INSP - Final | 10/30/1997 | 10/31/1997 | 10/31/1997 | P | PASS |
|
|
|
MADE OK OK FOR FRONT DESK TO SIGN FOR ME
|
INSP-Final Inspection | 10/30/1997 | 10/31/1997 | 10/31/1997 | A | PASS |
Joe Tawney
|
|
|
10/31/97 406 - OK FOR PERM OCC
|
Permanent Occupancy | | 10/31/1997 | 10/31/1997 | | DONE |
|
|
|
|
INSP - Final | 10/23/1997 | 10/24/1997 | 10/24/1997 | P | NR |
|
|
|
CIRCUIT CITY need pplmg approval
|
INSP-Final Inspection | 10/23/1997 | 10/24/1997 | 10/24/1997 | A | PART |
Joe Tawney
|
|
|
10/24/97 406 - CIRCUIT CITY/ REINSPECTION/ SAYS YOU HAVE 8:00 APT OK FOR TEMP OCC DUCT DET SMOKE SEALS FIRE DOOR ADJ EXT MARKING
|
INSP - Final | 10/23/1997 | 10/23/1997 | 10/23/1997 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL FAIL FIRE DOOR AND SPKLR SUPERVISION
|
INSP-Sprinkler Rough-in/Hydro | 10/20/1997 | 10/21/1997 | 10/21/1997 | A | NR |
Joe Tawney
|
|
|
10/21/97 406 - FINAL NOT READY ALARM SYSTEM
|
INSP-Sprinkler Rough-in/Hydro | 10/20/1997 | 10/20/1997 | 10/20/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TESTS FOR TWO WET PIPE SYSTEMS
|
INSP-Conference | 10/7/1997 | 10/7/1997 | 10/7/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF TO DISCUSS LOCATION OF FIRE EXT
|
INSP - Wall cover | 9/16/1997 | 9/17/1997 | 9/17/1997 | A | PASS |
|
|
|
09/17/97 338 - CEILING GRID made ok to drop in tiles with the ele insp approval
|
INSP-Supply line flush | 9/16/1997 | 9/17/1997 | 9/17/1997 | A | PART |
Joe Tawney
|
|
|
09/17/97 406 - SPKLR ROUGH IN OK ON SPKLR ROUGH IN AND OK TO COVER
|
INSP - Carpentry | 8/27/1997 | 8/28/1997 | 8/28/1997 | A | PASS |
|
|
|
08/28/97 338 - Scheduled by Hello! on 08/27/97 at 16:52:22. CONFERENCE O USING ARMSTRONG INTERMEDIATE LOOKING GOOD ALL IS ON SCHEDULU
|
INSP-Supply line flush | 8/28/1997 | 8/28/1997 | 8/28/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 8/26/1997 | 8/27/1997 | 8/28/1997 | A | CANC |
|
|
|
08/28/97 338 - cancelledwill recall
|
INSP-Supply line flush | 8/25/1997 | 8/26/1997 | 8/26/1997 | A | NR |
Joe Tawney
|
|
|
08/26/97 406 - NOT READY FOR UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 8/15/1997 | 8/15/1997 | 8/15/1997 | | PASS |
|
|
|
08/15/97 338 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 8/12/1997 | 8/13/1997 | 8/13/1997 | A | PASS |
|
|
|
08/13/97 338 - made ok to insulate
|
INSP - Framing/Rough-in | 8/8/1997 | 8/11/1997 | 8/11/1997 | P | PASS |
|
|
|
08/11/97 336 - made ok for the furred walls at the perimeter as there is
|
INSP - Roof | 8/8/1997 | 8/11/1997 | 8/11/1997 | A | PART |
|
|
|
08/11/97 336 - made ok
|
INSP - Conference | 8/8/1997 | 8/8/1997 | 8/8/1997 | | PASS |
|
|
|
/ / 338 - with drywall super Keith and stan the project manager
|
INSP - Framing/Rough-in | 8/7/1997 | 8/8/1997 | 8/8/1997 | A | NR |
|
|
|
08/07/97 338 - not ready conference only with drywall for and pro manage
|
INSP - Foundation | 7/31/1997 | 8/1/1997 | 7/31/1997 | P | PASS |
|
|
|
08/01/97 338 - CONCRETE RE-BAR MASN-REBAR OK
|
INSP - Footings | 7/25/1997 | 7/29/1997 | 7/28/1997 | A | PASS |
|
|
|
07/29/97 338 - REBAR FOR FOOTING made ok with sp insp app
|
INSP - Masonry | 7/25/1997 | 7/29/1997 | 7/28/1997 | A | PASS |
|
|
|
07/29/97 338 - REBARmade ok with sp insp approval
|
INSP - Masonry | 7/25/1997 | 7/28/1997 | 7/28/1997 | A | PASS |
|
|
|
07/28/97 338 - made ok with the sp insp approval
|
INSP - Masonry | 7/11/1997 | 7/18/1997 | 7/18/1997 | A | PART |
Tom Arcoraci
|
|
|
spec inspect on site report pending
