Permanent Occupancy | | 6/17/1998 | 6/17/1998 | | DONE |
|
|
|
|
INSP - Final | 5/20/1998 | 5/20/1998 | 5/20/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP - Final | 5/20/1998 | 5/21/1998 | 5/12/1998 | A | PASS |
|
|
|
SIGNED THE OCC REQ CARD FINAL AND DELIVERED TO CATHY
|
INSP - Final | 5/12/1998 | 5/12/1998 | 5/12/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL ON X RAY ROOM FAIL SPKLR HEAD OVERSPACED FROM WALL
|
INSP-Final Inspection | 5/12/1998 | 5/12/1998 | 5/12/1998 | A | PART |
Joe Tawney
|
|
|
05/12/98 406 - ###-#### FINAL ON X RAY ROOM OK STILL NEED MED GAS TEST REPORT TO CLOSE PERMIT
|
INSP-Sprinkler Rough-in/Hydro | 2/2/1998 | 2/2/1998 | 2/2/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST
|
INSP - Final | 12/23/1997 | 12/26/1997 | 12/26/1997 | A | PART |
|
|
|
12/26/97 338 - 5TH FLOOR TELEMETRY phase 1- only for temp occ signed the
|
INSP-Final Inspection | 12/23/1997 | 12/24/1997 | 12/26/1997 | A | PASS |
Joe Tawney
|
|
|
12/24/97 406 - 5TH FLOOR TELEMETRY TOWER/ 10:00 APT FINAL OK FOR TEMP OCC
|
INSP-Final Inspection | 12/18/1997 | 12/19/1997 | 12/19/1997 | P | CANC |
Joe Tawney
|
|
|
12/19/97 406 - FINAL NOT READY INSPECTION CANCELLED
|
INSP - Framing/Rough-in | 10/29/1997 | 10/29/1997 | 10/29/1997 | P | |
|
|
|
NORTH TOWER--5TH FLOOR
|
INSP - Framing/Rough-in | 10/27/1997 | 10/27/1997 | 10/27/1997 | P | PART |
|
|
|
TELEMETRY AT ST AL'S/ 5TH FLOOR this is a partial frame/conference
|
INSP - Framing/Rough-in | 9/26/1997 | 9/29/1997 | 9/29/1997 | A | NR |
|
|
|
09/29/97 338 - not ready for insp want to inspect with 1 layer of rock o
|