Permanent Occupancy | | 7/17/1998 | 7/17/1998 | | DONE |
|
|
|
|
INSP - Final | 7/16/1998 | 7/16/1998 | 7/16/1998 | P | PASS |
|
|
|
07/16/98 333 - FNL -OK FINAL
|
INSP - Final | 7/15/1998 | 7/15/1998 | 7/15/1998 | P | PART |
|
|
|
07/15/98 333 - signed for temp cn placed
|
INSP-Final Inspection | 7/15/1998 | 7/15/1998 | 7/15/1998 | A | PASS |
Rick Jackson
|
|
|
occ approved
|
INSP-Final Inspection | 7/14/1998 | 7/14/1998 | 7/14/1998 | P | FAIL |
Rick Jackson
|
|
|
Scott ###-#### sprinkler head painted, room detector not working with test button
|
INSP - Final | 6/30/1998 | 7/1/1998 | 7/1/1998 | P | PART |
|
|
|
07/01/98 333 - temp ok cn placed
|
INSP-Alarm Testing | 6/30/1998 | 6/30/1998 | 6/30/1998 | P | PART |
Rick Jackson
|
|
|
Scheduled by Hello!. Contact phone is [3420479]. sprinkler obstruction by lights in kitchen, NFPA 72 certificate, temp occ approved for south building only
|
INSP-Final Inspection | 6/29/1998 | 6/29/1998 | 6/29/1998 | P | FAIL |
Rick Jackson
|
|
|
ADA room not complete, check elevator recall, CO detectors not installed, sprinkler head in riser room needed, recheck for alarm monitoring
|
INSP-Final Inspection | 6/25/1998 | 6/26/1998 | 6/26/1998 | P | FAIL |
Rick Jackson
|
|
|
Scott ###-#### c/n issued for numerous items.
|
INSP - Framing/Rough-in | 6/24/1998 | 6/25/1998 | 6/25/1998 | A | FAIL |
|
|
|
06/25/98 333 - aconference on final
|
INSP-Sprinkler Rough-in/Hydro | 6/9/1998 | 6/10/1998 | 6/10/1998 | A | PASS |
Rick Jackson
|
|
|
hydro testing/ ###-#### jenifer hydro okay. heads installed in stairs. riser room has numerous pentrations - doesn't meet 1 hour - they aren't finished with room
|
INSP - Framing/Rough-in | 6/8/1998 | 6/8/1998 | 6/8/1998 | P | PART |
|
|
|
06/08/98 333 - conference Scott ###-#### this morning confrerence about attic acess
|
INSP-Sprinkler Rough-in/Hydro | 5/29/1998 | 5/29/1998 | 5/29/1998 | P | PART |
|
|
|
Scheduled by Hello!. Contact phone is [3420479]. the wet system has been fully tented, ok to insulate. The dry pipe penetrations through the attic negate the use of the overbuild sheathing as a draft stop because they are oversized.
|
INSP-Sprinkler Rough-in/Hydro | 5/27/1998 | 5/27/1998 | 5/27/1998 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Hello!. Contact phone is [3420479]. not tented properly. reinspect when ready
|
INSP - Framing/Rough-in | 5/12/1998 | 5/13/1998 | 5/13/1998 | A | FAIL |
|
|
|
05/13/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 4/21/1998 | 4/22/1998 | 4/22/1998 | A | PASS |
|
|
|
04/22/98 333 - 4th floor ok
|
INSP - Framing/Rough-in | 4/20/1998 | 4/20/1998 | 4/20/1998 | P | FAIL |
|
|
|
04/20/98 333 - cn placed
|
INSP - Framing/Rough-in | 4/15/1998 | 4/16/1998 | 4/16/1998 | P | PART |
|
|
|
04/16/98 333 - third floor north ok
|
INSP-Sprinkler Rough-in/Hydro | 4/16/1998 | 4/16/1998 | 4/16/1998 | P | FAIL |
Rick Jackson
|
|
|
###-####/jENNIFER not tented over ends of sprinkler piping
|
INSP - Wall cover | 4/15/1998 | 4/15/1998 | 4/15/1998 | | PASS |
|
|
|
/ / 333 - SOUTH SIDE OK
|
INSP - Framing/Rough-in | 4/14/1998 | 4/14/1998 | 4/14/1998 | P | PASS |
|
|
|
04/14/98 333 - 2nd floor ok
|
INSP - Framing/Rough-in | 4/8/1998 | 4/9/1998 | 4/9/1998 | A | PART |
|
|
|
04/09/98 333 - south tower ok
|
INSP - Framing/Rough-in | 4/8/1998 | 4/8/1998 | 4/8/1998 | | FAIL |
|
|
|
04/08/98 333 - cn not made
|
INSP - Framing/Rough-in | 4/7/1998 | 4/8/1998 | 4/8/1998 | A | PASS |
|
|
|
south side ok
|
INSP - Framing/Rough-in | 4/7/1998 | 4/7/1998 | 4/7/1998 | P | FAIL |
|
|
|
04/07/98 333 - cn not made
|
INSP - Framing/Rough-in | 4/6/1998 | 4/6/1998 | 4/7/1998 | P | PART |
|
|
|
04/06/98 333 - 3rd floor ok
|
INSP - Framing/Rough-in | 4/1/1998 | 4/2/1998 | 4/2/1998 | A | PART |
|
|
|
04/02/98 333 - EXPLAINED CN
|
INSP - Framing/Rough-in | 3/31/1998 | 3/31/1998 | 3/31/1998 | P | FAIL |
|
|
|
03/31/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 3/17/1998 | 3/17/1998 | 3/17/1998 | | PART |
|
|
|
/ / 333 - MET W / SCOTT ABOUT FIRESTOPPING
|
INSP-Sprinkler Rough-in/Hydro | 3/17/1998 | 3/17/1998 | 3/17/1998 | A | PART |
Rick Jackson
|
|
|
attic rough-in okay. Shilo informed of requirement for inspector to check tenting of piping going through unheated attic area.
