INSP - Final | 11/4/1998 | 11/5/1998 | 11/5/1998 | A | PASS |
Russ Owen
|
|
|
DOUG--###-#### WESTERN TRAILERS MANUF BLDG
|
Permanent Occupancy | | 11/5/1998 | 11/5/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/26/1998 | 10/26/1998 | 10/26/1998 | P | PASS |
Rick Jackson
|
|
|
re-inspection for final occ approved
|
INSP - Final | 10/23/1998 | 10/23/1998 | 10/23/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok for 90 day temp.
|
INSP - Final | 10/22/1998 | 10/23/1998 | 10/23/1998 | P | FAIL |
|
|
|
10/23/98 333 - given to jim2 ì
|
INSP-Final Inspection | 10/22/1998 | 10/23/1998 | 10/23/1998 | P | PART |
Rick Jackson
|
|
|
doug ###-#### NFPA 704 for storage area; NFPA 72
|
INSP-Final Inspection | 10/14/1998 | 10/15/1998 | 10/15/1998 | A | CANC |
Rick Jackson
|
|
|
MIKE ###-#### PAINT BOOTH inspection was for the paint booth under BLD97-3293
|
INSP - Framing/Rough-in | 10/13/1998 | 10/13/1998 | 10/13/1998 | P | PART |
Russ Owen
|
|
|
10/13/98 407 - cameron ###-#### conference
|
INSP - Final | 9/24/1998 | 9/25/1998 | 9/25/1998 | P | PART |
Russ Owen
|
|
|
09/25/98 407 - This is for a temporary only in the shop area,I have talk and mechanical,an Fire will be out later today,If Fire ok then they may occupy shop only.
|
INSP-Sprinkler Rough-in/Hydro | 9/24/1998 | 9/25/1998 | 9/25/1998 | P | PART |
Rick Jackson
|
|
|
CAMERON ###-#### temp occ approved for remainder of FAB; offices not ready
|
INSP-Final Inspection | 9/22/1998 | 9/23/1998 | 9/23/1998 | P | PART |
Rick Jackson
|
|
|
mike ###-#### tested the office/shop area riser flow switch - okay. not a final occupancy request
|
INSP - Framing/Rough-in | 9/17/1998 | 9/18/1998 | 9/18/1998 | A | PART |
Russ Owen
|
|
|
09/18/98 407 - ok to occupy a portion of shop.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/1998 | 9/18/1998 | 9/18/1998 | A | PART |
Rick Jackson
|
|
|
CAMERON ###-####-FIRST HALF OF MAN BLD-CALL 1ST approval for occ in additional 2 stalls okay. see floor plan ot job site for location. upstairs office area - sprinkler head overspaced; water heater room has no lid - recheck this room
|
INSP - Framing/Rough-in | 9/15/1998 | 9/16/1998 | 9/16/1998 | A | PART |
Russ Owen
|
|
|
09/16/98 407 - left corrections for t-bar .
|
INSP - Framing/Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 | P | PART |
Russ Owen
|
|
|
09/11/98 407 - ok to occupie small section at corner as on plan.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/1998 | 9/11/1998 | 9/11/1998 | P | PART |
Rick Jackson
|
|
|
DOUG ###-#### partial temp occ inspection - west bays approved only. tested alarms and sprinkler
|
INSP-Sprinkler Rough-in/Hydro | 9/4/1998 | 9/4/1998 | 9/4/1998 | P | PASS |
Rick Jackson
|
|
|
MIKE ###-#### hydro pass
|
INSP - Final | 8/31/1998 | 9/3/1998 | 9/3/1998 | A | FAIL |
|
|
|
09/03/98 335 - ###-#### TEMP OCC 10:00 AS PER INSPECTOR CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 8/31/1998 | 9/3/1998 | 9/3/1998 | A | FAIL |
Rick Jackson
|
|
|
###-#### TEMP OCC 10:00 AS PER INSPECTOR emergency lights, exit lights, sprinkler monitoring, PIV too low
|
INSP - Conference | 8/27/1998 | 8/27/1998 | 8/27/1998 | A | PART |
Russ Owen
|
|
|
/ / 407 - meet with owner contractor fire/electrical and others for a
|
INSP-Conference | 8/24/1998 | 8/27/1998 | 8/27/1998 | A | PART |
Rick Jackson
|
|
|
DOUG ###-#### discussed requirements for temp: fusible links for vents to above 286F; extinguishers; emergency lights; sprinkler monitoring; testing alarms; access; etc
|
INSP-Sprinkler Rough-in/Hydro | 8/24/1998 | 8/24/1998 | 8/24/1998 | P | CANC |
Rick Jackson
|
|
|
mike ###-#### this is for the paint booth
|
INSP-Sprinkler Rough-in/Hydro | 8/19/1998 | 8/20/1998 | 8/20/1998 | A | FAIL |
Rick Jackson
|
|
|
MIKE ###-#### couldn't keep flow going due to hose problems
|
INSP-Supply line flush | 8/20/1998 | 8/20/1998 | 8/20/1998 | P | PASS |
Rick Jackson
|
|
|
reinspect from 8/20 am underground flush okay for paint booth
|
INSP-Sprinkler Rough-in/Hydro | 8/6/1998 | 8/7/1998 | 8/7/1998 | A | PART |
|
|
|
MFG AREA AND 2ND FLOOR OFICE HYDRO OK...CORRECTIONS LEFT FOR ROUGHIN...1ST OFFICE NOT HYDRO. PAINT BOOTH CONNECTED W/O HYDRO. TOLD H/R SUPR THAT FLUSH UG AND PIPING NOW REQ'D
|
INSP-Sprinkler Rough-in/Hydro | 7/15/1998 | 7/20/1998 | 7/20/1998 | A | PART |
Rick Jackson
|
|
|
late a.m. mike ###-#### underground hydro and flush okay. installation of main shop not complete. paint booth requires all inspections (flush, hydros, rouhg-in)
|
INSP - Framing/Rough-in | 5/20/1998 | 5/20/1998 | 5/21/1998 | P | PART |
Russ Owen
|
|
|
05/20/98 407 - subject to inspection reports from special inspector.
|
INSP - Framing/Rough-in | 5/18/1998 | 5/19/1998 | 5/19/1998 | A | PASS |
Jim Storey
|
|
|
05/19/98 301 - FRMS-OK FORMS-REBAR 2 ND LIFT OF MASSONARY
|
INSP - Concrete | 4/2/1998 | 4/3/1998 | 4/3/1998 | A | PART |
Russ Owen
|
|
|
04/03/98 407 - footins and walls have been poured prior to any city insp indicated MTI special inspector at site before all pours.
|