INSP - Final | 3/26/1999 | 3/26/1999 | 3/26/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PER4M OCC
|
INSP - Final | 3/26/1999 | 3/26/1999 | 3/26/1999 | | PASS |
Carl Dependahl
|
|
|
03/26/99 340 - ###-#### JANINE//FINAL OCCUPY fire ok; ok for c/o
|
INSP - Final | 3/25/1999 | 3/26/1999 | 3/26/1999 | P | PASS |
Carl Dependahl
|
|
|
###-#### JANINE//FINAL OCCUPY
|
Permanent Occupancy | | 3/26/1999 | 3/26/1999 | | DONE |
|
|
|
|
INSP - Final | 3/23/1999 | 3/23/1999 | 3/23/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK EXC NEED NFPA 72 FORM
|
INSP - Final | 11/9/1998 | 11/10/1998 | 11/12/1998 | A | PASS |
|
|
|
11/10/98 338 - made ok signed the occ req card on 111098 for the temp.
|
INSP-Final Inspection | 11/9/1998 | 11/10/1998 | 11/10/1998 | A | PART |
Joe Tawney
|
|
|
11/10/98 406 - RICHARD ###-#### REINSP OK FOR TEMP OCC HEAT IN RISER ROOM, KNOX BOX, NFPA FORM, FAX SIG
|
INSP - Final | 11/6/1998 | 11/9/1998 | 11/9/1998 | P | CANC |
|
|
|
11/09/98 338 - cancelled by the contractor as fire life safety did not p
|
INSP-Final Inspection | 11/6/1998 | 11/9/1998 | 11/9/1998 | A | FAIL |
Joe Tawney
|
|
|
11/09/98 406 - RICHARD ###-#### FINAL FAIL ALARM SYSTEM, EMERG LIGHTS, RISER ROOM, EXIT LIGHTS
|
INSP - Final | 11/5/1998 | 11/6/1998 | 11/6/1998 | P | FAIL |
Carl Dependahl
|
|
|
RICH ###-####...338 area, need fire/safety...no further insp performed.
|
INSP-Final Inspection | 11/5/1998 | 11/6/1998 | 11/6/1998 | A | NR |
Joe Tawney
|
|
|
11/06/98 406 - RICH ###-#### FINAL NOT READY ì
|
INSP - Final | 11/2/1998 | 11/4/1998 | 11/4/1998 | A | NR |
Wes Worcester
|
|
|
11/04/98 342 - RICHARD ###-#### be sure to check for ventillation of the contractor about same 338
|
INSP-Sprinkler Rough-in/Hydro | 10/6/1998 | 10/6/1998 | 10/6/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ABOVE AND UNDERGROUND HYDRO TEST OK ON SPKLR ROUGH IN
|
INSP - Conference | 10/5/1998 | 10/5/1998 | 10/5/1998 | | PASS |
Alan Hauser
|
|
|
/ / 350 - stop to see what was going on, haven't had any inspections h
|
INSP-Supply line flush | 9/30/1998 | 9/30/1998 | 9/30/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SUPPLY LINE FLUSH AND PARTIAL OK ON ROUGH IN REINSP RE
|
INSP - Framing/Rough-in | 9/22/1998 | 9/22/1998 | 9/22/1998 | P | FAIL |
|
|
|
09/22/98 338 - called to explain
|
INSP - Framing/Rough-in | 8/3/1998 | 8/4/1998 | 8/4/1998 | A | PART |
|
|
|
08/04/98 338 - MADE OK TO HANG DRYWALL
|
INSP - Framing/Rough-in | 7/21/1998 | 7/22/1998 | 7/22/1998 | P | PART |
|
|
|
07/22/98 338 - framing/ eric evans/ ###-#### need responsible person on
|
INSP - Framing/Rough-in | 6/1/1998 | 6/1/1998 | 6/2/1998 | P | PART |
|
|
|
06/02/98 338 - ok for the s. and west ext walls of the /combustable
|
INSP - Concrete | 5/19/1998 | 5/20/1998 | 5/20/1998 | A | NR |
|
|
|
late a.m. tony/###-#### suspended slab workers gone home no answer at access #
|
INSP - Foundation | 5/13/1998 | 5/14/1998 | 5/15/1998 | A | PART |
|
|
|
05/15/98 338 - POURED YEST.
|
INSP - Foundation | 5/5/1998 | 5/5/1998 | 5/5/1998 | P | FAIL |
|
|
|
05/05/98 338 - c/n issued approved plans do not match the work in progre
|
INSP - Foundation | 4/30/1998 | 5/1/1998 | 5/1/1998 | P | PASS |
Wes Worcester
|
|
|
05/01/98 342 - early pm please tony ###-####
|
INSP - Foundation | 5/1/1998 | 5/1/1998 | 5/1/1998 | P | PART |
|
|
|
made ok to pour the perimeted foundation walls only. r-bar is placed
|