Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD98-00758
StatusFinaled
Name STAN MOCK
Site Address 3660 N HARBOR LN
Project NameFINANCIAL PLANNING
Customer Number 
ePlanReviewNo
Description
FINANCIAL PLANNING SERVICES * TO CONSTRUCT A ONE STORY 4,704 SQ. FT. OFFICE BUILDING AND INTERIORS. THE BUILDING IS WOOD FRAMED AND NON-SPRINKLED. THE WEST WALL IS BEING BUILT TO 1-HOUR REQUIREMENTS FOR EXTERIOR WALL CONSTRUCTION WITH THE ANTICIPATION OF A NEW LOT LINE BEING ESTABLISHED IN THE FUTURE BETWEEN 10-20' FROM THE WEST WALL. (PARKING LOT IS NOT A PART OF THIS PROJECT). DRH98-0041 PC#177-98 JML
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 10/2/199810/2/1998 DONE
Details
INSP-Final Inspection9/30/19989/30/19989/30/1998PPASS
DetailsRick Jackson
fire lanes completed - occ approved
INSP - Final9/28/19989/28/19989/28/1998PNR
DetailsWes Worcester
09/28/98 342 - JOE ###-#### tried 2 times and was busy
INSP - Final8/31/19988/31/19988/31/1998PFAIL
DetailsCarl Dependahl
joe 870-*7356...need pub wks ok & plan onsite
INSP - Final8/28/19988/28/19988/28/1998PNR
DetailsCarl Dependahl
2:00 if possible...STILL NEED OTHER SIG'S, TEMP ON FIRE.
INSP - Final8/28/19988/28/19988/28/1998ANR
DetailsCarl Dependahl
CONF ONLY W/ SUPT. RE FINAL REQ'S
INSP - Final8/27/19988/28/19988/28/1998ACANC
DetailsWes Worcester
08/28/98 342 - joe ###-####
INSP-Final Inspection8/27/19988/28/19988/28/1998APART
DetailsRick Jackson
joe ###-#### temp occ approved. awaiting parking lot and fire lane
INSP - Final8/26/19988/26/19988/26/1998PFAIL
DetailsCarl Dependahl
late pm joe ###-####...need all other ok's
INSP - Framing/Rough-in8/26/19988/26/19988/26/1998PPASS
DetailsCarl Dependahl
rec'd surveyor's letter...west wall ok. Clg grid & partition bracing in ok
INSP - Framing/Rough-in8/24/19988/24/19988/24/1998ANR
DetailsCarl Dependahl
conf only w/ Joe, supt...need surveyors letter or string line for measurements of p.l. at west.
INSP - Framing/Rough-in8/20/19988/20/19988/20/1998PFAIL
DetailsCarl Dependahl
conf w/ Marlene re set backs; rec'd new plat. c/n previously asked for surveyor's statement. keep c/n.( note: walls framed & approved to cover, need min. 10' to west wall.
INSP - Framing/Rough-in8/13/19988/17/19988/17/1998APART
DetailsCarl Dependahl
JOE ###-#### FRAM AND WALLCOVER...int partitions ok...need bracing per plan at grid.
INSP - Framing/Rough-in8/7/19988/7/19988/7/1998PNR
DetailsCarl Dependahl
keep c/n...still need survey, etc.
INSP - Energy code compliance7/27/19987/27/19987/27/1998PFAIL
DetailsCarl Dependahl
INSULATION JOE ###-####
INSP - Framing/Rough-in7/27/19987/27/19987/27/1998PFAIL
DetailsCarl Dependahl
C/N. NEED VERIFY TRUSS BRACING FIX, COMPLETE FIREBLOCKING AT WALL PENETRATIONS ABOVE CLG. STILL NEED SURVEY REPORT.
INSP - Conference7/24/19987/24/19987/24/1998 PASS
DetailsCarl Dependahl
/ / 340 - conf w/ Tamura re prop line & survey report...need report fo
INSP - Framing/Rough-in7/6/19987/6/19987/6/1998PFAIL
DetailsCarl Dependahl
r/i ###-#### joe c/n, need truss bracing at webs per eng'g, nail-off hangers, bolt saddles. survey & detail for 1hr. wall pending per previous c/n. ok to continue.
INSP - Framing/Rough-in6/30/19986/30/19986/30/1998PPART
DetailsCarl Dependahl
joe ###-#### ext walls only ok per elec
INSP - Framing/Rough-in6/29/19986/29/19986/29/1998PNR
DetailsCarl Dependahl
keep c/n, need fireblock ext wall prior to cover. still need survey report.
INSP - Framing/Rough-in6/26/19986/26/19986/26/1998PFAIL
DetailsCarl Dependahl
cover inspection joe ###-####...wants ext walls; need complete insulation, seal penetrations, need arch's detail for deletion of a-35's at truss blocks & proposed modification to 1hr (west) wall & survey report. ok to cover except as noted.
INSP - Framing/Rough-in6/23/19986/24/19986/24/1998APART
DetailsCarl Dependahl
06/24/98 340 - west wall nailing/joe ###-#### ok, need detail for possible modificatiion for gyp (1hr ) at attic/fasci also need survey report for prop. line
INSP - Framing/Rough-in6/22/19986/22/19986/22/1998PNR
DetailsCarl Dependahl
conference/ joe ###-#### not frame insp; bldr asked for partials...ok if passed other insps
INSP - Foundation6/8/19986/8/19986/8/1998PPART
DetailsCarl Dependahl
conf only; pending survey, discussed west wall (1hr) w/ John Levien and Joe of Beniton Const.
INSP - Foundation6/5/19986/5/19986/5/1998PFAIL
DetailsCarl Dependahl
joe ###-#### sub panel before cover hte floor placed vents at (1hr.) west fdn wall...no one onsite, didn't leave c/n...need surveyor's letter; is > 10' from pl??unprotected opening?
INSP - Foundation6/1/19986/1/19986/1/1998PPART
DetailsCarl Dependahl
Joe Sanford ###-#### NEED SURVEYOR'S LETTER, WALLS LOOK OK. NEED HD-2A'S AT NW CORNER
INSP - Foundation5/28/19985/28/19985/28/1998PPART
DetailsCarl Dependahl
ready after 2 cel ###-#### joe footing...c/n, need suveyor's verification. part only, need south side perimeter, other pads, ftgs appear ok.