|
INSP - Masonry | 7/11/1997 | 7/17/1997 | 7/17/1997 | A | PASS |
|
|
|
/ / 338 - made ok with sp insp approval
|
INSP - Masonry | 7/11/1997 | 7/16/1997 | 7/16/1997 | A | PASS |
|
|
|
07/16/97 338 - made ok with sp insp approval
|
INSP - Masonry | 7/11/1997 | 7/15/1997 | 7/15/1997 | A | PASS |
|
|
|
07/15/97 338 - MASN-REBAR OK
|
INSP - Masonry | 7/11/1997 | 7/14/1997 | 7/14/1997 | A | PASS |
|
|
|
07/14/97 338 - GROUT MASN-REBAR OK
|
INSP - Masonry | 7/7/1997 | 7/11/1997 | 7/11/1997 | A | PART |
Tom Arcoraci
|
|
|
|
INSP - Masonry | 7/7/1997 | 7/10/1997 | 7/10/1997 | A | PASS |
|
|
|
07/10/97 338 - made ok with sp insp approval MASN-REBAR OK
|
INSP - Footings | 7/7/1997 | 7/9/1997 | 7/9/1997 | A | PASS |
|
|
|
07/10/97 338 - OTHER AGENCIES AIGNED OFF ON THE SLAB MADE OK
|
INSP - Masonry | 7/7/1997 | 7/9/1997 | 7/9/1997 | A | PASS |
|
|
|
07/10/97 338 - MADE OK WITH SP INSP APPROVAL MASN-REBAR OK
|
INSP - Masonry | 7/7/1997 | 7/8/1997 | 7/8/1997 | A | PASS |
|
|
|
07/08/97 338 - made okwith sp insp ok
|
INSP - Conference | 7/3/1997 | 7/3/1997 | 7/3/1997 | | PASS |
|
|
|
/ / 338 - conf on cleanup of the streets
|
INSP - Masonry | 6/30/1997 | 7/3/1997 | 7/3/1997 | A | PASS |
|
|
|
07/03/97 338 - concrete and a.m. and p.m. masonry inspection made ok wit approvals
|
INSP - Masonry | 6/30/1997 | 7/3/1997 | 7/3/1997 | P | PASS |
|
|
|
07/03/97 338 - made ok
|
INSP - Masonry | 6/30/1997 | 7/2/1997 | 7/2/1997 | P | PASS |
|
|
|
07/02/97 338 - made ok with sp insp ok
|
INSP - Masonry | 6/30/1997 | 7/2/1997 | 7/2/1997 | A | PASS |
|
|
|
07/02/97 338 - concrete and a.m. and p.m. masonry inspection made ok wit
|
INSP - Masonry | 6/30/1997 | 7/1/1997 | 7/1/1997 | A | PASS |
|
|
|
07/01/97 338 - concrete and a.m. and p.m masonry inspection made ok with
|
INSP - Masonry | 6/30/1997 | 7/1/1997 | 7/1/1997 | P | PASS |
|
|
|
07/01/97 338 - made ok with sp insp approval
|
INSP - Masonry | 6/24/1997 | 6/26/1997 | 6/26/1997 | P | PASS |
|
|
|
06/26/97 338 - made ok with sp insp approvalCEMENT, ETC. SPECIAL INSPEC
|
INSP - Masonry | 6/24/1997 | 6/25/1997 | 6/25/1997 | A | PASS |
|
|
|
/ / 338 - POURING MASONRY GROUT REBAR & SLAB 9 A.M. SPECIAL INSPECTOR ON BOARD. MASN-REB
|
INSP - Masonry | 6/24/1997 | 6/24/1997 | 6/24/1997 | P | PASS |
|
|
|
06/24/97 338 - 1 o'clock special inspection on site, re-bar made ok with
|
INSP - Masonry | 6/20/1997 | 6/23/1997 | 6/23/1997 | A | PASS |
|
|
|
06/23/97 338 - made ok with sp insp approval
|
INSP - Masonry | 6/19/1997 | 6/20/1997 | 6/20/1997 | A | PART |
Tom Arcoraci
|
|
|
MASONRY REBAR...part, pend spec insp
|
INSP - Masonry | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | PASS |
|
|
|
06/19/97 338 - made ok with sp insp approval the r-bar is placed at this
|
INSP - Masonry | 6/17/1997 | 6/17/1997 | 6/17/1997 | P | PASS |
|
|
|
06/17/97 338 - MASONARY GROUT AND CONCRETE REINFORCEMENT. ..LATE P.M.MAD APPROVAL POURING COMPLETED AT MY ARRIVAL
|
INSP - Footings | 6/11/1997 | 6/12/1997 | 6/12/1997 | P | PASS |
|
|
|
06/12/97 338 - LINES B G & 1 made ok r-bar placed
|
INSP - Masonry | 6/11/1997 | 6/12/1997 | 6/12/1997 | P | PASS |
|
|
|
06/12/97 338 - made ok GROUT - GRID LINES B & G
|
INSP - Masonry | 6/10/1997 | 6/11/1997 | 6/12/1997 | P | PASS |
|
|
|
06/11/97 338 - made ok for the west wall to slab height
|
INSP - Footings | 6/5/1997 | 6/5/1997 | 6/5/1997 | P | PASS |
|
|
|
06/05/97 338 - LATE PM west 1/2 ok with sp insp approvel
|