INSP - Final | 8/29/1997 | 8/29/1997 | 8/29/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR CERT OF COMPL ON SHELL
|
INSP - Final | 8/29/1997 | 8/29/1997 | 8/29/1997 | | PASS |
|
|
|
/ / 338 - FNL -OK FINAL LCI-LETTER OF COMPLIANCE ISSUED
|
INSP - Letter of compliance | 8/29/1997 | 8/29/1997 | 8/29/1997 | | PASS |
|
|
|
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED
|
INSP - Final | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | PART |
|
|
|
06/26/97 338 - FINAL FOR C/O. LATE PM. SIGNED THE TEMP COL ON THE OCC R CORRECTION WILL COPY FIRE INSP OK FOR A TEMP C/C
|
INSP-Final Inspection | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | PART |
Joe Tawney
|
|
|
06/26/97 406 - FINAL FOR C/O. EARLY PM. OK FOR TEMP CERT OF COMPL NO TENANTS UNTIL SPKLR MONITORING INST AND DUCT DETECTORS INST AND TESTED
|
INSP-Final Inspection | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | FAIL |
Joe Tawney
|
|
|
06/19/97 406 - FINAL ON SPRINKLERS RON ###-#### - TONE - DIAL IN YOUR NU FINAL ON SHELL FAIL BOLLARDS AT GAS METERS BLDG ADDRESS SPKLR SYSTEM OFF EAST WALL ON GRID LINE 4 NOT 1 HR CONSTR PER PLAN CURB STRIPING
|
INSP-Sprinkler Rough-in/Hydro | 6/18/1997 | 6/18/1997 | 6/18/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 6/18/1997 | 6/18/1997 | 6/18/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 6/12/1997 | 6/12/1997 | 6/12/1997 | P | FAIL |
Joe Tawney
|
|
|
06/12/97 406 - BRIAN CAULKINS -###-#### HYDRO TEST FAIL FDC PIPING NOT INCLUDED
|
INSP - Final | 6/10/1997 | 6/11/1997 | 6/11/1997 | P | NR |
|
|
|
06/11/97 338 - OTH-OTHER AGENCIES NOT APPROVED not ready
|
INSP - Framing/Rough-in | 5/9/1997 | 5/12/1997 | 5/11/1997 | A | PASS |
|
|
|
05/12/97 338 - okto close in the soffits
|
INSP - Carpentry | 5/8/1997 | 5/8/1997 | 5/8/1997 | P | PASS |
Jim Sly
|
|
|
05/08/97 316 - Inspection of canopy for cover.... West End
|
INSP - Framing/Rough-in | 5/6/1997 | 5/7/1997 | 5/6/1997 | P | NR |
|
|
|
05/07/97 333 - not ready mansard not done cant find electr sticker
|
INSP - Framing/Rough-in | 5/1/1997 | 5/1/1997 | 5/1/1997 | P | PART |
Carl Dependahl
|
|
|
05/01/97 340 - ROOF NAILING SW SIDE OK; DRAFT STOP OK AT CANOPY. REQUEST FRAME OK
|
INSP - Conference | 4/30/1997 | 4/30/1997 | 4/30/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - W/ SUPT. RE DRAFT STOPS AT CANOPY, OK TO BEGIN COVER
|
INSP - Conference | 4/30/1997 | 4/30/1997 | 4/30/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - W/ SUPT. RE DRAFT STOPS AT CANOPY, OK TO BEGIN COVER
|
INSP - Framing/Rough-in | 4/25/1997 | 4/29/1997 | 4/29/1997 | A | FAIL |
Carl Dependahl
|
|
|
04/29/97 340 - C/N, NEED CLARIFICATION OF DRAFT STOPS, NAIL OFF CLIPS, H
|
