BLD-Final | 9/27/1999 | 9/27/1999 | 9/27/1999 | A | PASS |
|
|
|
made ok for l/c
|
INSP - Final | 6/23/1999 | 6/23/1999 | 6/23/1999 | P | FAIL |
|
|
|
06/23/99 338 - achd not approved
|
INSP - Framing/Rough-in | 6/14/1999 | 6/15/1999 | 6/15/1999 | A | FAIL |
|
|
|
06/15/99 338 - need to complete assys as per details
|
INSP - Framing/Rough-in | 6/15/1999 | 6/15/1999 | 6/15/1999 | | FAIL |
|
|
|
06/15/99 338 - need fix on the horiz. beam at the east prop line wall
|
INSP - Final | 6/7/1999 | 6/7/1999 | 6/7/1999 | P | FAIL |
|
|
|
06/07/99 338 - MUST FOLLOW ASSEMBLIES SUBMITTED SLOPPY WORK
|
INSP - Final | 6/2/1999 | 6/2/1999 | 6/2/1999 | | FAIL |
|
|
|
06/02/99 338 - cancelled will reschedule
|
INSP-Final Inspection | 5/26/1999 | 5/27/1999 | 5/27/1999 | P | PASS |
Rick Jackson
|
|
|
2pm Doug ###-#### occ approved
|
INSP - Framing/Rough-in | 5/14/1999 | 5/17/1999 | 5/17/1999 | P | FAIL |
|
|
|
conference/ Joe ###-#### c/n on the final need assy for the wall to floor deck at the stair rated walls and the redo of the fire proofing of the east I beam at each level this work is to be done per the plan approved by 338 in its complete detail.
|
INSP - Final | 5/11/1999 | 5/12/1999 | 5/12/1999 | P | FAIL |
|
|
|
05/12/99 338 - other agencies not approved
|
INSP-Final Inspection | 5/11/1999 | 5/12/1999 | 5/12/1999 | P | FAIL |
Rick Jackson
|
|
|
###-#### KEN//FIRE & LIFE SAFETY alarm plans not approved; access road not complete; elevator not working; address; tampers not wired properly
|
INSP - Framing/Rough-in | 4/21/1999 | 4/21/1999 | 4/30/1999 | P | PART |
|
|
|
04/26/99 338 - ok to drop in the tiles
|
INSP-Conference | 3/29/1999 | 3/30/1999 | 3/30/1999 | A | PART |
|
|
|
03/30/99 338 - made ok for conf
|
INSP - Framing/Rough-in | 2/18/1999 | 2/19/1999 | 2/19/1999 | A | PART |
Jim Storey
|
|
|
02/19/99 301 - 2nd and 3hrd floor line east wall ok.
|
INSP - Framing/Rough-in | 2/15/1999 | 2/16/1999 | 2/16/1999 | A | PART |
|
|
|
02/16/99 338 - made ok to cover ext walls only
|
INSP - Energy code compliance | 2/2/1999 | 2/2/1999 | 2/2/1999 | P | PART |
|
|
|
02/02/99 338 - madeok for the details of the heater protection and the v
|
INSP - Framing/Rough-in | 2/1/1999 | 2/1/1999 | 2/1/1999 | P | PART |
|
|
|
02/01/99 338 - made ok to cover the rest room areas only
|
INSP - Framing/Rough-in | 1/28/1999 | 1/29/1999 | 1/29/1999 | A | NR |
Carl Dependahl
|
|
|
01/29/99 340 - KEN SKAGGS ###-#### FR INSP unable to contact
|
INSP - Framing/Rough-in | 1/25/1999 | 1/25/1999 | 1/25/1999 | P | PART |
|
|
|
MADE OK FO TPOUR
|
INSP-Conference | 1/7/1999 | 1/7/1999 | 1/7/1999 | A | PART |
Rick Jackson
|
|
|
informed general contractor that the alarm plans have not been submitted and approved. electrical contractor was calling simplex as I was leaving...
|
INSP - Framing/Rough-in | 11/18/1998 | 11/19/1998 | 11/19/1998 | A | PART |
|
|
|
11/19/98 333 - resub on efis system
|
INSP - Framing/Rough-in | 11/12/1998 | 11/12/1998 | 11/12/1998 | A | PART |
|
|
|
11/12/98 333 - north wall efis exterior only ok
|
INSP - Framing/Rough-in | 10/22/1998 | 10/27/1998 | 10/27/1998 | A | PART |
|
|
|
10/27/98 333 - pre con
|
INSP-Conference | 10/27/1998 | 10/27/1998 | 10/27/1998 | A | PART |
Rick Jackson
|
|
|
pre-con meeting with Kim M. Sprinkler plans from State FM not on site and alarm plans not approved - requested both from K2 contractors
|
INSP - Framing/Rough-in | 10/20/1998 | 10/21/1998 | 10/21/1998 | P | FAIL |
|
|
|
10/21/98 333 - conference on handrails clearances to wall not correct
|
INSP - Concrete | 9/23/1998 | 9/24/1998 | 9/24/1998 | A | PASS |
|
|
|
09/24/98 333 - north half slab ok
|