INSP - Final | 10/15/1997 | 10/16/1997 | 10/16/1997 | A | PASS |
Jim Storey
|
|
|
10/16/97 301 - FNL -OK FINAL routed for perm sign off with contractor to city hall.
|
INSP - Letter of compliance | 10/16/1997 | 10/16/1997 | 10/16/1997 | | PASS |
|
|
|
Letter of Compliance #12964 issued to the EA L.L.C. Business ofc./warehouse bldg.
|
INSP - Final | 10/6/1997 | 10/7/1997 | 10/7/1997 | A | PART |
Jim Storey
|
|
|
10/07/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED TEMP OCC OK GRAB BARS 24'' BACK OF STOOL, ADDRESS NUMBERS CHANGE REQUIST OR NEED POS PERMITED.
|
INSP-Final Inspection | 10/6/1997 | 10/6/1997 | 10/6/1997 | P | PASS |
Rick Jackson
|
|
|
main exit door edge mount bolts removed. c/o approved.
|
INSP-Final Inspection | 9/26/1997 | 9/29/1997 | 9/29/1997 | A | FAIL |
Rick Jackson
|
|
|
C/N ISSUED.
|
INSP - Framing/Rough-in | 9/24/1997 | 9/25/1997 | 9/25/1997 | A | FAIL |
Jim Storey
|
|
|
09/25/97 301 - PEE GRID PRISTOL CEILING CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 9/5/1997 | 9/8/1997 | 9/8/1997 | P | PASS |
Jim Storey
|
|
|
09/08/97 301 - FRAM-OK FRAMING GWB -OK SHEETROCK NAILING
|
INSP - Framing/Rough-in | 9/5/1997 | 9/5/1997 | 9/5/1997 | P | PART |
Jim Storey
|
|
|
09/05/97 301 - OTH-OTHER AGENCIES NOT APPROVED CORR-CORREC-CA
|
INSP - Framing/Rough-in | 8/26/1997 | 8/27/1997 | 8/27/1997 | P | FAIL |
Jim Storey
|
|
|
08/27/97 301 - FRAMING AND FIRE RATED SHEET ROCK CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Conference | 8/26/1997 | 8/26/1997 | 8/26/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - NWP -GENERAL INSPECTION - NO WORK IN PROGRESS recieved engineers reports stamped approval.
|
INSP - Carpentry | 8/14/1997 | 8/14/1997 | 8/14/1997 | P | PASS |
Jim Storey
|
|
|
part framing ok to do first layer of ceilling.
|
INSP - Framing/Rough-in | 8/13/1997 | 8/13/1997 | 8/13/1997 | P | PASS |
Jim Storey
|
|
|
08/13/97 301 - RF -OK ROOF NAILING f occ.
|
INSP - Masonry | 7/30/1997 | 7/31/1997 | 7/31/1997 | A | |
|
|
|
They do have a special inspector and they will be ready to pour at 2:30
|
INSP - Masonry | 7/29/1997 | 7/30/1997 | 7/30/1997 | A | PASS |
|
|
|
07/30/97 333 - POURING AT 10:30 ok pending special insp reports
|
INSP - Masonry | 7/28/1997 | 7/29/1997 | 7/29/1997 | A | PART |
|
|
|
07/29/97 333 - POURING AT 10 A.M. SPEC. INSPECTOR ON SITE ok pending special insp reports
|
INSP - Masonry | 7/25/1997 | 7/28/1997 | 7/28/1997 | A | PASS |
Jim Storey
|
|
|
07/28/97 301 - READY AT 10:30 MASN-REBAR OK special insp report pending.
|
INSP - Masonry | 7/23/1997 | 7/24/1997 | 7/24/1997 | A | PASS |
Jim Storey
|
|
|
07/24/97 301 - recieved stampedreduction in f'c from engineer of record foundation
|
INSP - Masonry | 7/22/1997 | 7/23/1997 | 7/23/1997 | A | PART |
Jim Storey
|
|
|
07/23/97 301 - pouring about 11:30 a.m. special inspector on site. special insp.report pending
|
INSP - Foundation | 6/24/1997 | 6/24/1997 | 6/24/1997 | P | PASS |
Jim Storey
|
|
|
06/24/97 301 - FDN -OK FOUNDATION
|
INSP - Footings | 6/19/1997 | 6/20/1997 | 6/20/1997 | A | PASS |
Jim Storey
|
|
|
06/20/97 301 - FOOTING REBAR FRMS-OK FORMS-REBAR engineer design for 2500 psi. ok
|
INSP - Footings | 6/19/1997 | 6/19/1997 | 6/19/1997 | P | CANC |
Jim Storey
|
|
|
06/19/97 301 - cancled by contractor
|
INSP - Footings | 6/18/1997 | 6/18/1997 | 6/19/1997 | P | PART |
Jim Storey
|
|
|
06/18/97 301 -
|