Permanent Occupancy | | 2/2/1999 | 2/2/1999 | | DONE |
|
|
|
|
INSP - Final | 6/30/1998 | 6/30/1998 | 6/30/1998 | P | PASS |
|
|
|
06/30/98 338 - dale ###-#### MADE OK SIGNED THE PERM COL OF OCC REQ CARD
|
INSP - Final | 5/18/1998 | 5/18/1998 | 5/18/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP - Final | 5/14/1998 | 5/14/1998 | 5/15/1998 | P | NR |
|
|
|
05/15/98 338 - NEED FIRE SIGNOFF
|
INSP-Conference | 4/14/1998 | 4/14/1998 | 4/14/1998 | | PART |
|
|
|
PRE REINSP CONFERENCE WITH JOB SUPT
|
INSP-Final Inspection | 4/1/1998 | 4/2/1998 | 4/2/1998 | A | NR |
Joe Tawney
|
|
|
04/02/98 406 - dale ###-#### NOT READY INSP CANCELLED WILL RESCHED ì
|
INSP - Final | 4/1/1998 | 4/2/1998 | 4/1/1998 | A | CANC |
|
|
|
04/02/98 338 - dale called and cancelled pending ok from fire insp 406
|
INSP - Final | 3/26/1998 | 3/27/1998 | 3/27/1998 | P | NR |
|
|
|
03/27/98 338 - DALE WILL CALL YOU TO SCHEDULE--JOE GOING IN AM OTH-OTHER AGENCIES NOT APPROVED will reschedule next week
|
INSP-Final Inspection | 3/26/1998 | 3/27/1998 | 3/27/1998 | A | FAIL |
Joe Tawney
|
|
|
03/27/98 406 - costco ###-#### dale FINAL FAIL HIGH PILED STORAGE ISSUE NOT RESOLVED
|
INSP-Final Inspection | 3/24/1998 | 3/25/1998 | 3/25/1998 | P | PASS |
Joe Tawney
|
|
|
03/25/98 406 - final for the whole job-mike ###-#### SPKLR INSP OK GRINNEL FIRE PROT
|
INSP - Framing/Rough-in | 3/13/1998 | 3/13/1998 | 3/13/1998 | P | PART |
|
|
|
03/13/98 338 - ceiling in the food court ok to drop in the tilesceiling
|
INSP-Final Inspection | 3/11/1998 | 3/11/1998 | 3/11/1998 | P | PASS |
Joe Tawney
|
|
|
03/12/98 406 - nick ###-####-food court area SPKLR ROUGH IN OK FOOD COURT AREA
|
INSP - Framing/Rough-in | 3/5/1998 | 3/6/1998 | 3/6/1998 | A | PASS |
|
|
|
03/06/98 338 - shafts in the rear made ok ASAP PLEASE--DELI CHIX AREA--D
|
INSP - Framing/Rough-in | 2/26/1998 | 2/27/1998 | 2/27/1998 | P | PASS |
|
|
|
02/27/98 338 - FOOD COURT AT COSTCO--DALE ###-####made ok 02/26/98
|
INSP - Framing/Rough-in | 2/23/1998 | 2/23/1998 | 2/23/1998 | P | PART |
|
|
|
02/23/98 338 - dale ###-#### conference
|
INSP-Sprinkler Rough-in/Hydro | 1/20/1998 | 1/28/1998 | 1/28/1998 | A | PASS |
Joe Tawney
|
|
|
01/28/98 406 - ###-#### ROUGH IN OK ON HEADS INSTALLED IN PHARMACY
|
INSP - Framing/Rough-in | 1/26/1998 | 1/27/1998 | 1/27/1998 | P | PART |
|
|
|
01/27/98 338 - COSTCO\\###-#### CEILINGS OK TO DROP IN TILES AT PHARM.
|
INSP - Framing/Rough-in | 1/14/1998 | 1/15/1998 | 1/15/1998 | P | PASS |
Tom Arcoraci
|
|
|
3ostco Dale ###-#### OK FOR COVER AFTER ELEC AND PLUMB ROUGH
|
INSP - Conference | 12/11/1997 | 12/11/1997 | 12/11/1997 | | PASS |
|
|
|
/ / 338 - made ok
|
INSP - Framing/Rough-in | 12/4/1997 | 12/5/1997 | 12/5/1997 | A | PART |
|
|
|
/ / 338 - ok to cover with the ele division approval e
|
INSP-Sprinkler Rough-in/Hydro | 11/25/1997 | 12/1/1997 | 12/2/1997 | P | PASS |
Joe Tawney
|
|
|
12/01/97 406 - OK ON HYDRO TEST FOR SPKLR ADDITION IN TIRE SHOP
|
INSP - Roof | 11/21/1997 | 11/24/1997 | 11/24/1997 | A | PASS |
|
|
|
EARLY AM PLEASE NAILING OK STR STRAPS PER THE APPROVED PLAN
|
INSP - Footings | 10/24/1997 | 10/27/1997 | 10/27/1997 | P | PASS |
|
|
|
READY AT 1:00 R-BAR PLACED SP INSP ON SITE
|