Permanent Occupancy | | 10/19/1998 | 10/19/1998 | | DONE |
|
|
|
|
INSP - Final | 10/15/1998 | 10/15/1998 | 10/15/1998 | | PASS |
|
|
|
/ / 338 - MADE OK CARD NOT ON SITE OK FOR OFFICE TO SIGN THE FINAL COL
|
INSP-Conference | 10/14/1998 | 10/15/1998 | 10/15/1998 | A | PASS |
Joe Tawney
|
|
|
10/15/98 406 - MIKE-RUSSELL CORP-###-#### PER JOE CONF AT 10:00 FOR FN REINSP OK FOR PERM OCC
|
INSP - Final | 9/28/1998 | 9/28/1998 | 9/28/1998 | P | PART |
|
|
|
09/28/98 338 - MADE OK FOR TEMP OCC
|
INSP - Final | 9/25/1998 | 9/25/1998 | 9/28/1998 | P | PART |
|
|
|
09/28/98 338 - MADE OK FOR TEMP OCC
|
INSP-Final Inspection | 9/18/1998 | 9/18/1998 | 9/18/1998 | P | PART |
Joe Tawney
|
|
|
09/18/98 406 - MIKE ###-#### FINAL OK FOR TEMP OCC PKING LOT FIRE EXT CONTROL VLV NFPA 72 SPKLR OB
|
INSP-Sprinkler Rough-in/Hydro | 9/14/1998 | 9/14/1998 | 9/14/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND AND ABOVE GROUND HYDRO TESTS
|
INSP-Supply line flush | 9/11/1998 | 9/14/1998 | 9/14/1998 | A | PART |
Joe Tawney
|
|
|
09/14/98 406 - SAM ###-#### 8 AM OK ON SUPPLY LINE FLUSH
|
INSP - Framing/Rough-in | 7/27/1998 | 7/27/1998 | 7/27/1998 | P | PART |
|
|
|
07/27/98 338 - OK TO INSULATE ONLY NEED FIRE STOPS AT PLATE PENETRATIONS
|
INSP-Sprinkler Rough-in/Hydro | 7/24/1998 | 7/24/1998 | 7/24/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ROUGH IN OF DRY SYSTEM EXC SOFFIT AREA IN 4 CORNERS
|
INSP - Framing/Rough-in | 7/6/1998 | 7/7/1998 | 7/7/1998 | A | NR |
|
|
|
07/07/98 338 - truss eng and lateral supports not complete, interior she
|
INSP - Foundation | 6/4/1998 | 6/4/1998 | 6/4/1998 | P | PART |
|
|
|
06/04/98 338 - made ok to pour r-bar is placed
|
INSP - Foundation | 6/2/1998 | 6/2/1998 | 6/2/1998 | P | PART |
|
|
|
06/02/98 338 - made ok to pour with ele ground ok,d r-bar is placed form
|