INSP - Final | 7/30/1998 | 7/30/1998 | 7/30/1998 | P | PART |
Jim Storey
|
|
|
07/30/98 301 - TCO -TEMP C OF O ISSUED w/c/n posted for p.paine to check
|
INSP-Final Inspection | 7/24/1998 | 7/27/1998 | 7/27/1998 | P | PASS |
Joe Tawney
|
|
|
07/27/98 406 - 1 o'clock with perry/ gary ###-#### FINAL OK FOR CERT OF COMPLETION FOR SHELL AND CORE
|
INSP-Sprinkler Rough-in/Hydro | 7/14/1998 | 7/15/1998 | 7/15/1998 | A | PART |
Joe Tawney
|
|
|
07/15/98 406 - 200 lb test/ ###-#### OK ON HYDRO TEST
|
INSP - Framing/Rough-in | 6/18/1998 | 6/18/1998 | 6/18/1998 | P | PART |
|
|
|
06/18/98 338 - made ok to cover the 3rd floor bathroom ceilings fire cau
|
INSP-Sprinkler Rough-in/Hydro | 5/26/1998 | 5/26/1998 | 5/26/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ROUGH IN OF SPKLR SYSTEM
|
INSP - Framing/Rough-in | 5/20/1998 | 5/21/1998 | 5/21/1998 | A | PAR |
|
|
|
OK TO DROP IN CEILING TILES THIS AREA
|
INSP - Framing/Rough-in | 5/19/1998 | 5/19/1998 | 5/19/1998 | P | PART |
|
|
|
fire caulking 2nd floor/ ###-#### made ok above the restrooms
|
INSP - Wall cover | 4/24/1998 | 4/24/1998 | 4/24/1998 | P | PASS |
|
|
|
04/28/98 338 - made ok fire caulk ok above the restrooms no answer on the contact #
|