BLD-Final | 10/8/1999 | 10/11/1999 | 10/9/1999 | A | PASS |
|
|
|
Final reinspect for the Amerisuites Hotel
|
Permanent Occupancy | | 10/8/1999 | 10/8/1999 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/7/1999 | 10/5/1999 | 10/5/1999 | P | PASS |
Joe Tawney
|
|
|
reinsp ok for permanent occupancy
|
INSP-Final Inspection | 5/12/1999 | 5/12/1999 | 5/12/1999 | P | NR |
Joe Tawney
|
|
|
05/12/99 406 - not ready allC/N items not completed
|
INSP-Conference | 1/22/1999 | 1/22/1999 | 1/22/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CHECKED LOCATION OF HYDRANTS AT SITE TO VERIFY ADEQUATE WATE OK
|
INSP - Final | 1/11/1999 | 1/11/1999 | 1/11/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR FULL TEMP OCC
|
INSP - Final | 1/11/1999 | 1/11/1999 | 1/11/1999 | | PART |
|
|
|
/ / 338 - MADE OK FOR TEMP SIGNED THE TEMP COLSTILL NEED HARD COPY OF
|
INSP - Final | 1/7/1999 | 1/7/1999 | 1/7/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - FINAL OK FOR LIMITED TEMP OCC NO PUBLIC ACCESS AT THIS TIME.
|
INSP - Final | 1/6/1999 | 1/6/1999 | 1/6/1999 | | PART |
|
|
|
/ / 338 - made ok for conditionaql temporary occ cert for hotel person
|
INSP-Final Inspection | 1/4/1999 | 1/5/1999 | 1/5/1999 | A | NR |
Joe Tawney
|
|
|
01/05/99 406 - Preston ###-#### FINAL NOT READY
|
INSP - Final | 12/30/1998 | 12/31/1998 | 12/31/1998 | A | FAIL |
Tom Arcoraci
|
|
|
12/31/98 408 - preston- ###-#### temp occ insp NOT READY WITH FIRE INSPECTOR
|
INSP-Final Inspection | 12/30/1998 | 12/31/1998 | 12/31/1998 | A | FAIL |
Rick Jackson
|
|
|
preston- ###-#### fn fire insp tested sprinkler alarms only. corridors and stairtowers not complete.
|
INSP-Final Inspection | 12/31/1998 | 12/31/1998 | 12/31/1998 | | FAIL |
Rick Jackson
|
|
|
12/31/98 409 - preston- ###-#### fn fire insp tested sprinkler alarm portion only. stair towers and corridors, alarms
|
INSP-Final Inspection | 12/14/1998 | 12/17/1998 | 12/17/1998 | A | PART |
Joe Tawney
|
|
|
12/17/98 406 - ERIC PAGER ###-#### PER JOE 9:00 FN INSP
|
INSP-Conference | 12/14/1998 | 12/14/1998 | 12/14/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - PROFIT MEETING WITH ALL INSPECTORS, CONTRACTOR AND SUB CONTR
|
INSP - Framing/Rough-in | 12/10/1998 | 12/11/1998 | 12/11/1998 | A | PART |
|
|
|
12/11/98 338 - made ok to drop in he tile in east hall 1st floor
|
INSP - Final | 12/10/1998 | 12/10/1998 | 12/10/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST OF 1ST & 2ND FLRS, OK ON BOOSTER PUMP TEST
|
INSP - Wall cover | 11/13/1998 | 11/16/1998 | 11/16/1998 | A | PART |
|
|
|
11/14/98 338 - PRESTON ###-#### WALL COVER INSP madeok to cover restroom
|
INSP - Framing/Rough-in | 11/9/1998 | 11/10/1998 | 11/10/1998 | A | FAIL |
|
|
|
11/10/98 338 - PRESTON BAKER- ###-####-2ND FLOOR BATHROOMS fail penetrat
|
INSP - Framing/Rough-in | 11/6/1998 | 11/9/1998 | 11/9/1998 | A | PART |
|
|
|
11/09/98 338 - made ok to cover the 2nd floor and the rest of the 3rd fl
|
INSP - Framing/Rough-in | 11/4/1998 | 11/4/1998 | 11/5/1998 | P | PART |
Tom Arcoraci
|
|
