INSP - Final | 1/9/1998 | 1/12/1998 | 1/12/1998 | A | PASS |
Wes Worcester
|
|
|
01/12/98 342 -
|
INSP - Grading Inspection | 1/7/1998 | | 1/7/1998 | | PASS |
Rita DeYoung
|
|
|
House was occupied without bond being posted or final being given by building department. Did final inspection today and all grading and drainage has been completed. House can be finaled.
|
INSP - Final | 9/18/1997 | 9/19/1997 | 9/19/1997 | A | NR |
|
|
|
09/18/97 453 - need p/w
|
INSP - Grading Inspection | 9/19/1997 | | 9/19/1997 | | BOND |
Rita DeYoung
|
|
|
Rough grading completed. Grading plan was changed to add a 6foot high retaining wall. Told Dale Behrman that this would require a Category 1 Hillside application for final approval. The engineer has approved the rough grading and recommended a bond of $11,200.00 for the remainder of the work to be completed. This is acceptable.
|
INSP - Conference | 9/16/1997 | 9/17/1997 | 9/17/1997 | A | PART |
Wes Worcester
|
|
|
09/17/97 342 - 10:00 as per wes w.
|
INSP - Energy code compliance | 5/16/1997 | 5/19/1997 | 5/18/1997 | A | PASS |
|
|
|
05/19/97 333 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Final | 5/12/1997 | 5/13/1997 | 5/13/1997 | A | PASS |
Alan Hauser
|
|
|
05/13/97 350 - late a.m. call tim behrman pager ###-#### before going ou frame ok, ok to insulate
|
INSP - Framing/Rough-in | 5/13/1997 | 5/13/1997 | 5/13/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - frame ok, ok to insulate
|
INSP - Framing/Rough-in | 5/8/1997 | 5/9/1997 | 5/8/1997 | A | FAIL |
|
|
|
05/09/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Foundation | 1/30/1997 | 1/30/1997 | 1/30/1997 | | PASS |
|
|
|
/ / 333 - FDN -OK FOUNDATION
|
INSP - Framing/Rough-in | 1/29/1997 | 1/30/1997 | 1/30/1997 | A | NR |
Carl Dependahl
|
|
|
01/30/97 340 - Basement wall...NOT FRAME INSP, FOUNDATION WALL...NR, SEN
|
INSP - Footings | 1/17/1997 | 1/21/1997 | 1/21/1997 | A | PART |
|
|
|
01/21/97 333 - 1EFORE 8:30 FTG -OK FOOTING pending reciept of engineers report
|