INSP - Final | 2/12/1999 | 2/12/1999 | 2/12/1999 | | PASS |
Jim Storey
|
|
|
02/12/99 301 - FNL -OK FINAL
|
Permanent Occupancy | | 2/12/1999 | 2/12/1999 | | DONE |
|
|
|
|
INSP - Final | 2/8/1999 | 2/8/1999 | 2/9/1999 | P | PART |
Jim Storey
|
|
|
02/08/99 301 - temp occ ok
|
INSP-Final Inspection | 2/5/1999 | 2/5/1999 | 2/5/1999 | P | PASS |
Rick Jackson
|
|
|
RICK ###-#### occ approved
|
INSP-Conference | 1/6/1999 | 1/6/1999 | 1/6/1999 | P | PART |
Rick Jackson
|
|
|
verified damper operation with electrician; reviewed plans for final
|
INSP - Framing/Rough-in | 11/25/1998 | 11/27/1998 | 11/27/1998 | A | FAIL |
Jim Storey
|
|
|
11/27/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PASS |
Jim Storey
|
|
|
10/27/98 301 - rick ###-#### or ###-#### roof sheeting insp RF -OK ROOF NAILING
|
INSP - Framing/Rough-in | 10/23/1998 | 10/23/1998 | 10/23/1998 | P | NR |
Jim Storey
|
|
|
10/23/98 301 - rick ###-#### nailing on sheeting
|
INSP - Concrete | 8/28/1998 | 8/28/1998 | 8/28/1998 | | PART |
Jim Storey
|
|
|
08/28/98 301 - stem wall/###-#### pouring 2:00 special inspector COVERED BY SPECIAL INSP PENDING REPORT.
|
INSP - Foundation | 8/25/1998 | 8/26/1998 | 8/26/1998 | A | PASS |
Jim Storey
|
|
|
08/26/98 301 - RICK ###-#### FOOTING INSPECTION MID MORNING IF POSSIBLE. LUNCH TIME NOT EARLY MORNING. FTG -OK FOOTING rebar ok pending special insp.
|
INSP - Framing/Rough-in | 8/7/1998 | 8/7/1998 | 8/7/1998 | | PART |
Jim Storey
|
|
|
08/07/98 301 - placed w/special insp. pending report.
|
INSP - Framing/Rough-in | 8/6/1998 | 8/7/1998 | 8/6/1998 | A | PART |
Jim Storey
|
|
|
foundation placed w/special insp. pending report.
|
INSP - Foundation | 8/4/1998 | 8/4/1998 | 8/4/1998 | P | PASS |
Jim Storey
|
|
|
08/04/98 301 - RICK ###-#### ###-#### FRMS-OK FORMS
|