Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD96-03206
StatusFinaled
Name BOISE CITY
Site Address 3150 AIRPORT WAY
Project NameBOISE AIRPORT GARAGE
Customer Number 
ePlanReviewNo
Description
BOISE AIR TERMINAL PUBLIC PARKING GARAGE FACILITY-TO CONSTRUCT A NEW 450,715 SQ. FT., FOUR TIER, POST-TENSIONED CONCRETE OPEN PARKING GARAGE WITH PRE-ENGINEERED STEEL ROOF CANOPY SYSTEM AND STRUCTURAL STEEL FRAME STAIR AND LOBBY ENCLOSURES. THIS BUILDING IS NOT FIRE SPRINKLED. THE UNFINISHED UNSPECIFIED BUILDING SPACES SHALL NOT BE FINISHED WITHOUT SEPARATE TENANT IMPROVEMENT PERMITS. THE PRE-ENGINEERED STEEL ROOF CANOPY IS NOT APPROVED UNDER THIS PERMIT. A SEPARATE PLAN SUBMITTAL, APPROVAL AND BUILDING PERMIT ARE REQUIRED FOR THE ROOF CANOPY PORTION OF THIS BUILDING PROJECT. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR-79-96/CU-38-96/PC-96-723/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final2/3/19982/4/19982/4/1998APASS
DetailsJim Storey
02/04/98 301 - eric ###-#### FNL -OK FINAL engineer of record actceptance of all decrepicies in speci insp. and field c/n reviewed and actcepted by kent soelberg p.e. with rutherford & chekene. all records to this effect archived at city hall w this bld. permi
INSP-Final Inspection2/4/19982/4/19982/4/1998APASS
DetailsRick Jackson
final inspection conducted a few weeks ago - updating the permit plan computer log.
INSP-Final Inspection11/25/199712/1/199712/1/1997APART
DetailsRick Jackson
PARKING GARAGE retest smoke detectors and elevator recall - passed.
INSP - Final10/30/199710/30/199710/30/1997PPART
DetailsJim Storey
10/30/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED TCO -TEMP C OF O ISSUED
INSP-Final Inspection10/30/199710/30/199710/30/1997APART
DetailsRick Jackson
temp c/o approved. c/n issued
INSP-Alarm Testing10/29/199710/29/199710/29/1997PCANC
DetailsRick Jackson
attempted test of alarm system. contractor not ready due to water (from leak) in panel and phone line problems.
INSP - Final10/22/199710/24/199710/24/1997PFAIL
DetailsJim Storey
10/24/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED breakway wrong swing.
INSP-Final Inspection10/22/199710/24/199710/24/1997AFAIL
DetailsRick Jackson
c/n issued. alarm system not ready.
INSP-Alarm Testing10/23/199710/23/199710/23/1997PPART
DetailsRick Jackson
contractor requests 2:00 pm for generator and alarm tests. generator passed. alarms not ready.
INSP - Conference10/22/199710/22/199710/22/1997PPART
DetailsRick Jackson
FIRING UP GENERATOR/ set up generator test for 10/23 at 2:00 pm.
INSP-Conference10/7/199710/7/199710/7/1997APART
DetailsRick Jackson
conference about smoke detector placement for elevators.
INSP-Final Inspection10/2/199710/6/199710/6/1997APART
DetailsRick Jackson
architect requested insp for 8:15 - 409 pre-final inspection. reviewed alarm testing, elevator, generator and standpipe requirements.
INSP - Wall cover9/29/19979/29/19979/30/1997PPASS
DetailsJim Storey
09/30/97 301 - STEEL STUDS FRAM-OK FRAMING
INSP - Framing/Rough-in9/17/19979/17/19979/17/1997APART
DetailsTom Arcoraci
shaft wall discussion, elavator shaft and room discussion ok for one side drywall
INSP - Framing/Rough-in9/2/19979/3/19979/3/1997APART
DetailsJim Storey
09/03/97 301 - west wall elavator only. ok.
INSP - Framing/Rough-in8/25/19978/25/19978/25/1997 PART
DetailsJim Storey
/ / 301 - pick up reports
INSP - Conference8/14/19978/15/19978/15/1997ANR
DetailsJim Storey
08/15/97 301 -
INSP-Sprinkler Rough-in/Hydro8/12/19978/12/19978/12/1997PPART
Details
hydro ok, c/n issued on hose stations standpipe rough-in/ hydro test
INSP - Miscellaneous8/11/19978/11/19978/11/1997 FAIL
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED fire proofing of steel at col pt cable pre-cut showing signs of rust not to be used with out engineers aproval.
INSP - Conference7/21/19977/21/19977/21/1997 PART
DetailsJim Storey
/ / 301 - conf. work in progess special insp. on site no word as to a special insp. change as per agreement at brgining of the project.
INSP - Conference7/18/19977/18/19977/18/1997 FAIL
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED weld lengths of pre-cast atchment.oversized holes of steel baseplate posts. special insp. if redu will requier call for requis
INSP - Flatwork7/17/19977/17/19977/17/1997 PART
DetailsJim Storey
/ / 301 - work in progess special insp. on site. pending report for la floor.
INSP - Framing/Rough-in7/3/19977/3/19977/3/1997 PART
DetailsJim Storey
/ / 301 - special insp. on site work in progess
INSP - Conference6/26/19976/26/19976/26/1997 PART
DetailsJim Storey
/ / 301 - pending s.i. report,
INSP - Flatwork6/19/19976/19/19976/19/1997 PART
DetailsJim Storey
/ / 301 - special insp. in progess pending reports
INSP - Conference6/3/19976/3/19976/3/1997 PASS
DetailsJim Storey
/ / 301 - WIP -WORK IN PROGRESS RECIEVED SPECIAL INSP. REPORTS
INSP - Conference4/22/19974/22/19974/22/1997 FAIL
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED resolve to special insp. repo stamped shop on pt. required.
INSP - Conference3/25/19973/25/19973/25/1997 PASS
DetailsJim Storey
/ / 301 - WIP -WORK IN PROGRESS
INSP - Flatwork3/18/19973/18/19973/18/1997 PART
DetailsJim Storey
/ / 301 - WIP -WORK IN PROGRESS
INSP - Conference3/10/19973/11/19973/11/1997APASS
DetailsJim Storey
03/11/97 301 - cover placement and control isues in special insp. qc, ba set of rebar and pt configuration as well as shop drawing from strucuarl engineer.
INSP - Footings2/20/19972/21/19972/21/1997PPART
DetailsJim Storey
02/21/97 301 - REBAR WORK IN PROGESS WHAT IS SET IS OK SPECIAL INSP. ON REPORTS.
INSP - Foundation2/20/19972/21/19972/21/1997PPART
DetailsJim Storey
02/21/97 301 - REBAR