Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD98-00600
StatusFinaled
Name UNIVERSITY PLAZA LLC
Site Address 960 S BROADWAY AVE Unit: 101
Project NameUNIVERSITY PLAZA
Customer Number 
ePlanReviewNo
Description
*UNIVERSITY PLAZA* LOBBY & COMMON AREA UPGRADES, WORK TO INCLUDE, NEW SMOKE GUARD DOORS 2nd THRU 5th floors, NEW LOBBY AND COMMON AREA FINISHES, NEW TOILET ROOM 1st FLOOR ONLY (ACCESSIBLE UNISEX) AND NEW ENTRY. WORK TO BE PERFORMED ON ALL 5 FLOORS. NOTE: THIS BUILIDNG IS FULLY FIRE SPRINKLERED. ANY ALTERATION OR MODIFICATION TO THE FIRE SPRINKLER SYSTEM SHALL BE PER NFPA #13 AS REGULATED BY THE FIRE DEPARTMENT. (PC#136-98) RMH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final2/10/19992/11/19992/11/1999PPASS
DetailsJim Storey
02/11/99 301 - FNL -OK FINAL sa per approved plans and agreement on file
INSP-Conference2/11/19992/11/19992/11/1999 PASS
DetailsRick Jackson
/ / 409 - REVIEWED WITH STRUCTURAL AND MECH INSPECTOR THE NEWLY FOUND
INSP - Final2/10/19992/10/19992/10/1999PFAIL
DetailsJim Storey
02/10/99 301 - n/r
INSP - Final2/10/19992/9/19992/10/1999 PASS
DetailsRick Jackson
/ / 409 - OCC APPROVED
INSP-Final Inspection1/28/19991/29/19991/29/1999AFAIL
DetailsRick Jackson
01/29/99 409 - JAMES CUPPS- ###-#### FIRE FN INSP fire pump running and controller don't send signal off-site
INSP - Framing/Rough-in8/13/19988/14/19988/14/1998APASS
DetailsJim Storey
08/14/98 301 - ###-#### jan FRAM-OK FRAMING
INSP-Final Inspection7/30/19987/31/19987/31/1998PFAIL
DetailsRick Jackson
MIKE ###-#### HE WOULD LIKE YOU TO CALL HIM pump monitoring, tampers, exit signs, heat detectors in shaft
INSP - Framing/Rough-in7/9/19987/10/19987/10/1998AFAIL
DetailsJim Storey
07/10/98 301 - CEILING TILE COVER UP/ ###-#### UNIT 101 CORR-CORREC-CALL FOR REINSP WHEN COMPLETED fire stopping and 4th floor m grid wires needed.
INSP - Final6/29/19986/30/19986/30/1998APART
Details
06/30/98 333 - covered befor I got thereappears ok
INSP - Framing/Rough-in6/18/19986/19/19986/19/1998APART
Details
06/19/98 333 - ok to cover mech room at 1st floor elevator and 3rd floor
INSP-Sprinkler Rough-in/Hydro6/3/19986/3/19986/3/1998PPART
DetailsRick Jackson
jan ###-#### voice pager/job trailer he will be there okay to cover main lobby sprinkler system only
INSP - Framing/Rough-in6/3/19986/3/19986/2/1998PFAIL
DetailsJim Storey
06/03/98 301 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Concrete5/13/19985/14/19985/14/1998APASS
DetailsWes Worcester
05/14/98 342 - concrete slab/larry ###-####
INSP - Framing/Rough-in5/11/19985/11/19985/11/1998 PART
DetailsWes Worcester
/ / 342 -
INSP - Framing/Rough-in5/11/19985/11/19985/11/1998 PASS
DetailsWes Worcester
/ / 342 -
INSP - Framing/Rough-in5/11/19985/11/19985/11/1998PFAIL
DetailsJim Storey
05/11/98 301 - LARR TO WESY/###-#### - AFTER LUNCH PLEASE. TRANS