Permit Information
Permit NumberBLD97-01095
StatusExpired
Name SCOTT SHEAD
Site Address 350 N MILWAUKEE ST
Project NameBTS - EXPANSION
Customer Number 
ePlanReviewNo
Description
BOISE TOWN SQUARE EXPANSION - TO CONSTRUCT A NEW 91,705 SQ. FT., TWO STORY MALL ADDITION TO THE NORTH SIDE OF THE EXISTING BOISE TOWNE SQUARE MALL TO EXISTING MALL. THIS EXPANSION IS CONSTRUCTED OF CONCRETE SLAB FLOORS, MASONRY EXTERIOR WALLS, STEEL FRAME AND METAL ROOF SYSTEM, AS WELL AS, METAL STUD INTERIOR PARTITIONS. THIS IS FOR THE COMPLETION OF THE MALL AND ACCESSORY PORTIONS OF THIS EXPANSION, BUT DOES NOT INCLUDE THE FINISH OF ANY TENANT SPACES. A SEPARATE TENANT IMPROVEMENT PERMIT IS REQUIRED TO COMPLETE EACH PROPOSED TENANT SPACE. THIS BUILDING ADDITION IS FULLY FIRE SPRINKLED. THE SPRINKLERS ARE USED FOR AREA INCREASE. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR-147-96 CU-106-85/MOD PC236-97/JCM (FIRST FLOOR 47,705 SQ. FT., SECOND FLOOR 44,000 SQ. FT.)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Conference6/29/19986/29/19986/29/1998 PART
Details
/ / 338 - TO SET UP TIME FOR P.M.INSPECTION
INSP - Final6/26/19986/29/19986/29/1998ANR
Details
06/29/98 338 - blaine ###-#### NOT READY OCC REQ CARD NOT ON SITE
INSP - Final6/22/19986/23/19986/24/1998AFAIL
DetailsJim Storey
06/24/98 301 - final blaine/###-####
INSP - Final6/10/19986/11/19986/11/1998APART
Details
06/12/98 338 - Office ###-#### Pager ###-#### Allan Reeser he will be around in the morning to meet you out there
INSP - Conference5/13/19985/13/19985/13/1998 PART
Details
/ / 338 - TEST OF EMERGENCY SYSTEMS FOR SMOKE EVAC SPRINKS AND ALARMS.
INSP-Alarm Testing4/30/19985/13/19985/13/1998APART
DetailsJoe Tawney
05/13/98 406 - ALAN/###-#### - WITNESS AND TEST OF ALARM SYSTEM. 9AM REQ ALARM SYSTEM OK EXC RECALIBRATE BEAM DETECTOR & REPROGRAM MANUAL SWITCHE
INSP - Framing/Rough-in4/22/19984/22/19984/22/1998PPART
Details
04/22/98 338 - ###-####/ALAN - RE-INSP. ON ABOVE CEILING GRID.
INSP - Framing/Rough-in4/16/19984/17/19984/17/1998APART
Details
04/17/98 338 - C/N MADE OK TO DROP IN TILE IINFO CO COME BY FAX ABOVE DR
INSP-Sprinkler Rough-in/Hydro4/17/19984/17/19984/17/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON HYDRO TEST
INSP-Supply line flush3/31/19983/31/19983/31/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON UNDERGROUND FLUSH
INSP - Foundation3/9/19983/10/19983/11/1998PPASS
Details
03/11/98 338 - footings not ready will recall will be ok to pour with sp
INSP - Framing/Rough-in3/9/19983/10/19983/11/1998APART
Details
03/11/98 338 - partial framing allen ###-#### restrooms expansion made o
INSP - Conference3/10/19983/10/19983/10/1998 PASS
Details
/ / 338 - contr. changed insp on frame till early p.m. to be done with
INSP-Sprinkler Rough-in/Hydro3/6/19983/9/19983/9/1998APART
DetailsJoe Tawney
03/09/98 406 - BATHROOM AREA 2ND FLOOR NORTH EAST CORNER ERICK ###-#### OK ON ROUGH IN FOR 2ND FLOOR
INSP - Framing/Rough-in2/18/19982/18/19982/18/1998PNH
DetailsWes Worcester
02/18/98 342 - EXPANSION--ALAN ###-####--PARTIAL reached answering machi
INSP - Framing/Rough-in2/16/19982/17/19982/18/1998APART
DetailsWes Worcester
02/17/98 342 - screw off bottom plate, address penetrations in 1 hr corr blocking
INSP - Conference1/30/19982/3/19982/3/1998PPASS
Details
02/03/98 338 - ###-#### 2:30 is the appointment doug t. (arch) will be there also