|
11/04/98 408 - 3RD FLOOR BATHROOM--PRESTON ###-#### ok to cover 3rd floor
|
INSP - Framing/Rough-in | 11/2/1998 | 11/2/1998 | 11/2/1998 | P | PART |
|
|
|
11/03/98 338 - ok to cover east end of 4 th floor
|
INSP-Sprinkler Rough-in/Hydro | 10/27/1998 | 10/27/1998 | 10/27/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - ok on hydro test of 3rd & 4th flrs, underground,FDC,DPV,& st
|
INSP - Framing/Rough-in | 10/22/1998 | 10/23/1998 | 10/23/1998 | A | PART |
|
|
|
10/23/98 338 - COVER INSPECTION PRESTON ###-#### ok to cover parts of th
|
INSP - Wall cover | 10/19/1998 | 10/20/1998 | 10/20/1998 | A | FAIL |
|
|
|
10/20/98 338 - fire caulk putty pads not complet no cover
|
INSP - Wall cover | 10/15/1998 | 10/15/1998 | 10/15/1998 | P | PART |
|
|
|
MADE K TO COVER 4TH FLOOR WALLS BETWEEN SUITES
|
INSP - Framing/Rough-in | 9/29/1998 | 10/13/1998 | 10/13/1998 | A | FAIL |
|
|
|
10/13/98 338 - need eng for the holes cut in bearing/ demising walls
|
INSP - Wall cover | 10/9/1998 | 10/13/1998 | 10/13/1998 | A | PART |
Tom Arcoraci
|
|
|
10/13/98 408 - preston ###-#### done by 338
|
INSP - Wall cover | 10/13/1998 | 10/13/1998 | 10/13/1998 | | PART |
|
|
|
/ / 338 - MADD OK RECIEVED ENG FIX FOR RE ROUT OF STORM DRAINS
|
INSP - Framing/Rough-in | 9/29/1998 | 10/12/1998 | 10/12/1998 | A | NR |
|
|
|
10/12/98 338 - will call for insp for 10-13-98
|
INSP - Framing/Rough-in | 9/29/1998 | 10/9/1998 | 10/9/1998 | A | PART |
|
|
|
10/09/98 338 - conference on the plans review and approved plans and the
|
INSP - Framing/Rough-in | 9/29/1998 | 10/8/1998 | 10/8/1998 | A | PART |
|
|
|
10/08/98 338 - made ok to cover the 1st floor all penetrations made ok.
|
INSP - Framing/Rough-in | 9/29/1998 | 10/7/1998 | 10/7/1998 | A | FAIL |
|
|
|
10/07/98 338 - PROPER ASSYS NOT ON SITE NO INSP MADE
|
INSP - Framing/Rough-in | 9/29/1998 | 10/6/1998 | 10/6/1998 | A | NR |
|
|
|
10/06/98 338 - not ready assys were not on site inspection will not be d
|
INSP-Supply line flush | 10/6/1998 | 10/6/1998 | 10/6/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SUPPLY LINE FLUSH OK ON 4TH FLR ROUGH IN
|
INSP - Framing/Rough-in | 9/29/1998 | 10/5/1998 | 10/5/1998 | A | NR |
|
|
|
10/05/98 338 - need fire stop info prior to inspection
|
INSP - Framing/Rough-in | 9/29/1998 | 10/2/1998 | 10/2/1998 | A | FAIL |
|
|
|
subs do not have proper info not ready no insp completed
|
INSP - Framing/Rough-in | 10/2/1998 | 10/2/1998 | 10/2/1998 | | PART |
|
|
|
10/02/98 338 - MADE OK TO COVER PART OF THE 3RD FLOOR EAST END
|
INSP - Framing/Rough-in | 9/29/1998 | 10/1/1998 | 10/1/1998 | A | CANC |
Tom Arcoraci
|
|
|
bob called early and said insp could wait til tomorroe as subs were all not ready
|
INSP - Framing/Rough-in | 9/29/1998 | 9/30/1998 | 9/30/1998 | A | FAIL |
|
|
|
09/30/98 338 - not ready fire assys are not complete next not complete i
|
INSP - Framing/Rough-in | 9/30/1998 | 9/30/1998 | 9/30/1998 | P | PART |
|
|
|
09/30/98 338 - made ok to cover the suite walls in the west of the 3rd a
|
