Permit Information
Permit NumberBLD97-00110
StatusFinaled
Name GST TELECOM
Site Address 199 N CAPITOL BLVD
Project NameWASHINGTON MUTUAL
Customer Number 
ePlanReviewNo
Description
(WASHINGTON MUTUAL - 3RD FLR) To construct and finish an office support area of 1860 sq. feet on the 3rd floor, A 3,671 sq. ft. Switch Gear Room with support areas on the fourth floor and a 140 sq. ft. Fuel Tank Storage room in the basement for emergency generator additional fuel supply. Construction to be of noncombustible frame with fire resistive protection of framing, suspended ceiling system and structural upgrade of floor system under battery storage area per engineering, all per approved plans. Separate electrical, mechanical & plumbing permits are required. Contractor responsible for full compliance with attached Fire Dept. plan review comments. NOTE: This building is fully fire sprinklered. Sprinkler system is used to comply with high-rise requirements. PC#021-97/drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final4/29/19974/30/19974/30/1997PCANC
DetailsJim Storey
04/29/97 301 - trans to kim 4th south end.
Permanent Occupancy 4/30/19974/30/1997 DONE
Details
INSP-Final Inspection4/28/19974/29/19974/29/1997APASS
Details
ALARMS TESTED, BASEMENT SEPARATION OF TANK TESTED, PASS
INSP-Final Inspection4/17/19974/17/19974/17/1997AFAIL
Details
3rd floor corridor requirements and basement diesel tank requirements NOT MET
INSP-Sprinkler Rough-in/Hydro4/16/19974/16/19974/16/1997PPASS
Details
1pm pre-action system test system trip test ok, need to connect fm 200 smoke detectors to building supervisory since panel location is not constantly attended and signal is not sent to approved central station. will check w/ final
INSP - Framing/Rough-in4/8/19974/9/19974/8/1997PPASS
Details
04/09/97 333 - GRID 3 RD FLOOR SCLG-OK SUSPENDED CEILING
INSP-Conference3/26/19973/26/19973/26/1997APART
Details
delivered notice of violation to roger of merrill. Discussed possible ways to correct.
INSP - Final3/21/19973/25/19973/25/1997AFAIL
Details
gst 4th flr not complete, want to use fm 200 in place of sprinklers, plans called for fm200 to be additional. alarms not connected, corridor doors not installed. advised Roger w/ Merrill to drop sprinklers into space or request approval of fm200 as a replacement system from the fire chief.
INSP - Ceiling grid3/6/19973/7/19973/6/1997APASS
Details
03/07/97 333 - 4TH FLOOR SCLG-OK SUSPENDED CEILING
INSP - Framing/Rough-in2/24/19972/24/19972/23/1997PPASS
Details
02/24/97 333 -