Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD97-03626
StatusFinaled
Name BORAH HIGH SCHOOL
Site Address 6001 CASSIA ST
Project NameBORAH HIGH SCHOOL REROOF
Customer Number 
ePlanReviewNo
Description
BORAH HIGH SCHOOL REROOF WING # 1 * THE WORK CONSISTS OF A COMPLETE PREMANUFACTURED WOOD TRUSS OVERBUILD WITH ASPHALT SHINGLE ROOF, FIBERGLASS INSULATION AND E.I.F.S. GABLE ENDS AND CORNICE, INCLUDING NEW CONCRETE COLUMN. INTERIOR WORK CONSISTS OF 1 HOUR FIRE RATED UPGRADES TO CHEMISTRY AND ADJOINING STORAGE ROOM. WORK ALSO INCLUDES MISCELLANEOUS ELECTRICAL, MECHANICAL AND A COMPLETE FIRE SPRINKLER SYSTEM. PC#783-97
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final1/29/19991/29/19991/29/1999PPASS
Details
dean- ###-#### fn insp- madeok to sign oc req card with 406 signoff
INSP-Final Inspection1/28/19991/28/19991/28/1999PPASS
DetailsJoe Tawney
01/28/99 406 - BILL ###-#### REINSP OK FOR CERT OF COMPLETION ì
INSP-Alarm Testing10/30/199810/30/199810/30/1998PPASS
Details
trip test and detectors passed, need spare heads
INSP - Final8/31/19988/31/19988/31/1998 PART
Details
/ / 338 - MADEOK FOR TEMP TEMP CONTITIONS IN FORCE
INSP-Final Inspection8/28/19988/29/19988/29/1998 PART
Details
dry system converted to wet, dampers locked closed until alarms complete
INSP - Final8/27/19988/28/19988/28/1998AFAIL
Details
not ready for insp alarms and sprink system are caputs
INSP - Final8/28/19988/28/19988/28/1998 FAIL
Details
08/28/98 338 - sprink system and alarms and dampers does not work
INSP-Final Inspection8/27/19988/28/19988/28/1998AFAIL
Details
dry sprinkler system failed trip time test, smoke dampers would not close, not connected to alarms
INSP - Final8/27/19988/27/19988/27/1998 NR
DetailsJoe Tawney
/ / 406 - FINAL NOT READY
INSP - Final8/27/19988/27/19988/27/1998 NR
DetailsJoe Tawney
/ / 406 - FINAL NOT READY
INSP-Sprinkler Rough-in/Hydro8/24/19988/24/19988/24/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON ABOVE GROUND HYDRO TEST EXC FDC & SUPPLY LINE TO BE TE UNDERGROUND OK ON CORRIDOR & CLASSROOM ROUGH IN WITH NOTED CORRECTIONS
INSP-Conference8/14/19988/14/19988/14/1998 PART
DetailsJoe Tawney
/ / 406 - CONF ON WHAT REQ FOR OCC DID NOT HAVE FD REVIEW W/PLANS PROV
INSP - Framing/Rough-in5/26/19985/26/19985/26/1998PPART
Details
###-#### to wet to get on the roof
INSP - Framing/Rough-in4/24/19984/27/19984/27/1998APART
Details
04/27/98 338 - SP INSP APROVAL MADE OK MISC COL AT PER.
INSP - Foundation4/21/19984/22/19984/22/1998PPART
Details
04/22/98 338 - COLUMN POUR TEST SP INSP MADE OK
INSP - Foundation4/16/19984/17/19984/17/1998APART
Details
04/17/98 338 - poured with sp insp onlyScheduled by Hello!.
INSP - Foundation4/2/19984/3/19984/3/1998APART
Details
04/03/98 338 - no answer on the phone forman not on site