Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD97-01254
StatusFinaled
Name C BENCHMARK CONSTRUCTION
Site Address 6490 S EISENMAN RD
Project NameBURGER KING
Customer Number 
ePlanReviewNo
Description
(BURGER KING)(NEW) TO CONSTRUCT A ONE STORY 4,048 SQ.FT. BURGER KING FACILITY. CONSTRUCTION TO BE WOOD FRAME, TRUSS ROOF SYSTEM, BRICK AND EIF FINISH SYSTEMS, SHEET METAL AND SINGLE PLY ROOFING, INTERIOR TO BE SHEET-ROCKED AND SUSPENDED CEILING. ALL PER APPROVED PLANS ON FILE AND CU-70-96 AND DESIGN REVIEW #28-97. PC 266-97 NEW DRIVE-THROUGH RESTAURANT AND INDOOR PLAYGROUND. DR#28-97 CU#70-96 PC#266-97
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 2/10/19982/10/1998 DONE
Details
INSP-Final Inspection11/19/199711/19/199711/19/1997APASS
DetailsRick Jackson
c/o approved. corrections completed.
INSP - Final11/17/199711/18/199711/18/1997PPART
DetailsRuss Owen
left correction about the resubmital i got after the welding had been commpleted the engineer had wanted special insp. this was not on the approved plans.
INSP - Framing/Rough-in11/12/199711/12/199711/12/1997PPASS
DetailsJim Storey
11/12/97 301 - REIN FOR CEILING GRID SCLG-OK SUSPENDED CEILING
INSP - Framing/Rough-in11/10/199711/10/199711/10/1997PPART
DetailsRuss Owen
CEILING GRID/ BURGER KING STILL NEED A FEW LIGHTS SUPPORTED WITH WIRE.
INSP - Ceiling grid11/7/199711/7/199711/7/1997 FAIL
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in11/6/199711/7/199711/7/1997ACANC
DetailsRuss Owen
11/07/97 407 - CEILING, transfer to jimk st.
INSP - Framing/Rough-in10/21/199710/22/199710/22/1997PPART
DetailsJim Storey
10/22/97 301 - BURGER KING FRAM-OK FRAMING for all but the shaft.
INSP - Framing/Rough-in10/17/199710/20/199710/20/1997PPART
DetailsJim Storey
10/20/97 301 - sheer panels all but west entry ok . tube steel frame nee record to justify planreview notes 9,10,11 weld 1/4 fellets ok.
INSP - Foundation9/23/19979/23/19979/23/1997PPART
DetailsRuss Owen
09/23/97 407 - foundation before pouring floor OK NEED TO HAVE ENGINEEER CLARIFY ANCHOR BOLT ITEM. LEFT CORRECTION OK T EXCEPT AT OWN RISK SUBJECT TO ANY CHANGES REQUIRED BY ENGINEER
INSP - Footings9/23/19979/19/19979/19/1997PPASS
DetailsRuss Owen
CAME BACK AT 1:30 STILL NOT COMPLETELY READY,HAD CREW CLEAN-OUT GROUT CELLS WAITED 1-1/2 SO THE COULD POUR.SAID NEED TO GET DONE TO DO SLAB ON SATURDAY.
INSP - Foundation9/23/19979/19/19979/19/1997PNR
DetailsRuss Owen
NOT READY LEFT CORRECTIONS NOT TO POUR SLAB.
INSP - Foundation9/23/19979/19/19979/19/1997ANR
DetailsRuss Owen
CAME BACK AT 9:30 NOT READY,TOLD THEM I WOULD COME BACK AFTER LUNCH,MASSONRY INSP.
INSP - Foundation9/18/19979/18/19979/19/1997PNR
DetailsRuss Owen
09/18/97 407 - not ready.
INSP - Conference9/11/19979/12/19979/12/1997APART
DetailsRuss Owen
09/12/97 407 - EARLY AM PLEASE ,they wanted to wet set verts told to get engineer, said they would just tie.
INSP - Foundation9/12/19979/12/19979/12/1997PPASS
DetailsRuss Owen
09/12/97 407 - rebar mid afternoon
INSP-Conference7/30/19977/30/19977/30/1997PPASS
Details
drilling and blasting begun, checked for fire dept blasting permit