Permanent Occupancy | | 10/2/1998 | 10/2/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/30/1998 | 9/30/1998 | 9/30/1998 | P | PASS |
Rick Jackson
|
|
|
fire lanes completed - occ approved
|
INSP - Final | 9/28/1998 | 9/28/1998 | 9/28/1998 | P | NR |
Wes Worcester
|
|
|
09/28/98 342 - JOE ###-#### tried 2 times and was busy
|
INSP - Final | 8/31/1998 | 8/31/1998 | 8/31/1998 | P | FAIL |
Carl Dependahl
|
|
|
joe 870-*7356...need pub wks ok & plan onsite
|
INSP - Final | 8/28/1998 | 8/28/1998 | 8/28/1998 | P | NR |
Carl Dependahl
|
|
|
2:00 if possible...STILL NEED OTHER SIG'S, TEMP ON FIRE.
|
INSP - Final | 8/28/1998 | 8/28/1998 | 8/28/1998 | A | NR |
Carl Dependahl
|
|
|
CONF ONLY W/ SUPT. RE FINAL REQ'S
|
INSP - Final | 8/27/1998 | 8/28/1998 | 8/28/1998 | A | CANC |
Wes Worcester
|
|
|
08/28/98 342 - joe ###-####
|
INSP-Final Inspection | 8/27/1998 | 8/28/1998 | 8/28/1998 | A | PART |
Rick Jackson
|
|
|
joe ###-#### temp occ approved. awaiting parking lot and fire lane
|
INSP - Final | 8/26/1998 | 8/26/1998 | 8/26/1998 | P | FAIL |
Carl Dependahl
|
|
|
late pm joe ###-####...need all other ok's
|
INSP - Framing/Rough-in | 8/26/1998 | 8/26/1998 | 8/26/1998 | P | PASS |
Carl Dependahl
|
|
|
rec'd surveyor's letter...west wall ok. Clg grid & partition bracing in ok
|
INSP - Framing/Rough-in | 8/24/1998 | 8/24/1998 | 8/24/1998 | A | NR |
Carl Dependahl
|
|
|
conf only w/ Joe, supt...need surveyors letter or string line for measurements of p.l. at west.
|
INSP - Framing/Rough-in | 8/20/1998 | 8/20/1998 | 8/20/1998 | P | FAIL |
Carl Dependahl
|
|
|
conf w/ Marlene re set backs; rec'd new plat. c/n previously asked for surveyor's statement. keep c/n.( note: walls framed & approved to cover, need min. 10' to west wall.
|
INSP - Framing/Rough-in | 8/13/1998 | 8/17/1998 | 8/17/1998 | A | PART |
Carl Dependahl
|
|
|
JOE ###-#### FRAM AND WALLCOVER...int partitions ok...need bracing per plan at grid.
|
INSP - Framing/Rough-in | 8/7/1998 | 8/7/1998 | 8/7/1998 | P | NR |
Carl Dependahl
|
|
|
keep c/n...still need survey, etc.
|
INSP - Energy code compliance | 7/27/1998 | 7/27/1998 | 7/27/1998 | P | FAIL |
Carl Dependahl
|
|
|
INSULATION JOE ###-####
|
INSP - Framing/Rough-in | 7/27/1998 | 7/27/1998 | 7/27/1998 | P | FAIL |
Carl Dependahl
|
|
|
C/N. NEED VERIFY TRUSS BRACING FIX, COMPLETE FIREBLOCKING AT WALL PENETRATIONS ABOVE CLG. STILL NEED SURVEY REPORT.
|
INSP - Conference | 7/24/1998 | 7/24/1998 | 7/24/1998 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - conf w/ Tamura re prop line & survey report...need report fo
|
INSP - Framing/Rough-in | 7/6/1998 | 7/6/1998 | 7/6/1998 | P | FAIL |
Carl Dependahl
|
|
|
r/i ###-#### joe c/n, need truss bracing at webs per eng'g, nail-off hangers, bolt saddles. survey & detail for 1hr. wall pending per previous c/n. ok to continue.
|
INSP - Framing/Rough-in | 6/30/1998 | 6/30/1998 | 6/30/1998 | P | PART |
Carl Dependahl
|
|
|
joe ###-#### ext walls only ok per elec
|
INSP - Framing/Rough-in | 6/29/1998 | 6/29/1998 | 6/29/1998 | P | NR |
Carl Dependahl
|
|
|
keep c/n, need fireblock ext wall prior to cover. still need survey report.
|
INSP - Framing/Rough-in | 6/26/1998 | 6/26/1998 | 6/26/1998 | P | FAIL |
Carl Dependahl
|
|
|
cover inspection joe ###-####...wants ext walls; need complete insulation, seal penetrations, need arch's detail for deletion of a-35's at truss blocks & proposed modification to 1hr (west) wall & survey report. ok to cover except as noted.
|
INSP - Framing/Rough-in | 6/23/1998 | 6/24/1998 | 6/24/1998 | A | PART |
Carl Dependahl
|
|
|
06/24/98 340 - west wall nailing/joe ###-#### ok, need detail for possible modificatiion for gyp (1hr ) at attic/fasci also need survey report for prop. line
|
INSP - Framing/Rough-in | 6/22/1998 | 6/22/1998 | 6/22/1998 | P | NR |
Carl Dependahl
|
|
|
conference/ joe ###-#### not frame insp; bldr asked for partials...ok if passed other insps
|
INSP - Foundation | 6/8/1998 | 6/8/1998 | 6/8/1998 | P | PART |
Carl Dependahl
|
|
|
conf only; pending survey, discussed west wall (1hr) w/ John Levien and Joe of Beniton Const.
|
INSP - Foundation | 6/5/1998 | 6/5/1998 | 6/5/1998 | P | FAIL |
Carl Dependahl
|
|
|
joe ###-#### sub panel before cover hte floor placed vents at (1hr.) west fdn wall...no one onsite, didn't leave c/n...need surveyor's letter; is > 10' from pl??unprotected opening?
|
INSP - Foundation | 6/1/1998 | 6/1/1998 | 6/1/1998 | P | PART |
Carl Dependahl
|
|
|
Joe Sanford ###-#### NEED SURVEYOR'S LETTER, WALLS LOOK OK. NEED HD-2A'S AT NW CORNER
|
INSP - Foundation | 5/28/1998 | 5/28/1998 | 5/28/1998 | P | PART |
Carl Dependahl
|
|
|
ready after 2 cel ###-#### joe footing...c/n, need suveyor's verification. part only, need south side perimeter, other pads, ftgs appear ok.
|