Permanent Occupancy | | 8/14/1998 | 8/14/1998 | | DONE |
|
|
|
|
INSP - Final | 7/23/1998 | 7/24/1998 | 7/24/1998 | P | PASS |
|
|
|
07/24/98 338 - SIGNED THE TEMP COL OF THE OCC REQ CARD FOR PHASE 5
|
INSP-Final Inspection | 7/23/1998 | 7/24/1998 | 7/24/1998 | A | PASS |
Joe Tawney
|
|
|
07/24/98 406 - FINAL POSSIBLE A TEMP OCC. JOHN ###-#### THE BON MARCHE REINSP OK ON PHASE 5 AND OK FOR PERM OCC & OR CERT OF COMPLETION
|
INSP - Final | 7/6/1998 | 7/7/1998 | 7/7/1998 | P | PART |
|
|
|
07/07/98 338 - TCO -TEMP C OF O ISSUED ok for same i signed the occ req
|
INSP-Final Inspection | 7/6/1998 | 7/7/1998 | 7/7/1998 | P | PART |
Joe Tawney
|
|
|
07/07/98 406 - John ###-#### OK FOR TEMP OCC OF PHASE VI ì
|
INSP - Final | 6/9/1998 | 6/10/1998 | 6/10/1998 | P | PART |
Joe Tawney
|
|
|
06/10/98 406 - JOHN ###-#### AND 338 IS ALSO SCHEDULED TO GO OUT TEMP OCC FINAL OK FOR TEMP ON PHASE IV
|
INSP-Conference | 6/9/1998 | 6/10/1998 | 6/10/1998 | P | PASS |
|
|
|
06/09/98 338 - OK FOR THE PHASE 5 OF PROJECT FOR TEMP OCC
|
INSP-Final Inspection | 6/3/1998 | 6/3/1998 | 6/3/1998 | P | PART |
Joe Tawney
|
|
|
06/03/98 406 - fire sprinkle Mike ###-#### OK SPKLR PROTECTION FOR ESCALATOR OPENING OK RI FOR PHASE 4 PART PHASE 5
|
INSP - Final | 5/13/1998 | 5/14/1998 | 5/14/1998 | P | PART |
|
|
|
05/14/98 338 - signed the temp col for this phase
|
INSP-Final Inspection | 5/13/1998 | 5/14/1998 | 5/14/1998 | P | PART |
Joe Tawney
|
|
|
05/14/98 406 - john ###-#### FINAL PHASE III OK FOR TEMP OCC
|
INSP - Final | 5/7/1998 | 5/11/1998 | 5/8/1998 | P | PART |
|
|
|
05/11/98 338 - sogned the temp col called cathy to verify
|
INSP - Final | 5/7/1998 | 5/7/1998 | 5/7/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - FINAL OK ON SPKLR SYSTEM COVERAGE WOMENS DEPT PHASE III
|
INSP-Final Inspection | 5/7/1998 | 5/7/1998 | 5/7/1998 | P | PART |
Joe Tawney
|
|
|
05/07/98 406 - ###-#### SHOE DEPT PHASE II OK FOR TEMP OCC
|
INSP - Framing/Rough-in | 4/30/1998 | 5/1/1998 | 5/1/1998 | A | PASS |
|
|
|
made ok seizmic ok935
|
INSP - Framing/Rough-in | 4/30/1998 | 4/30/1998 | 4/30/1998 | | CANC |
|
|
|
04/30/98 338 - cancelled till 05-01-98
|
INSP - Framing/Rough-in | 4/29/1998 | 4/30/1998 | 4/30/1998 | A | CANC |
|
|
|
CANCELLED BY JON TILL 05-01-98
|
INSP - Framing/Rough-in | 4/30/1998 | 4/30/1998 | 4/30/1998 | | CANC |
|
|
|
04/30/98 338 - cancelled till 05-01-98
|
INSP-Final Inspection | 4/30/1998 | 4/30/1998 | 4/30/1998 | P | PART |
Joe Tawney
|
|
|
04/30/98 406 - mike ###-#### OK ON SPKLR ROUGH IN FOR MALL AREA OF BON ADD ONE HEAD
|
INSP - Final | 4/23/1998 | 4/24/1998 | 4/24/1998 | A | PASS |
|
|
|
04/24/98 338 - c/c issued final approval documentation from sp insp agen
|
INSP - Letter of compliance | 4/24/1998 | 4/24/1998 | 4/24/1998 | | PASS |
|
|
|
/ / 338 - # 014265
|
INSP - Letter of compliance | 4/24/1998 | 4/24/1998 | 4/24/1998 | | PASS |
|
|
|
/ / 338 - # 014265
|
INSP-Final Inspection | 4/22/1998 | 4/23/1998 | 4/24/1998 | P | PART |
Joe Tawney
|
|
|
