Permanent Occupancy | | 3/13/1997 | 3/13/1997 | | DONE |
|
|
|
|
INSP - Final | 3/12/1997 | 3/12/1997 | 3/12/1997 | P | PASS |
Jim Sly
|
|
|
03/12/97 316 - Frank n Buns/ for perm occup. OK
|
INSP - Final | 11/26/1996 | 11/27/1996 | 11/27/1996 | P | NR |
Carl Dependahl
|
|
|
11/27/96 340 - 316 AREA, SENT IN ERROR
|
INSP-Sprinkler Rough-in/Hydro | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
Joe Tawney
|
|
|
11/25/96 406 - TONY ###-#### NOT SURE WHAT HE WANTED. OK FOR PERM OCC
|
INSP-Sprinkler Rough-in/Hydro | 11/21/1996 | 11/22/1996 | 11/22/1996 | A | FAIL |
Joe Tawney
|
|
|
11/22/96 406 - joe, this might be a final, i was confused./pat per stan normal/pat FINAL INSP FAILED ANSUL TEST DOOR HDWRE EMERG LIGHTS
|
INSP - Framing/Rough-in | 11/15/1996 | 11/15/1996 | 11/15/1996 | P | PASS |
Jim Sly
|
|
|
11/15/96 316 - OK
|
INSP - Carpentry | 11/14/1996 | 11/14/1996 | 11/14/1996 | P | FAIL |
Jim Sly
|
|
|
11/14/96 316 - 1 HR. SHAFT C/N... Architect to re-submit details for ap
|
INSP - Carpentry | 11/12/1996 | 11/13/1996 | 11/13/1996 | A | FAIL |
Jim Sly
|
|
|
11/12/96 316 - 1 HR. SHAFT C/N....Need to build per approved plans.
|
INSP - Ceiling grid | 11/8/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Jim Sly
|
|
|
11/12/96 316 - OK
|
INSP - Carpentry | 11/8/1996 | 11/8/1996 | 11/11/1996 | P | FAIL |
Jim Sly
|
|
|
11/11/96 316 - 1 HR. SHAFT C/N.
|
INSP - Carpentry | 11/8/1996 | 11/8/1996 | 11/8/1996 | | FAIL |
Jim Sly
|
|
|
11/08/96 316 - 1 HR. SHAFT C/N.
|
INSP - Framing/Rough-in | 10/24/1996 | 10/25/1996 | 10/25/1996 | P | PART |
Jim Sly
|
|
|
10/24/96 316 - OK to cover interior walls and demising wall. Left note 2 hr hood shaft W/O inspections of each layer.
|