INSP - Final | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | FAIL |
Tom Arcoraci
|
|
|
07/02/98 408 - after 9am Mike ###-#### OK AFTER PUBLIC WORKS SIGNS
|
INSP-Final Inspection | 6/29/1998 | 6/29/1998 | 6/29/1998 | P | PASS |
Joe Tawney
|
|
|
06/29/98 406 - mike ###-#### REINSP OK FOR CERT OF COMPLETION ì
|
INSP - Final | 12/30/1997 | 12/31/1997 | 12/31/1997 | A | NR |
Jim Sly
|
|
|
12/30/97 316 - Need all required signatures on occ req card ...left note
|
INSP-Final Inspection | 12/30/1997 | 12/31/1997 | 12/31/1997 | A | FAIL |
Joe Tawney
|
|
|
12/31/97 406 - HARD CARD ON THE WALL IN THE ADDITION OF POST OFFICE FINAL FAIL SPKLR PROTECTION REQUIRED
|
INSP - Conference | 12/30/1997 | 12/30/1997 | 12/30/1997 | | PASS |
Jim Sly
|
|
|
/ / 316 - Met with superintendent to discuss requirements for final...
|
INSP - Final | 12/29/1997 | 12/30/1997 | 12/30/1997 | A | NR |
Jim Sly
|
|
|
12/30/97 316 - C/N...Need all required signatures....
|
INSP - Framing/Rough-in | 11/20/1997 | 11/19/1997 | 11/19/1997 | P | PASS |
Tom Arcoraci
|
|
|
|
INSP - Framing/Rough-in | 11/19/1997 | 11/19/1997 | 11/19/1997 | P | CANC |
|
|
|
sent to 408
|
INSP - Foundation | 11/7/1997 | 11/7/1997 | 11/7/1997 | A | PASS |
Tom Arcoraci
|
|
|
|
INSP - Framing/Rough-in | 11/6/1997 | 11/7/1997 | 11/7/1997 | A | CANC |
Tom Arcoraci
|
|
|
WALLS SHOULD BE FOUNDATION INSP
|
INSP - Footings | 11/4/1997 | 11/4/1997 | 11/4/1997 | P | PASS |
|
|
|
11/04/97 333 - after 1:45 FTG -OK FOOTING
|