INSP - Framing/Rough-in1/20/19981/21/19981/21/1998APASS
Details
01/21/98 338 - MASONARY\ALAN ###-#### ok to pour with spcl insp approva
INSP - Framing/Rough-in1/9/19981/9/19981/9/1998PPART
Details
01/09/98 338 - ###-#### Allen grouting at 2pm masonry wall Strata willbe SP INSP APPROVAL
INSP - Conference12/11/199712/11/199712/12/1997PPASS
Details
12/12/97 338 - met with allen walked the remodel anmd the project ok to floor when weather protection is in place. the special inspector is wit charge to confirm compliance
INSP - Framing/Rough-in12/10/199712/11/199712/12/1997APART
Details
12/11/97 338 - 2ND FLOOR alan called cancelled till tomorrow
INSP - Miscellaneous11/28/199712/1/199712/1/1997APASS
Details
12/01/97 338 - GROUT--ENGINEER LOOKING AT THIS ALSO made ok with the eng
INSP - Foundation10/2/199710/2/199710/2/1997PPASS
Details
10/02/97 338 - SLAB-OK SLAB
INSP - Foundation9/23/19979/23/19979/23/1997PPASS
Details
09/23/97 338 - MADE OK WITH THE BLESSING OF THE SPECIAL INSPECTOR
INSP - Carpentry9/17/19979/18/19979/18/1997AFAIL
Details
09/18/97 338 - 12 foot to the south end and tapered to the north end ble c/n issued for the eng of record to submit fix and demo proceedures prio reconstruction. also stated ubc 3303 for pedestrial protection
INSP - Carpentry9/17/19979/17/19979/17/1997PPASS
Details
09/17/97 338 - SPECIAL INSPECTION AT 12:00 AND 4:00 made ok with sp insp
INSP - Framing/Rough-in9/16/19979/16/19979/16/1997PCANC
Details
09/16/97 338 - SPE. INSPECTOR WILL BE THERE AT 1:30 should be a masonry
INSP - Masonry9/16/19979/16/19979/16/1997 PASS
Details
/ / 338 - for grout cells and reinforcing ok with sp insp approval
INSP - Framing/Rough-in9/12/19979/15/19979/15/1997ACANC
Details
09/15/97 338 - CENTER BLOCK GROUTING SPECIAL INSPECTOR AT 10:30 AND 3:30 masonry grout and reinf
INSP - Framing/Rough-in9/12/19979/15/19979/15/1997PCANC
Details
09/15/97 338 - SPECIAL INSPECTIONthis is to be a masonry
INSP - Masonry9/15/19979/15/19979/15/1997 PASS
Details
/ / 338 - for p.m. bond beam r-bar and grout made ok only with sp insp approval
INSP - Masonry9/15/19979/15/19979/15/1997 PASS
Details
/ / 338 - bond beam and rebar
INSP - Masonry9/15/19979/15/19979/15/1997 PASS
Details
/ / 338 - for bond beam and reinf MASN-REBAR OK
INSP - Masonry9/14/19979/14/19979/14/1997 PASS
Details
/ / 338 - north wall to the 12' ele +- with sp insp approval
INSP - Miscellaneous9/11/19979/12/19979/14/1997APASS
Details
09/12/97 338 - made ik with sp inspa pproval MASN-REBAR OK
INSP - Foundation9/11/19979/11/19979/11/1997PCANC
Details
09/11/97 338 - GROUTING MASNORY WALLS SPEC. INSPECTOR GROUTING AT 4 P.M. this sjould be a masonry insp
INSP - Masonry9/11/19979/11/19979/11/1997 PART
Details
/ / 338 - west wall to the 17' level ok with sp insp approval
INSP - Framing/Rough-in9/10/19979/10/19979/10/1997PCANC
Details
09/10/97 338 - Scheduled by Hello! on 09/10/97 at 08:42:30. pouring concrete for masonery walls
INSP - Masonry9/10/19979/10/19979/10/1997 PART
Details
/ / 338 - poured the 2nd bond bea at the 8-0"level west wall only
INSP - Miscellaneous9/8/19979/9/19979/9/1997APASS
Details
09/09/97 338 - cinderblock MASN-REBAR OK
INSP - Wall cover9/9/19979/9/19979/9/1997PPART
Details
09/09/97 338 - CONCRETE MASONARY WALL HE WILL HAVE A SPECIAL INSPECTOR A need to have confomation of the lack f bond beam over the doorways plan calls for solid grouting to the 8'-0" height.