04/23/98 406 - JOHN ###-#### FINAL OK FOR TEMP OCC ON "IN BON" PHASE OF REMODEL
|
INSP - Final | 4/22/1998 | 4/23/1998 | 4/23/1998 | P | PART |
|
|
|
04/24/98 338 - temp made ok fire ext in place for phase 2-a/b
|
INSP-Final Inspection | 4/15/1998 | 4/16/1998 | 4/16/1998 | A | PART |
Joe Tawney
|
|
|
mike ###-#### OK ON ROUGH IN OF IN BON PORTION OF REMODEL
|
INSP - Framing/Rough-in | 4/7/1998 | 4/7/1998 | 4/7/1998 | P | PART |
|
|
|
04/07/98 338 - verify slip joint at the attachment of the overhead door
|
INSP - Final | 3/24/1998 | 3/27/1998 | 3/27/1998 | A | PART |
|
|
|
03/27/98 338 - TCO -TEMP C OF O ISSUED by cathy for the 2nd phase/additi
|
INSP-Final Inspection | 3/24/1998 | 3/27/1998 | 3/27/1998 | A | PASS |
Joe Tawney
|
|
|
03/27/98 406 - 7:00 as per 406 and 338 john ###-#### FINAL OK FOR TEMP OCC OF NEW ADDITION
|
INSP-Alarm Testing | 3/25/1998 | 3/26/1998 | 3/26/1998 | A | PART |
Joe Tawney
|
|
|
03/26/98 406 - JOHN ###-#### ALARM TEST OK ON SIGNALLING DEVICES, PULLS, & SMOKE DET DUCT DET NOT TES
|
INSP-Conference | 3/23/1998 | 3/23/1998 | 3/23/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF ON SMOKE EVAC SYSTEM AND FINAL INSPECTION SCHEDULE WITH
|
INSP - Conference | 3/17/1998 | 3/17/1998 | 3/17/1998 | | PART |
|
|
|
/ / 338 - with Jon Anderson on the signoffs needed for temp occ on the
|
INSP - Framing/Rough-in | 3/9/1998 | 3/11/1998 | 3/10/1998 | P | CANC |
|
|
|
CONFERENCE WITH JOHN FOR 2:00 PLEASE--###-####. HE WILL CALL YOU TO CONFIRM.. cancelled as per 338.mps
|
INSP-Conference | 3/9/1998 | 3/11/1998 | 3/10/1998 | P | CANC |
Joe Tawney
|
|
|
JOHN WILL CALL TO CONFIRM 2:00 WITH YOU..###-#### cancelled as per 338.mps
|
INSP - Conference | 3/10/1998 | 3/10/1998 | 3/10/1998 | | PART |
|
|
|
/ / 338 - with Jack Bolar and jon anderson ---requiremens for the smok
|
INSP - Conference | 3/9/1998 | 3/9/1998 | 3/9/1998 | | PASS |
|
|
|
/ / 338 - with jon on conf request of an inspection to determin possib of new 20,000 s.f. addition prior to the installation of the new evac sy the system parts are not to arrive until same date as gand opening conf for wed p.m. 03
|
INSP - Conference | 3/9/1998 | 3/9/1998 | 3/9/1998 | | PASS |
|
|
|
/ / 338 - with jon on conf request of an inspection to determin possib of new 20,000 s.f. addition prior to the installation of the new evac sy the system parts are not to arrive until same date as gand opening conf for wed p.m. 03
|
INSP - Framing/Rough-in | 3/5/1998 | 3/6/1998 | 3/6/1998 | A | PART |
|
|
|
03/06/98 338 - most of 2nd 1/2 of ceiling gridScheduled by Hello!. Cont
|
INSP - Framing/Rough-in | 3/4/1998 | 3/5/1998 | 3/5/1998 | A | CANC |
|
|
|
03/05/98 338 - cancelled by jonScheduled by Hello!. Contact phone is [8
|
INSP - Framing/Rough-in | 2/19/1998 | 2/20/1998 | 2/20/1998 | P | PART |
|
|
|
02/20/98 338 - east 1/3 ceiling grid ok ###-#### jon
|
INSP - Framing/Rough-in | 2/10/1998 | 2/11/1998 | 2/11/1998 | A | PART |
|
|
|
02/11/98 338 - jon ###-#### framing mADE OK SP INSP TO VERIFY INSTALL OF
|