INSP - Final | 3/6/1997 | 3/7/1997 | 3/7/1997 | A | PASS |
Alan Hauser
|
|
|
03/07/97 350 - FINAL REINSPECT final, stairway guardrail/handrail approved as per bob archibald
|
INSP - Letter of compliance | 3/7/1997 | 3/7/1997 | 3/7/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c#12066
|
INSP - Letter of compliance | 3/7/1997 | 3/7/1997 | 3/7/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c#12066
|
INSP - Final | 3/6/1997 | 3/6/1997 | 3/5/1997 | P | FAIL |
|
|
|
03/06/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 12/11/1996 | 12/11/1996 | 12/11/1996 | P | NR |
Wes Worcester
|
|
|
no response from Truss co stamped and signed
|
INSP - Conference | 12/11/1996 | 12/10/1996 | 12/11/1996 | P | PART |
Wes Worcester
|
|
|
Routed engineering response to Bob Garrison for action
|
INSP - Conference | 12/10/1996 | 12/10/1996 | 12/10/1996 | P | PART |
Wes Worcester
|
|
|
Discussed engineering w/Bob Garrison
|
INSP - Framing/Rough-in | 12/9/1996 | 12/10/1996 | 12/10/1996 | A | PART |
Wes Worcester
|
|
|
ROCKERS TO GO AHEAD...REFERRING ENGINEERING FOR TRUSS BRACING TO PLAN CHECK
|
INSP - Carpentry | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | FAIL |
Wes Worcester
|
|
|
trusses not braced as per Idaho truss detail and eng letter of acceptance of variation not received to date
|
INSP - Energy code compliance | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 12/3/1996 | 12/5/1996 | 12/5/1996 | A | PART |
Wes Worcester
|
|
|
doing minor truss bracing
|
INSP - Footings | 10/7/1996 | 10/7/1996 | 10/7/1996 | P | PASS |
|
|
|
setbacks seem okay
|
INSP - Footings | 10/7/1996 | 10/7/1996 | 10/7/1996 | | PASS |
|
|
|
/ / 400 - setbacks seem okay
|