INSP - Final | 3/16/1998 | 3/17/1998 | 3/17/1998 | A | PASS |
Jim Storey
|
|
|
03/17/98 301 - woody ###-#### 45 min road trip for already approved insp.
|
INSP - Final | 3/16/1998 | 3/17/1998 | 3/16/1998 | A | PASS |
Jim Sly
|
|
|
03/16/98 316 - Perm Occ. OK
|
Permanent Occupancy | | 3/16/1998 | 3/16/1998 | | DONE |
|
|
|
|
INSP - Final | 3/12/1998 | 3/13/1998 | 3/13/1998 | A | PART |
Jim Sly
|
|
|
03/12/98 316 - Temp Occ...C/N..Need appr letter from Engineer..Minor des
|
INSP-Final Inspection | 3/13/1998 | 3/13/1998 | 3/13/1998 | P | PASS |
Joe Tawney
|
|
|
03/13/98 406 - woody ###-#### REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 3/12/1998 | 3/12/1998 | 3/12/1998 | P | FAIL |
Joe Tawney
|
|
|
03/12/98 406 - ECONO LUBE--WOODY ###-#### REINSP FAIL INSTALATION OF TANKS WITH VENTS INSTALLED
|
INSP-Final Inspection | 3/11/1998 | 3/11/1998 | 3/11/1998 | P | NR |
Jim Sly
|
|
|
03/11/98 316 - NR..............
|
INSP - Final | 3/6/1998 | 3/9/1998 | 3/9/1998 | P | FAIL |
Jim Sly
|
|
|
03/09/98 316 - ECONO LUBE-C/N..Handrails, letter appr spec insp, Need al
|
INSP-Final Inspection | 3/6/1998 | 3/9/1998 | 3/9/1998 | A | PART |
Joe Tawney
|
|
|
03/09/98 406 - ECONO LUBE--WOODY ###-#### FINAL OK FOR TEMP OCC BLDG ADDRESS REVIEW OF ART 79 80 & 81 FOR LUBE TAN
|
INSP - Framing/Rough-in | 2/11/1998 | 2/12/1998 | 2/12/1998 | A | PASS |
Tom Arcoraci
|
|
|
02/12/98 408 - econo lube ###-#### needs ok for eng of record to change roof from a class a to as built
|
INSP - Conference | 1/8/1998 | 1/8/1998 | 1/8/1998 | P | PASS |
Jim Sly
|
|
|
01/08/98 316 - New Job super...Talked about inspection requirements.
|
INSP - Foundation | 12/17/1997 | 12/18/1997 | 12/18/1997 | A | PART |
Jim Sly
|
|
|
12/18/97 316 - OK pending special insp approval....
|
INSP - Carpentry | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | PART |
Jim Sly
|
|
|
12/12/97 316 - Poured North wall and walls around sevice bays OK pending
|
INSP - Footings | 12/10/1997 | 12/10/1997 | 12/10/1997 | P | PART |
Tom Arcoraci
|
|
|
12/10/97 408 -
|
INSP - Foundation | 12/5/1997 | 12/8/1997 | 12/8/1997 | A | PART |
Jim Sly
|
|
|
12/05/97 316 - North found wall ..OK pending special insp approval...
|
INSP - Foundation | 12/3/1997 | 12/3/1997 | 12/3/1997 | P | PART |
Tom Arcoraci
|
|
|
REBAR POURING AT 2:30 spec inspec on site
|
INSP - Footings | 12/1/1997 | 12/2/1997 | 12/2/1997 | P | PART |
Jim Sly
|
|
|
12/02/97 316 - ECONO LUBE OK Pending special inspection approval.....
|
INSP - Foundation | 11/25/1997 | 11/26/1997 | 11/26/1997 | P | PART |
Jim Sly
|
|
|
11/26/97 316 - ECONO LUBE--OK pending special inspector approval..found
|
INSP - Footings | 11/20/1997 | 11/21/1997 | 11/21/1997 | P | PART |
Jim Sly
|
|
|
11/21/97 316 - rebar For foot 1st pour..OK pending special insp. approva
|