INSP - Final | 5/4/1998 | 5/4/1998 | 5/4/1998 | | PASS |
Jim Storey
|
|
|
05/04/98 301 - FNL -OK FINAL
|
Permanent Occupancy | | 5/4/1998 | 5/4/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 4/22/1998 | 4/22/1998 | 4/22/1998 | P | PASS |
Rick Jackson
|
|
|
fire lanes per approved plans. occ approved
|
INSP - Final | 12/15/1997 | 12/17/1997 | 12/17/1997 | P | PASS |
Jim Storey
|
|
|
12/17/97 301 - FNL -OK FINAL TCO -TEMP C OF O ISSUED routed by contractor.
|
INSP-Final Inspection | 12/17/1997 | 12/17/1997 | 12/17/1997 | P | PART |
Rick Jackson
|
|
|
12/17/97 409 - REINSPECTION fire lanes per approved plans still needed. temp c/o approved.
|
INSP - Final | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | FAIL |
Jim Storey
|
|
|
12/15/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED hand rail. fire damper lables stopping.
|
INSP-Final Inspection | 12/12/1997 | 12/12/1997 | 12/12/1997 | P | FAIL |
Rick Jackson
|
|
|
12/12/97 409 - c/n issued
|
INSP - Framing/Rough-in | 12/3/1997 | 12/3/1997 | 12/3/1997 | P | PART |
Jim Storey
|
|
|
12/03/97 301 - CEILING GRID conf. ok
|
INSP - Framing/Rough-in | 11/18/1997 | 11/19/1997 | 11/19/1997 | A | PASS |
Jim Storey
|
|
|
11/19/97 301 - basement ceilings GWB -OK SHEETROCK NAILING on celling assembly
|
INSP - Framing/Rough-in | 11/10/1997 | 11/12/1997 | 11/12/1997 | A | PASS |
Jim Storey
|
|
|
11/12/97 301 - GWB -OK SHEETROCK NAILING shaft and tunnel in basement.
|
INSP - Framing/Rough-in | 11/5/1997 | 11/5/1997 | 11/6/1997 | P | PART |
Jim Storey
|
|
|
11/05/97 301 - FRAM-OK FRAMING CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 10/30/1997 | 10/30/1997 | 10/30/1997 | P | PART |
Jim Storey
|
|
|
10/30/97 301 - ok to rock exterior walls only
|
INSP - Foundation | 10/1/1997 | 10/2/1997 | 10/2/1997 | A | PASS |
Jim Storey
|
|
|
10/02/97 301 - REBAR FRMS-OK FORMS-REBAR
|
INSP - Footings | 9/19/1997 | 9/22/1997 | 9/22/1997 | A | PASS |
Jim Storey
|
|
|
09/22/97 301 - LATE A.M. FRMS-OK FORMS-REBAR
|
INSP - Foundation | 9/9/1997 | 9/10/1997 | 9/10/1997 | A | PASS |
Jim Storey
|
|
|
09/10/97 301 - FDN -OK FOUNDATION
|
INSP - Footings | 9/4/1997 | 9/5/1997 | 9/5/1997 | A | PASS |
Jim Storey
|
|
|
09/05/97 301 - FRMS-OK FORMS-REBAR out side perimitor
|
INSP - Footings | 8/27/1997 | 8/28/1997 | 8/28/1997 | A | PASS |
Jim Storey
|
|
|
08/28/97 301 - BASEMENT AND RE-BAR FRMS-OK FORMS-REBARfooting ok special insp on line for testing
|