INSP - Final | 1/26/1998 | 1/26/1998 | 1/26/1998 | P | PASS |
|
|
|
01/26/98 333 - CARD SIGNED FOR PERM PHASE 1
|
Permanent Occupancy | | 1/26/1998 | 1/26/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/20/1998 | 1/20/1998 | 1/20/1998 | P | PASS |
Rick Jackson
|
|
|
Phase 1 completed. strobe device relocated and functional. c/o approved - card not on-site to sign.
|
INSP-Final Inspection | 1/13/1998 | 1/13/1998 | 1/13/1998 | P | PART |
Rick Jackson
|
|
|
tested alarms - pass. kitchen extinguishing system, outside sprinkler control valve and monitoring to be part of Phase 2 permit. dampers in corridor functioned properly
|
INSP - Final | 1/8/1998 | 1/9/1998 | 1/9/1998 | P | PASS |
|
|
|
01/09/98 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP-Final Inspection | 1/9/1998 | 1/9/1998 | 1/9/1998 | P | NR |
Rick Jackson
|
|
|
alarms not ready. sprinkler riser/PIV not monitored.
|
INSP-Final Inspection | 1/7/1998 | 1/8/1998 | 1/9/1998 | P | PART |
Rick Jackson
|
|
|
01/08/98 409 - he will call you. checked devices/placement. will test in 1/9/98
|
INSP - Final | 1/7/1998 | 1/8/1998 | 1/8/1998 | P | FAIL |
|
|
|
01/08/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 12/16/1997 | 12/16/1997 | 12/16/1997 | P | PASS |
|
|
|
12/16/97 333 - BOISE SENIOR CENTER/ LAST PARTIAL OF CH STUD CEILING. WOULD LIKE AROUND 4:00 ceiling ok will check firestops later
|
INSP-Sprinkler Rough-in/Hydro | 12/16/1997 | 12/16/1997 | 12/16/1997 | A | PASS |
Rick Jackson
|
|
|
hydro test of anti-freeze system
|
INSP - Framing/Rough-in | 12/11/1997 | 12/11/1997 | 12/11/1997 | P | PART |
|
|
|
12/11/97 333 - CLG -OK CEILING COVER
|
INSP-Sprinkler Rough-in/Hydro | 12/10/1997 | 12/11/1997 | 12/11/1997 | P | CANC |
Rick Jackson
|
|
|
12/11/97 409 - ANTI-FREEZE FLUSH--PAGE DOUG AT ###-#### TO MEET YOU doug didn't answer page at 4:00 pm.
|
INSP-Final Inspection | 12/4/1997 | 12/5/1997 | 12/5/1997 | P | PASS |
Rick Jackson
|
|
|
after 1:00 Doug ###-#### sprinkler hydro only - passed. not a final inspection for occupancy
|
INSP - Framing/Rough-in | 12/2/1997 | 12/3/1997 | 12/3/1997 | A | PASS |
|
|
|
12/03/97 333 - ch studs in phase 1 senior center corridor ceilings ok
|
INSP - Framing/Rough-in | 11/13/1997 | 11/14/1997 | 11/14/1997 | A | PASS |
|
|
|
11/14/97 333 - late am FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 11/12/1997 | 11/12/1997 | 11/12/1997 | P | PART |
|
|
|
11/12/97 333 - one side only
|
INSP - Roof | 11/6/1997 | 11/7/1997 | 11/7/1997 | A | PASS |
|
|
|
11/07/97 333 - ok
|
INSP - Framing/Rough-in | 10/31/1997 | 11/3/1997 | 11/3/1997 | A | PASS |
|
|
|
11/03/97 333 - roof ok to cover
|
INSP - Roof | 10/28/1997 | 10/28/1997 | 10/28/1997 | P | PASS |
|
|
|
10/28/97 333 - mansard ok
|
INSP - Conference | 10/23/1997 | 10/23/1997 | 10/23/1997 | P | PASS |
|
|
|
10/23/97 333 - ok on soffit detail
|
INSP - Carpentry | 10/10/1997 | 10/10/1997 | 10/10/1997 | A | PASS |
|
|
|
10/10/97 333 - resubmittal
|
INSP - Foundation | 10/9/1997 | 10/9/1997 | 10/9/1997 | P | PASS |
|
|
|
10/09/97 333 - STEM WALL FDN -OK FOUNDATION
|
INSP - Footings | 10/8/1997 | 10/8/1997 | 10/8/1997 | P | PASS |
|
|
|
10/08/97 333 - FTG -OK FOOTING
|