|
INSP-Supply line flush | 3/17/1998 | 3/17/1998 | 3/17/1998 | P | PASS |
Rick Jackson
|
|
|
|
INSP-Supply line flush | 3/12/1998 | 3/17/1998 | 3/17/1998 | A | NR |
Rick Jackson
|
|
|
shilo - cw moore United Water wasn't requested to open key valve. will request a flush when UW can make it.
|
INSP - Framing/Rough-in | 3/10/1998 | 3/11/1998 | 3/11/1998 | P | FAIL |
|
|
|
03/11/98 333 - need firestops scott ###-####
|
INSP - Framing/Rough-in | 3/3/1998 | 3/4/1998 | 3/4/1998 | A | PART |
|
|
|
03/04/98 333 - fir downs ok to cover SCOTT ###-####
|
INSP - Final | 3/2/1998 | 3/3/1998 | 3/3/1998 | A | FAIL |
|
|
|
03/03/98 333 - not a final conference about 1 hour lids Scheduled by Hello!. Contact phone is [466
|
INSP-Sprinkler Rough-in/Hydro | 3/3/1998 | 3/3/1998 | 3/3/1998 | A | PASS |
Rick Jackson
|
|
|
2,3,4th floors approved for cover. dry system in attic not finished and not approved for cover or tenting.
|
INSP - Framing/Rough-in | 2/23/1998 | 2/24/1998 | 2/24/1998 | A | PART |
|
|
|
02/24/98 333 - reviewed 1hr requirementsSCOTT ###-####
|
INSP - Framing/Rough-in | 2/12/1998 | 2/12/1998 | 2/12/1998 | P | PART |
|
|
|
02/12/98 333 - talked sbout firestopping ###-#### scott
|
INSP-Sprinkler Rough-in/Hydro | 2/10/1998 | 2/11/1998 | 2/11/1998 | A | PASS |
Rick Jackson
|
|
|
###-#### SHELLIE 2nd floor only rough-in okay
|
INSP - Framing/Rough-in | 2/4/1998 | 2/9/1998 | 2/9/1998 | A | PART |
|
|
|
02/09/98 333 - pre frame
|
INSP - Framing/Rough-in | 2/3/1998 | 2/4/1998 | 2/4/1998 | A | PART |
|
|
|
02/04/98 333 - pre frame
|
INSP - Final | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | FAIL |
|
|
|
12/15/97 333 - first floor pour ok
|
INSP - Framing/Rough-in | 12/15/1997 | 12/15/1997 | 12/15/1997 | A | PART |
|
|
|
12/15/97 333 - first floor pour ok
|
INSP - Framing/Rough-in | 12/5/1997 | 12/8/1997 | 12/8/1997 | A | PART |
|
|
|
12/08/97 333 - deck STEEL WELDING
|
INSP - Conference | 12/2/1997 | 12/3/1997 | 12/3/1997 | P | PASS |
|
|
|
12/03/97 333 - talked about welds for deck ul system
|
INSP - Footings | 10/15/1997 | 10/16/1997 | 10/16/1997 | A | NR |
Jim Storey
|
|
|
10/16/97 301 - n/r special insp. pending recall when job is ready for gr
|
INSP - Footings | 10/13/1997 | 10/14/1997 | 10/14/1997 | A | PASS |
|
|
|
10/14/97 333 - around 11:00 please FDN -OK FOUNDATION one half
|
INSP - Foundation | 10/9/1997 | 10/10/1997 | 10/10/1997 | A | PASS |
|
|
|
10/10/97 333 - WOULD PREFER AROUND 11:30 PLEASE FTG -OK FOOTING
|
INSP - Footings | 10/7/1997 | 10/8/1997 | 10/8/1997 | P | PASS |
|
|
|
10/08/97 333 - west half ok
|
INSP - Footings | 10/7/1997 | 10/7/1997 | 10/7/1997 | P | PART |
|
|
|
10/07/97 333 - FTG -OK FOOTING
|