INSP-Final Inspection | 8/25/1997 | 8/29/1997 | 8/29/1997 | A | PART |
Joe Tawney
|
|
|
08/29/97 406 - hydro final OK ON HYDRO TEST OF 2 SYSTEMS NEED HYDRO ON FDC PIPING OK ON ROUGH IN OF SYSTEMS
|
INSP-Final Inspection | 8/25/1997 | 8/28/1997 | 8/28/1997 | A | CANC |
Joe Tawney
|
|
|
08/27/97 406 - hydro finish CANCELED RESCH FOR 8/29/97
|
INSP-Supply line flush | 8/22/1997 | 8/25/1997 | 8/25/1997 | P | PART |
Joe Tawney
|
|
|
08/25/97 406 - WILL CALL YOU IN MORNING TO CHECK WITH YOU.... OK ON UNDERGROUND FLUSH FOR EAST SHELL BLDG
|
INSP-Final Inspection | 8/22/1997 | 8/22/1997 | 8/22/1997 | P | PART |
Joe Tawney
|
|
|
08/22/97 406 - OK ON UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 8/18/1997 | 8/19/1997 | 8/19/1997 | A | CANC |
|
|
|
08/19/97 338 - not required for commercial const
|
INSP - Framing/Rough-in | 8/11/1997 | 8/12/1997 | 8/11/1997 | A | PASS |
|
|
|
08/12/97 338 - INSULATION OK TO COVER THE EXT WALL FURRING
|
INSP - Framing/Rough-in | 8/8/1997 | 8/8/1997 | 8/8/1997 | P | PASS |
|
|
|
08/08/97 338 - partial on the canopies (sp) madeok with ele insp approva
|
INSP - Masonry | 7/8/1997 | 7/9/1997 | 7/9/1997 | A | PASS |
|
|
|
07/10/97 338 - GROUT MASN-REBAR OK OK WITH SP INSP APPROVAL
|
INSP - Foundation | 7/8/1997 | 7/8/1997 | 7/8/1997 | P | PASS |
|
|
|
07/08/97 338 - made ok with sp insp qapproval MASN-REBAR OK
|
INSP - Masonry | 7/8/1997 | 7/8/1997 | 7/8/1997 | P | PASS |
|
|
|
07/08/97 338 - made ok with sp insp aproval
|
INSP - Foundation | 7/1/1997 | 7/1/1997 | 7/1/1997 | P | PASS |
|
|
|
07/01/97 338 - made ok with sp insp approval
|
INSP - Footings | 6/30/1997 | 6/30/1997 | 7/1/1997 | P | PASS |
|
|
|
06/30/97 338 - made ok with sp insp approval
|
INSP - Foundation | 6/25/1997 | 6/25/1997 | 6/25/1997 | P | PASS |
|
|
|
06/25/97 338 - made ok with sp insp approval
|
INSP - Footings | 6/23/1997 | 6/24/1997 | 6/24/1997 | P | PASS |
|
|
|
06/24/97 338 - made ok with sp insp approval
|
INSP - Foundation | 6/23/1997 | 6/23/1997 | 6/23/1997 | P | PASS |
|
|
|
06/23/97 338 - made ok with sp insp approval
|
INSP - Foundation | 6/19/1997 | 6/20/1997 | 6/20/1997 | P | PART |
Tom Arcoraci
|
|
|
STEM WALL spec insp
|
INSP - Footings | 6/18/1997 | 6/19/1997 | 6/19/1997 | P | PASS |
|
|
|
06/19/97 338 - made ok with sp insp approval
|
INSP - Foundation | 6/17/1997 | 6/18/1997 | 6/18/1997 | A | PASS |
|
|
|
06/18/97 338 - made ok with sp insp approva;
|
INSP - Footings | 6/13/1997 | 6/16/1997 | 6/16/1997 | A | PART |
|
|
|
06/16/97 338 - partial made ok south wall engineering to follow for chan
|