Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD96-03202
StatusFinaled
Name TREASURE VALLEY PSYCHIATRIC
Site Address 411 N ALLUMBAUGH ST
Project NameTREASURE VALLEY
Customer Number 
ePlanReviewNo
Description
TREASURE VALLEY PSYCHIATRIC OFFICE * TO BUILD A ONE STORY, 7470 S.F. PSYCHIATRIC DOCTORS OFFICE BUILDING, CONSTRUCTED OF A BUTLER STEEL FRAME SYSTEM WITH BUTLER METAL ROOF SYSTEM, STRUCTURAL CONCRETE BRICK AND STEEL STUD EXTERIOR WALLS AND CONCRETE SLAB FLOORS. THE INTERIOR IS FINISHED WITH GYPSUMBOARD COVERED STEEL STUD WALLS AND AN ACOUSTIC SUSPENDED CEILING SYSTEM. THIS BUILDING WILL BE FULLY FIRE SPRINKLED. THE SPRINKLER SYSTEM IS BEING USED TO DELETE THE RATED CORRIDOR CONSTRUCTION PER UBC 1005.7 EXC. #8. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED LIST OF CONDITIONS. DR#-80-96/PC#722-96/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final12/29/199712/29/199712/29/1997 PASS
Final
Permanent Occupancy 12/29/199712/29/1997 DONE
Details
INSP - Final12/10/199712/11/199712/12/1997PNR
Details
12/12/97 338 - CARD has not been signed by ele or plmg there is a fee du per monica.
INSP - Final11/6/199711/7/199711/7/1997APASS
DetailsTom Arcoraci
TREASURE VALLEY SIGNED TEMP OCC
INSP-Final Inspection11/5/199711/5/199711/5/1997PPASS
DetailsJoe Tawney
11/05/97 406 - REINSP FOR FINAL OK FOR PERM OCC
INSP-Final Inspection10/31/199711/3/199711/3/1997AFAIL
DetailsJoe Tawney
11/03/97 406 - TREASURE VALLEY FINAL FAIL EMERG LIGHTS BLDG ADDRESS SPARE SPKLR HEADS
INSP-Sprinkler Rough-in/Hydro10/30/199710/31/199710/31/1997AFAIL
DetailsJoe Tawney
10/31/97 406 - TREASURE VALLEY HYDRO TEST ON FDC PIPING FAIL
INSP-Supply line flush10/23/199710/23/199710/23/1997 PART
DetailsJoe Tawney
/ / 406 - OK ON UNDERGROUND FLUSH
INSP-Sprinkler Rough-in/Hydro10/17/199710/17/199710/17/1997 PART
DetailsJoe Tawney
/ / 406 - OK ON HYDRO TEST EXCEPT FOR FDC PIPING
INSP - Wall cover10/13/199710/15/199710/15/1997PPASS
Details
CEILING GRID made ok with verbal corrections
INSP - Framing/Rough-in9/9/19979/9/19979/9/1997PPASS
Details
09/09/97 338 - made ok to cover other agencies made ok next visit will b seizmic
INSP - Framing/Rough-in9/3/19979/4/19979/4/1997ANR
Details
09/04/97 338 - Scheduled by Hello! on 09/03/97 at 09:03:28.DID SAME INSP
INSP-Sprinkler Rough-in/Hydro9/3/19979/4/19979/4/1997AFAIL
DetailsJoe Tawney
09/03/97 406 - SPKLR ROUGH IN NO APPROVED PLANS ON SITE ALSO CONF ON OTH
INSP - Framing/Rough-in9/3/19979/3/19979/3/1997PNR
Details
09/03/97 338 - OTH-OTHER AGENCIES NOT APPROVED NOT READY
INSP - Masonry8/1/19978/4/19978/4/1997APASS
DetailsRuss Owen
08/04/97 407 - last lift at the four corners.
INSP - Masonry7/30/19977/30/19977/30/1997PPASS
Details
07/30/97 338 - made ok r-bar placed
INSP - Masonry7/30/19977/30/19977/30/1997 PASS
Details
/ / 338 - MASN-REBAR OK
INSP - Masonry7/28/19977/29/19977/28/1997APASS
Details
07/29/97 338 - made ok with sp insp approval
INSP - Foundation6/30/19977/1/19977/1/1997APASS
Details
07/01/97 338 - made ok with sp insp approval
INSP - Foundation6/26/19976/27/19976/27/1997PPASS
Details
06/27/97 338 - made ok with sp insp approvalSTEM WALLS
INSP - Footings6/26/19976/26/19976/26/1997PPASS
Details
06/26/97 338 - made ok with special insp approval
INSP - Footings6/24/19976/24/19976/24/1997PPASS
Details
06/24/97 338 - FOOTING REINSPECT north wall/sw and se corners r-bar plac pass of the sp insp ufer ground is in place in the footing
INSP - Footings6/23/19976/24/19976/24/1997ANR
Details
06/24/97 338 - not ready need sp insp letter/and work to be ready when c