BLD-Final | 11/4/1999 | 11/4/1999 | 11/4/1999 | P | PASS |
|
|
|
Ok for L/C
|
INSP - Final | 4/9/1999 | 4/9/1999 | 4/9/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION ON SHELL
|
INSP-Conference | 4/1/1999 | 4/1/1999 | 4/1/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/DAVE TUCKER REG SIGN OFF OF PERMIT
|
INSP - Final | 12/21/1998 | 12/21/1998 | 12/21/1998 | | PART |
|
|
|
12/21/98 338 - c/n issued need fire; ele; p/z; and mech perm sign-off
|
INSP - Final | 12/18/1998 | 12/18/1998 | 12/18/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC CONTROL VLV SUPR, ACCELERATOR
|
INSP-Final Inspection | 12/17/1998 | 12/17/1998 | 12/17/1998 | P | FAIL |
Joe Tawney
|
|
|
12/17/98 406 - dwayne- ###-#### fn fire REINSP FAIL ACCEL FAILED DUCT DET CONTROL VLV MONITORING
|
INSP-Final Inspection | 12/4/1998 | 12/7/1998 | 12/7/1998 | P | FAIL |
Joe Tawney
|
|
|
12/07/98 406 - dwayne ###-#### fn fire per joe 1? REINSP FAIL SPKLR SYSTEM DUCT DET
|
INSP - Final | 12/2/1998 | 12/4/1998 | 12/4/1998 | A | FAIL |
|
|
|
12/04/98 338 - OTHER AGENCIES NOT APPROVED
|
INSP - Final | 12/3/1998 | 12/3/1998 | 12/3/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL FAIL SPKLR SYSTEM NOT READY FOR TEST
|
INSP-Sprinkler Rough-in/Hydro | 10/9/1998 | 10/12/1998 | 10/12/1998 | P | PART |
Joe Tawney
|
|
|
10/12/98 406 - brian ###-#### r-in spr insp-early if possible OK ROUGH IN OF SHELL & 1ST FLR OK HYDRO TEST 1ST FLR
|
INSP-Sprinkler Rough-in/Hydro | 6/3/1998 | 6/3/1998 | 6/3/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST OF FDC
|
INSP-Sprinkler Rough-in/Hydro | 5/29/1998 | 5/29/1998 | 5/29/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST EXCEPT FDC PIPING
|
INSP-Supply line flush | 5/29/1998 | 5/29/1998 | 5/29/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 3/30/1998 | 3/30/1998 | 3/31/1998 | P | PASS |
Jim Storey
|
|
|
03/30/98 301 - RF -OK ROOF NAILING
|
INSP - Framing/Rough-in | 3/18/1998 | 3/18/1998 | 3/18/1998 | P | PART |
|
|
|
03/18/98 338 - nailing robbie edmans -nails in deck penetrate to far int
|
INSP - Framing/Rough-in | 3/18/1998 | 3/18/1998 | 3/18/1998 | | PASS |
|
|
|
/ / 338 - with cornell larson, will get nailing problems resolved and,
|
INSP - Framing/Rough-in | 1/26/1998 | 1/26/1998 | 1/26/1998 | P | PART |
|
|
|
01/26/98 338 - robert ###-#### made ok r-bar placed ok to pour with sp i to re-check panel # 5
|
INSP - Foundation | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | PASS |
|
|
|
01/07/98 338 - made ok with sp insp approval
|
INSP - Footings | 12/29/1997 | 12/30/1997 | 12/30/1997 | A | PASS |
|
|
|
12/30/97 338 - made ok with sp insp papproval
|
INSP - Footings | 12/17/1997 | 12/17/1997 | 12/18/1997 | P | PASS |
|
|
|
12/17/97 338 - made ok with the ok from the special inspector
|
INSP - Footings | 12/16/1997 | 12/16/1997 | 12/16/1997 | P | CANC |
Dave Lightfoot
|
|
|
12/16/97 337 -
|
INSP - Framing/Rough-in | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | CANC |
|
|
|
12/15/97 338 - this is to be concrete reinforcing for tilt up walls
|
INSP - Framing/Rough-in | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | CANC |
|
|
|
12/15/97 338 - this is to be a reinforcing inspection for tilt up walls
|
INSP - Footings | 11/10/1997 | 11/12/1997 | 11/12/1997 | A | PART |
|
|
|
center col forms only ok after sp insp approval
|