Permit Information
Permit NumberBLD97-02891
StatusFinaled
Name DIAMOND CONSTRUCTION
Site Address 2404 S ORCHARD ST
Project NameDAVIS COMM/RETAIL
Customer Number 
ePlanReviewNo
Description
COMMERCIAL/RETAIL SPACE FOR BRENT DAVIS * TO CONSTRUCT A 23,500 SQ. FT. MASONRY BLOCK BUILDING SHELL & CORE. TO CONSTRUCT A FOUR HOUR AREA SEPARATION WALL TO CREATE TWO SEPARATE BUILDING AREAS DO TO WATER FIRE FLOW AT BUILDING PROJECT LOCATION. TO BE LOCATED AND CONSTRUCTED AS SHOWN ON PLANS. NOTE: SEPARATE MISCELLANEOUS TENANT IMPROVEMENT PERMITS FOR SCUBA SALES/TRAINING POOL TENANT; ACTIVE WEAR RETAIL TENANT AND SULLIVAN DENTAL SUPPLY TENANT, ARE BEING ISSUED WITH THIS PLAN FOR PURPOSE OF CERTIFICATE OF OCCUPANCY ISSUANCE. PLANS, PLAN REVIEW COMMENTS AND FEE'S FOR SHELL AND CORE AND TENANT IMPROVEMENTS ARE A PART OF THIS PERMIT. THE BUILDING IS NOT SPRINKLED. UNFINISHED SHELL & CORE AREAS AS SHOWN ON PLANS WILL REQUIRE SEPARATE SUBMITTAL OF APPLICATIONS; PLANS FOR REVIEW, APPROVAL & ISSUANCE OF PERMITS FOR EACH PROPOSED FUTURE TENANT. SOME CODE ISSUES REMAIN TO BE ADDRESSED PRIOR TO CERTAIN STAGES OF THE CONSTRUCTION. SEE PLAN REVIEW COMMENTS ATTACHED TO THE APPROVED PLANS. A LETTER OF COMPLIANCE IS REQUIRED FOR SHELL & CORE CONSTRUCTION PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANY FOR ANY OF THE INDIVIDUAL TENANTS. DR-61-97 PC#622-97/JML
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/18/201312/18/201312/18/2013PDONE
DetailsAdele J Schaffeld-Griffin
I am finalling out this permit as the only outstanding item was planning and zonning. Sara has made a site visit and is signing off on the project. I did not make a site visit but reviewed and closed out all existing permits. With that done this part, core and shell is completed. 12/18/13 ajs
INSP - Final7/7/19987/8/19987/8/1998APART
Details
07/08/98 338 - SIGNED THE OCC REQ CARD IN THE TEMP COL
INSP-Final Inspection7/7/19987/8/19987/8/1998APART
DetailsJoe Tawney
07/08/98 406 - kEVIN 8705915 REINSP OK FOR TEMP OCC
INSP - Final7/7/19987/7/19987/7/1998PNR
Details
07/07/98 338 - OTH-OTHER AGENCIES NOT APPROVED
INSP-Final Inspection7/7/19987/7/19987/7/1998PFAIL
DetailsJoe Tawney
07/07/98 406 - Kevin ###-#### FINAL FAIL DAMPERS & SMOKE SEALS IN RATED CORRIDOR
INSP - Final6/30/19987/1/19987/1/1998ANR
Details
07/01/98 338 - kevin ###-#### coorections not complete over allowed glaz
INSP-Final Inspection6/30/19986/30/19986/30/1998PNR
DetailsJoe Tawney
06/30/98 406 - Kevin ###-#### NOT READY FOR INSP
INSP - Framing/Rough-in6/9/19986/9/19986/9/1998PFAIL
Details
ceiling inspection ###-#### NOT READY FOR INSP COVERED W/O FRAME INSP 1-HOUR CEILING NOT COMPLETE ETC
INSP - Framing/Rough-in2/17/19982/18/19982/18/1998ANR
DetailsWes Worcester
02/18/98 342 - ###-#### ROOFING NO ONE THERE, NO LADDER, ROOF ONLY PARTI
INSP - Roof2/18/19982/18/19982/18/1998 NH
DetailsWes Worcester
/ / 342 - NO ANSWER AT JOB SITE, ANSWERING MACHINE ONLY, I WILL GO BYE
INSP - Conference1/7/19981/7/19981/7/1998 PASS
Details
/ / 333 -
INSP-Conference1/7/19981/7/19981/7/1998 PASS
DetailsJoe Tawney
/ / 406 - ATTENDED PRE CONSTR CONFERENCE NO QUESTIONS WERE ASKED
INSP - Miscellaneous1/5/19981/5/19981/5/1998PPART
Details
01/05/98 338 - masonary block made ok with sp insp approval
INSP - Foundation12/31/19971/2/19981/2/1998PPART
Details
01/02/98 333 - ok pending special insp report he will call you.