INSP - Framing/Rough-in | 9/28/1998 | 9/29/1998 | 9/29/1998 | A | FAIL |
|
|
|
09/29/98 338 - sheer wall bob ###-#### NOT REWADY FOR INSP OTHER AGENCIE
|
INSP - Wall cover | 9/24/1998 | 9/25/1998 | 9/25/1998 | A | PART |
|
|
|
09/25/98 338 - made ok for to cover the 2nd floor rooms only not hall
|
INSP-Sprinkler Rough-in/Hydro | 9/16/1998 | 9/16/1998 | 9/16/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ROUGH IN OF 2ND FLOOR OK TO COVER
|
INSP - Framing/Rough-in | 9/4/1998 | 9/8/1998 | 9/8/1998 | A | FAIL |
|
|
|
09/08/98 338 - NOT READY TO COVER C/N ISSUED FIRE ASSYS AND FIRE BLOCK A
|
INSP - Framing/Rough-in | 8/31/1998 | 8/31/1998 | 8/31/1998 | | NR |
|
|
|
08/28/98 338 - with m otto , P BAKER. B LEONARD. PLMER SUPER AND MYSELF
|
INSP - Framing/Rough-in | 8/28/1998 | 8/28/1998 | 8/28/1998 | P | NR |
|
|
|
fireproofing/bob ###-#### this is a conf had m otto on site to answer questions on the fire proofing requirements and the rated wall assys
|
INSP - Conference | 8/14/1998 | 8/14/1998 | 8/14/1998 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - wanted underground pipe looked at, they don't have permit, c
|
INSP - Framing/Rough-in | 8/13/1998 | 8/13/1998 | 8/13/1998 | P | PART |
|
|
|
08/13/98 338 - ok to start rocking as inspected
|
INSP - Framing/Rough-in | 8/11/1998 | 8/12/1998 | 8/12/1998 | A | PART |
|
|
|
08/12/98 338 - ok to cover bob ###-####
|
INSP - Wall cover | 8/11/1998 | 8/11/1998 | 8/11/1998 | P | PART |
|
|
|
08/11/98 338 - conf with bob leonard and p baker on the use of approved
|
INSP - Wall cover | 8/7/1998 | 8/7/1998 | 8/7/1998 | P | CANC |
|
|
|
this is for a conf only no framing is to be covered
|
INSP - Wall cover | 8/7/1998 | 8/7/1998 | 8/7/1998 | | PART |
|
|
|
08/07/98 338 - bob ###-#### struc. and wall need to supply ner 200 for t
|
INSP - Framing/Rough-in | 8/4/1998 | 8/5/1998 | 8/5/1998 | P | NR |
|
|
|
08/05/98 338 - this is a conference to speak to the rated walls and fram attending Dave McKlenna, Bob Leonard, Prestom Baker and P Paine.Must rev
|
INSP - Framing/Rough-in | 8/3/1998 | 8/4/1998 | 8/4/1998 | A | NR |
|
|
|
08/04/98 338 - NR NO ONE ON JOBSITE
|
INSP - Foundation | 6/8/1998 | 6/8/1998 | 6/8/1998 | P | PART |
|
|
|
06/08/98 338 - Preston ###-#### FOOTINGS out of time will inspect 06-09-
|
INSP - Foundation | 6/3/1998 | 6/3/1998 | 6/3/1998 | P | PART |
|
|
|
06/03/98 338 - MADE OK WITH SP INSP APPROVAL R-BAR IS PLACED
|
INSP - Foundation | 6/1/1998 | 6/2/1998 | 6/2/1998 | A | PART |
|
|
|
06/02/98 338 - made ok with sp insp for the west end only sp insp for th
|
INSP - Foundation | 5/27/1998 | 5/28/1998 | 5/28/1998 | A | PART |
|
|
|
AROUND 12:00-PRESTON ###-#### ok to pour only south and north walls
|
INSP - Concrete | 5/18/1998 | 5/19/1998 | 5/19/1998 | P | PART |
|
|
|
made ok with sp insp approval
|
INSP - Conference | 5/12/1998 | 5/12/1998 | 5/12/1998 | | PART |
|
|
|
/ / 338 - WITH OWNERS REP PROJECT SUPER AND SP INSP
|
INSP - Foundation | 5/7/1998 | 5/7/1998 | 5/7/1998 | P | PART |
|
|
|
05/07/98 338 - made ok to pour south wall 100 ft. +-
|