Permit Information
Permit NumberBLD98-00860
StatusFinaled
Name HEAVELY HAM
Site Address 6103 W FAIRVIEW AVE
Project NameHEAVENLY HAM
Customer Number 
ePlanReviewNo
Description
HEAVENLY HAM * CONSTRUCTION OF A 6,800 SQUARE FOOT CONCRETE MASONARY AND METAL FRAME TWO STORY STRUCTURE(ALL NON-COMBUSTIBLE AND NON-SPRINKLED). FIRST FLOOR OF 3900 SQUARE FOOT OF RETAIL AMD A 2900 SQUARE FOOT SECOND STORY FUTURE LEASE SPACE/OFFICE. DRH97-0238, CUP97-0088, PC#196-98. JML
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final3/25/19993/26/19993/26/1999PPASS
DetailsCarl Dependahl
###-#### JANINE//FINAL OCCUPY
INSP - Final3/26/19993/26/19993/26/1999 PASS
DetailsCarl Dependahl
03/26/99 340 - ###-#### JANINE//FINAL OCCUPY card signed by plbg, elec, & fire per cathy ok, for c/o.
Permanent Occupancy 3/25/19993/25/1999 DONE
Details
INSP - Final3/24/19993/24/19993/24/1999PFAIL
DetailsCarl Dependahl
03/24/99 340 - Heavenly Ham, final reinspect - Cathy has the card needplbg,elec finals, recall
INSP-Final Inspection3/24/19993/24/19993/24/1999PPASS
DetailsJoe Tawney
03/24/99 406 - REINSP OK FOR PERM OCC
INSP-Final Inspection12/11/199812/11/199812/11/1998 PART
DetailsJoe Tawney
12/10/98 406 - RICHARD EVANS ###-#### FN FIRE REINSP OK FOR TEMP OCC ALARM SUBMITTAL, KNOX BOX, FAX ALARM SIG, SIGNS
INSP - Final12/10/199812/10/199812/10/1998 PASS
Details
12/09/98 338 - made ok for temp occ
INSP-Final Inspection12/8/199812/9/199812/9/1998PFAIL
DetailsJoe Tawney
12/09/98 406 - RICHARD ###-#### FN FIRE-RE-INSP REINSP FAIL ALL ITEMS ON C/N NOT COMPLETED
INSP-Final Inspection12/4/199812/8/199812/8/1998AFAIL
DetailsJoe Tawney
12/08/98 406 - RICHARD EVANS ###-#### FN FIRE FINAL FAIL RATED DOORS, PLAN & FIRE REVIEW NOTES, ALARM SYSTEM, DUCT DET
INSP - Framing/Rough-in11/19/199811/19/199811/19/1998 PART
Details
11/14/98 338 - madeok for the shaft and the main grid need 3 pods and to
INSP - Framing/Rough-in11/19/199811/19/199811/19/1998 PART
Details
11/14/98 338 - madeok for the shaft and the main grid need 3 pods and to
INSP - Framing/Rough-in11/19/199811/19/199811/19/1998 PART
Details
11/14/98 338 - madeok for the shaft and the main grid need 3 pods and to
INSP - Final12/9/199812/10/199811/10/1998PPART
Details
12/11/98 338 - mad ok for emp occ signed the temp col behind 350/ 408
INSP - Framing/Rough-in10/14/199810/14/199810/14/1998PFAIL
Details
10/15/98 338 - OTH-OTHER AGENCIES NOT APPROVED c/n issued temp glass nee
INSP - Framing/Rough-in9/4/19989/8/19989/9/1998APART
Details
09/08/98 338 - upper decking ok with sp insp approvals for welding etc.
INSP - Framing/Rough-in8/18/19988/19/19988/19/1998APART
Details
08/19/98 338 - madeok r-bar is placed
INSP - Framing/Rough-in8/17/19988/17/19988/17/1998PPART
Details
08/17/98 338 - made ok to pour b/beam r-bar placed
INSP - Concrete8/12/19988/13/19988/13/1998ACANC
DetailsAlan Hauser
08/13/98 350 - kurt at ###-####-1025 pager # to be done by #408
INSP - Framing/Rough-in8/11/19988/11/19988/11/1998PPART
Details
08/11/98 338 - r-bar placed
INSP - Framing/Rough-in8/4/19988/5/19988/5/1998PPART
Details
08/05/98 338 - made ok to pour bond beam, all weep holes are in place an
INSP - Foundation7/13/19987/13/19987/13/1998PPART
Details
07/13/98 338 - made ok need to extend short bars for proper lap below wi
INSP - Foundation7/9/19987/10/19987/10/1998APART
Details
07/10/98 338 - FOOTING/ 1-###-#### made ok to pour r-bar is placed f