INSP - Framing/Rough-in | 4/24/1997 | 4/25/1997 | 4/25/1997 | A | PART |
|
|
|
04/25/97 338 - roof deck only front portion
|
INSP - Framing/Rough-in | 4/18/1997 | 4/21/1997 | 4/21/1997 | P | PART |
|
|
|
04/22/97 338 - PERRY, I'M NOT SURE WHAT THIS INSP.WAS FOR..... partial
|
INSP - Masonry | 4/10/1997 | 4/11/1997 | 4/10/1997 | P | PASS |
|
|
|
04/11/97 338 - made ok with sp insp approval r-bar placed
|
INSP - Masonry | 4/9/1997 | 4/10/1997 | 4/9/1997 | A | PASS |
|
|
|
04/10/97 338 - made ok with sp insp blessing
|
INSP - Wall cover | 4/9/1997 | 4/9/1997 | 4/8/1997 | P | PASS |
|
|
|
04/09/97 338 - rebar in block made ok this shuld be a masonry insp for t
|
INSP - Masonry | 4/8/1997 | 4/8/1997 | 4/8/1997 | | PASS |
|
|
|
/ / 338 - madeok with the spec. insp blessing r-bar placed
|
INSP - Masonry | 4/7/1997 | 4/7/1997 | 4/6/1997 | P | PASS |
|
|
|
04/07/97 338 - made ok with sp insp approval
|
INSP - Masonry | 4/2/1997 | 4/3/1997 | 4/3/1997 | A | PART |
Carl Dependahl
|
|
|
04/03/97 340 - BLK. REBAR...338 AREA, PENDING SPEC INSP REPORTS FROM STR
|
INSP - Foundation | 3/31/1997 | 4/1/1997 | 3/31/1997 | A | PASS |
|
|
|
03/31/97 338 - FND.REBAR made ok with sp insp ok
|
INSP - Masonry | 3/28/1997 | 3/31/1997 | 3/30/1997 | A | PASS |
|
|
|
03/31/97 338 - C M U made ok with sp insp ok
|
INSP - Foundation | 3/26/1997 | 3/27/1997 | 3/26/1997 | A | PASS |
|
|
|
03/27/97 338 - made ok with sp insp ok
|
INSP - Foundation | 3/24/1997 | 3/25/1997 | 3/24/1997 | A | PASS |
|
|
|
03/25/97 338 - FND. REBAR CMU ok with sp insp approval will pour at the come back out ì
|
INSP-Conference | 3/20/1997 | 3/20/1997 | 3/20/1997 | | PASS |
|
|
|
PRE CONSTR CONF
|
INSP - Footings | 3/14/1997 | 3/14/1997 | 3/13/1997 | P | PASS |
|
|
|
03/14/97 338 - MADE OK rebar FDN -OK FOUNDATION ì
|
INSP - Foundation | 3/11/1997 | 3/12/1997 | 3/11/1997 | A | PASS |
|
|
|
03/12/97 338 - FND.REBAR..POURING AT 1 P.M. made ok
|
INSP - Footings | 3/6/1997 | 3/7/1997 | 3/5/1997 | A | PASS |
|
|
|
03/07/97 338 - r-bar placed ok with sp insp approval
|
INSP - Foundation | 3/5/1997 | 3/6/1997 | 3/5/1997 | P | NR |
|
|
|
03/06/97 338 - RETAINING WALLpostpone till 03-07-97 # 1
|
INSP - Foundation | 3/5/1997 | 3/5/1997 | 3/5/1997 | | PASS |
|
|
|
/ / 338 - made ok r-bar placed in the east 3/4 ok to pour withthe spec
|
INSP - Footings | 2/28/1997 | 3/3/1997 | 3/3/1997 | P | NR |
|
|
|
03/03/97 338 - postpone till 03-04-97
|
INSP - Footings | 3/3/1997 | 3/3/1997 | 3/3/1997 | | PASS |
|
|
|
/ / 338 - spec insp made ok for the east 3/4 of building
|
INSP-Supply line flush | 2/26/1997 | 2/28/1997 | 2/28/1997 | P | PART |
Joe Tawney
|
|
|
02/28/97 406 - READY AT 3:00 OK FOR UNDERGROUND HYDRO TEST
|