair pins
INSP - Footings11/26/199611/27/199611/27/1996PPASS
DetailsJim Storey
/ / 301 - READY AT 1PM PLEASE. FRMS-OK FORMS-REBAR special insp on site
INSP - Footings11/26/199611/26/199611/26/1996PPART
DetailsJim Storey
11/26/96 301 - WIP -WORK IN PROGRESS special insp. on site pending repor
INSP - Footings11/25/199611/25/199611/25/1996PNR
DetailsWes Worcester
still placing dobbies and getting side clearance...spec insp to be on site
INSP - Foundation11/25/199611/25/199611/25/1996PPART
DetailsWes Worcester
poured with special insp on site...pending report as some dowels had less than 1" cover between them at jambs
INSP - Foundation11/21/199611/21/199611/21/1996PPART
DetailsWes Worcester
special insp on site
INSP - Conference11/19/199611/19/199611/19/1996APASS
DetailsWes Worcester
ck on lean concrete fill - going to pour at 3pm w/sp insp
INSP - Footings11/19/199611/19/199611/19/1996PPASS
DetailsWes Worcester
APPT. 3 P.M.
INSP - Footings11/19/199611/19/199611/19/1996ANR
DetailsWes Worcester
INSP - Site Preparation11/19/199611/19/199611/19/1996APART
DetailsWes Worcester
cleaning out mud and having soils tested
INSP - Footings11/14/199611/15/199611/15/1996AFAIL
DetailsWes Worcester
inadequate cover, special inspectors report rejected, eng of record and special inspector to meet on site. several 100'poured