FIRE-Final Inspection | 12/14/1999 | 12/16/1999 | 12/16/1999 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 10:26:49. Contact: ###-####. Conf. On spklr. Coverage for concealed spaces and exception to code.
|
BLD-Final | 12/14/1999 | 12/14/1999 | 12/14/1999 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 10:33:23. Contact: ###-####. Bldg. "C", shell ok for L/C.
|
FIRE-Final Inspection | 12/14/1999 | 12/14/1999 | 12/14/1999 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 10:32:42. Contact: ###-####. Reinsp. Ok for certificate of completion.
|
INSP - Final | 8/17/1999 | 8/17/1999 | 8/17/1999 | | FAIL |
|
|
|
other agencies not approved fire c/n frpom 04 of 1998
|
INSP-Conference | 8/17/1999 | | 8/17/1999 | | PEND |
|
|
|
with g kulchek on the l/c there is an active c/n for the shell by fire insp 406. He is to call 406 and arrange getting this taken care of
|
INSP - Final | 4/15/1999 | 4/15/1999 | 4/15/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL LETTER OF COMPL NOT YET ISSUED, SPKLR RISER ROOM
|
INSP - Final | 3/19/1998 | 3/20/1998 | 3/20/1998 | P | PART |
|
|
|
03/20/98 338 - TEMP MADE PK WHEN COMPLETED AND OOOR HARDWARE IS INSTALLE
|
INSP-Final Inspection | 3/19/1998 | 3/20/1998 | 3/20/1998 | P | FAIL |
Joe Tawney
|
|
|
03/20/98 406 - BLDG C--BILL ###-#### FINAL ON SHELL FAIL ALARM SYSYEM NOT TESTED WITH APPR PLANS
|
INSP-Sprinkler Rough-in/Hydro | 2/23/1998 | 2/24/1998 | 2/24/1998 | A | PART |
Joe Tawney
|
|
|
02/24/98 406 - shelly ###-#### OK ON HYDRO TEST EXCEPT FDC PIPING PARTIAL OK ON SPKLR ROUGH IN
|
INSP - Framing/Rough-in | 1/22/1998 | 1/22/1998 | 1/22/1998 | | PASS |
|
|
|
/ / 338 - for the ext wall cover on the inside of yen ching only
|
INSP - Framing/Rough-in | 12/1/1997 | 12/1/1997 | 12/1/1997 | P | PART |
|
|
|
12/01/97 338 -
|
INSP - Framing/Rough-in | 10/22/1997 | 10/22/1997 | 10/22/1997 | P | PART |
|
|
|
STEEL FRAMING corridor wall tunnel conference with Bob Leonard and the super
|
INSP-Supply line flush | 9/15/1997 | 9/15/1997 | 9/15/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP-Sprinkler Rough-in/Hydro | 9/11/1997 | 9/12/1997 | 9/12/1997 | A | NR |
Joe Tawney
|
|
|
09/12/97 406 - THESE ARE ALL UNDER GROUND UNDERGROUND FLUSH NOT READY RESCH
|
INSP - Foundation | 8/19/1997 | 8/20/1997 | 8/19/1997 | A | CANC |
|
|
|
foundation wall inspection only mis early start permit allowed for concrete on this project per 338
|
INSP - Footings | 8/19/1997 | 8/19/1997 | 8/19/1997 | P | NR |
|
|
|
08/19/97 338 - this is to be a MIS PERMIT FOR ALL STR CONCRETE
|
INSP - Conference | 7/25/1997 | 7/25/1997 | 7/25/1997 | | PART |
|
|
|
/ / 338 - with hawkins smith they will be down directly to office with apppand check for the same
|
INSP - Conference | 7/25/1997 | 7/25/1997 | 7/25/1997 | | PASS |
|
|
|
/ / 338 - caled gslane and bgarrisson to find out why full permit body
|
INSP - Footings | 7/25/1997 | 7/25/1997 | 7/25/1997 | P | PART |
|
|
|
07/25/97 338 - for early start permit only
|
INSP - Miscellaneous | 7/25/1997 | 7/25/1997 | 7/25/1997 | | PASS |
|
|
|
/ / 338 - RETURN TO THE JOBSITE TO RETRIEVE INVALID ISSUED PERMIT
|