Permanent Occupancy | | 8/25/1998 | 8/25/1998 | | DONE |
|
|
|
|
INSP - Final | 2/26/1998 | 2/26/1998 | 2/26/1998 | P | CANC |
Jim Storey
|
|
|
|
INSP - Final | 2/26/1998 | 2/26/1998 | 2/26/1998 | P | FAIL |
|
|
|
02/27/98 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP-Final Inspection | 2/26/1998 | 2/26/1998 | 2/26/1998 | P | PASS |
Rick Jackson
|
|
|
called in by contractor - Don for 1:30 all items corrected
|
INSP-Sprinkler Rough-in/Hydro | 2/24/1998 | 2/25/1998 | 2/26/1998 | P | PART |
Rick Jackson
|
|
|
02/25/98 409 - shelly ###-#### rough-in of attic area completed and okay. they will retent. all other corrected. draft stops not complete at far south and north ends. temp o approved.
|
INSP-Final Inspection | 2/24/1998 | 2/24/1998 | 2/24/1998 | A | FAIL |
Rick Jackson
|
|
|
correction notice issued. must verify sprinkler piping in attic, knox box, alarm plans, PIV lock, accessible room alarms, inspecotrs test door in room 22, hydraulic data nameplate on riser
|
INSP - Final | 2/20/1998 | 2/23/1998 | 2/23/1998 | A | NR |
Jim Storey
|
|
|
02/23/98 301 - ###-#### DON trans to kim via cell phone.
|
INSP-Final Inspection | 2/23/1998 | 2/23/1998 | 2/23/1998 | P | NR |
Rick Jackson
|
|
|
DON ###-#### corrections from 2/20 not completed. alarms/sprinkler not ready.
|
INSP - Framing/Rough-in | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PART |
|
|
|
02/19/98 333 - pre final PRELIM CONF WITH DON AT ###-####
|
INSP-Final Inspection | 2/18/1998 | 2/19/1998 | 2/19/1998 | P | PART |
Joe Tawney
|
|
|
02/19/98 406 - SHELLIE ###-#### OK ON UNDERGROUND FLUSH & ABOVE GROUND HYDRO TESTS EXCEPT FOR FDC PIPING
|
INSP-Sprinkler Rough-in/Hydro | 2/18/1998 | 2/19/1998 | 2/19/1998 | A | FAIL |
Joe Tawney
|
|
|
02/19/98 406 - SHELLIE ###-#### UNDERGROUND HYDRO TEST FAIL RESTRICTION IN PIPE OR PIV VLV
|
INSP-Conference | 1/27/1998 | 1/27/1998 | 1/27/1998 | A | PART |
Rick Jackson
|
|
|
basement requirements, reviewed plans.
|
INSP-Conference | 1/5/1998 | 1/7/1998 | 1/7/1998 | P | PART |
Rick Jackson
|
|
|
01/07/98 409 - relocated water main, riser in basement, outside valve/on question. architect was going to be on-site today to see if one hour co done.
|