Permanent Occupancy | | 9/11/1998 | 9/11/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/8/1998 | 9/9/1998 | 9/9/1998 | P | PASS |
Joe Tawney
|
|
|
09/09/98 406 - KEN ###-#### REINSP OK FOR PERM OCC
|
INSP - Final | 8/24/1998 | 8/25/1998 | 8/25/1998 | A | NR |
|
|
|
08/25/98 338 - other agencies not approved
|
INSP-Final Inspection | 8/24/1998 | 8/25/1998 | 8/25/1998 | A | FAIL |
Joe Tawney
|
|
|
08/25/98 406 - ###-#### FINAL FAIL ALARM SYSTEM SPKLR PROT IN COOLER
|
INSP-Sprinkler Rough-in/Hydro | 8/6/1998 | 8/6/1998 | 8/6/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST
|
INSP - Framing/Rough-in | 8/5/1998 | 8/5/1998 | 8/5/1998 | P | PART |
|
|
|
08/05/98 338 - madee okto drop in the tiles will check the diffuser conn
|
INSP-Alarm Testing | 7/20/1998 | | 7/20/1998 | | FAIL |
|
|
|
Alarm plans rec'd from grinnel today. Alarm plans have been reviewed and approved by another vendor. No work allowed by grinnel until plan modification fee has been paid and new plans approved.
|
INSP-Sprinkler Rough-in/Hydro | 7/17/1998 | 7/17/1998 | 7/17/1998 | | PART |
Joe Tawney
|
|
|
07/17/98 406 - Tracy ###-#### OK ON SPKLR ROUGH IN NEED FIRE HYD INSTALLED WITHIN 290' OF FDC
|
INSP - Framing/Rough-in | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | PART |
|
|
|
07/02/98 338 - Dominick ###-#### made ok to drywall the inside of the ex
|
INSP - Framing/Rough-in | 6/23/1998 | 6/23/1998 | 6/23/1998 | P | PART |
|
|
|
06/23/98 333 - exterior wall drywall needs to be checked for nailing whe
|
INSP-Supply line flush | 6/18/1998 | 6/18/1998 | 6/18/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Foundation | 5/20/1998 | 5/20/1998 | 5/20/1998 | P | PART |
|
|
|
foundation walls/ ###-#### made ok sp insp made ok to cover
|
INSP - Foundation | 5/8/1998 | 5/11/1998 | 5/8/1998 | A | PART |
|
|
|
05/11/98 338 - made ok after 5:00 r-bar placed sp insp made ok
|
INSP-Conference | 5/5/1998 | 5/6/1998 | 5/6/1998 | P | PASS |
|
|
|
05/06/98 338 - will schedule pre job conf for next week
|