Permit Information
Permit NumberBLD98-00482
StatusFinaled
Name GROVE HOTEL - 4TH FLR
Site Address 245 S CAPITOL BLVD
Project NameGROVE HOTEL-4TH FLR
Customer Number 
ePlanReviewNo
Description
(4TH FLOOR TENANT IMPROVEMENTS) Fire sprinklers used to meet high-rise requirements. To finish portions of the 4th floor (25,211 sq. ft. including terrace) in preparation for occupancy. Scope of work includes offices, hotel rooms, and terrace on the 4th floor. Work is to include restrooms accessible to the disabled, interior nonbearing walls, 1-hr occupancy separation, 1-hr corridors, stair enclosure to the 4th floor, and suspended ceilings all per approved drawings and plan check conditions on file. The occupant load of the terrace shall be based on 1 person per 15 square feet. Signs shall be posted per items #40 & #41 on the plan check report. PC-420-97 **CJW** (10-20-97) SEPARATING THE ELEVATOR VESTIBULE FROM THE CORRIDOR ON THE 4TH FLOOR WAS APPROVED. CHANGES ALLOW FOR AN INCREASED OCCUPANT LOAD. (2-27-98) THIS PERMIT FOR THE 4TH FLOOR WORK WAS SPLIT OFF FROM PERMIT BLD97-1950 WHICH WAS ORIGINALLY ISSUED TO COVER WORK ON THE 3RD AND 4TH FLOORS.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 7/25/19987/25/1998 DONE
Details
INSP-Final Inspection5/29/19986/1/19987/15/1998APASS
Details
rick ###-#### final occ
INSP - Final7/7/19987/7/19987/7/1998 PART
Details
/ / 333 - PROFIT MEETING
INSP - Final7/2/19987/2/19987/2/1998PPASS
Details
07/02/98 333 - 4th floor/rick ###-####
INSP - Framing/Rough-in6/30/19987/1/19987/1/1998PPASS
Details
07/01/98 333 - sign ok
INSP-Final Inspection6/26/19986/29/19986/29/1998PFAIL
DetailsRick Jackson
couldn't test roll-up doors, alarm plans, smoke evac not ready
INSP-Final Inspection6/24/19986/24/19986/24/1998PFAIL
DetailsRick Jackson
rick ###-#### alarms, roll up shutters didn't work with alarms, strobe in vending
INSP - Final6/15/19986/15/19986/15/1998PPART
Details
06/15/98 333 - SILLS OK
INSP - Final6/11/19986/11/19986/11/1998AFAIL
Details
06/11/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Final6/3/19986/3/19986/3/1998PPART
Details
06/03/98 333 - cn placed temp ok
INSP-Final Inspection6/2/19986/3/19986/3/1998APART
DetailsRick Jackson
requested by gen contractor for am temp occ approved. suites not ready to occupy
INSP - Final6/1/19986/2/19986/2/1998AFAIL
Details
06/02/98 333 - not ready
INSP-Final Inspection6/1/19986/2/19986/2/1998AFAIL
DetailsRick Jackson
Rick ###-#### temp occ. c/n issued. alarms not ready, smoke evac calcs needed, etc.
INSP - Final5/29/19986/1/19986/1/1998AFAIL
Details
06/01/98 333 - not ready
INSP-Final Inspection6/1/19986/1/19986/1/1998PFAIL
DetailsRick Jackson
fire alarm panel not working. lan smith notified of situation and will talk to owners
INSP - Final5/28/19985/29/19985/29/1998ACANC
Details
05/29/98 333 - canc by Rick
INSP-Final Inspection5/28/19985/29/19985/29/1998AFAIL
Details
4TH FLOOR--TEMP OCC--RICK ###-#### Left list, smoke exhaust not functional, areas of corridor not detected, not lit by npormal or emergency lights, elevators do not recall from this floor.
INSP - Final5/27/19985/28/19985/28/1998PFAIL
Details
05/28/98 333 - not ready
INSP - Framing/Rough-in5/19/19985/20/19985/20/1998PPART
Details
05/20/98 333 - grid ok
INSP - Framing/Rough-in5/15/19985/18/19985/18/1998PFAIL
DetailsJim Storey
05/18/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in4/1/19984/1/19984/1/1998PPASS
Details
04/01/98 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in3/27/19983/30/19983/30/1998APART
Details
03/30/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to cover al
INSP - Framing/Rough-in3/11/19983/11/19983/11/1998PPART
Details
03/11/98 333 - upper walls ok
INSP - Framing/Rough-in3/10/19983/10/19983/10/1998PFAIL
Details
03/10/98 333 - cover without insp