Permanent Occupancy | | 3/8/2000 | 3/8/2000 | | DONE |
|
|
|
|
BLD-Final | 12/22/1999 | 12/23/1999 | 12/23/1999 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/22/1999 at 14:05:35. Contact: ###-####. Temp. ok Rm. #226 doors as per plan need Ada & occ load signage.
|
BLD-Final | 12/16/1999 | 12/17/1999 | 12/17/1999 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/16/1999 at 08:27:48. Contact: ###-####. C/N.
|
FIRE-Final Inspection | 12/13/1999 | 12/14/1999 | 12/14/1999 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/13/1999 at 11:49:30. Contact: ###-####. Alarm test- need connection for reporting; test AHU shut-off.
|
FIRE-Hydro test above ground | 11/22/1999 | 11/23/1999 | 11/23/1999 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 14:06:15. Contact: ###-####. FDC not ready to hydro.
|
FIRE-Supply Line Hydro | 11/22/1999 | 11/23/1999 | 11/23/1999 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 14:07:38. Contact: ###-####. Supply hydro ok.
|
FIRE-Sprinkler Rough-in | 11/18/1999 | 11/18/1999 | 11/18/1999 | P | PART |
Rick Jackson
|
|
|
Tested fire pump and fire pump controller; flow test passed; controller not monitored.
|
FIRE-Hydro test above ground | 11/4/1999 | 11/5/1999 | 11/5/1999 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/04/1999 at 13:02:56. Contact: ###-####. Hydro okay on all floors.
|
FIRE-Conference | 11/1/1999 | 11/2/1999 | 11/2/1999 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 16:01:48. Contact: ###-####. With simplea and contractor to review fire alarm plans.
|
BLD-Framing/Rough-in | 10/18/1999 | 10/19/1999 | 10/20/1999 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/18/1999 at 15:53:19. Contact: ###-####. Ceiling 1st floor ok for cover
|
FIRE-Supply Line Flush | 10/12/1999 | 10/13/1999 | 10/13/1999 | A | PASS |
Rick Jackson
|
|
|
forest ###-#### Underground flush ok
|
FIRE-Supply Line Flush | 10/13/1999 | 10/13/1999 | 10/13/1999 | A | PASS |
Rick Jackson
|
|
|
met with sprinkler designer and Bill Alexander- sprinklers will also bo installed above duct in North Corridor- sprinklers will not be installed above duct in East corridor- (Below duct only)
|
BLD-Conference | 10/4/1999 | 10/4/1999 | 10/4/1999 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/04/1999 at 10:27:40. Contact: ###-####. Ok to install ceiling grid in portion of 4th floor
|
FIRE-Conference | 10/1/1999 | 10/4/1999 | 10/4/1999 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/01/1999 at 16:34:46. Contact: ###-####. Need alarm plans
|
FIRE-Sprinkler Rough-in | 9/29/1999 | 10/1/1999 | 10/1/1999 | A | FAIL |
Rick Jackson
|
|
|
4TH FLOOR-- FORREST- ###-#### R/I 4th floor corridor: not installed within 22" of deck; okay to cover gridded ceiling areas
|
BLD-Framing/Rough-in | 9/23/1999 | 9/24/1999 | 9/24/1999 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/23/1999 at 10:30:40. Contact: ###-####. 3-2 floor ceiling ok five stop and glass block wall c/n
|
FIRE-Sprinkler Rough-in | 9/22/1999 | 9/23/1999 | 9/24/1999 | P | FAIL |
Rick Jackson
|
|
|
forest ###-#### Okay to cover 2nd & 3rd floor classrooms and labs; Corridors require heads within 22" of deck
|
INSP - Framing/Rough-in | 7/8/1999 | 7/8/1999 | 7/8/1999 | | PART |
Jim Storey
|
|
|
07/07/99 301 - penthouse ok for cover
|
INSP - Framing/Rough-in | 5/18/1999 | 5/20/1999 | 5/20/1999 | A | PART |
Jim Storey
|
|
|
05/20/99 301 - 2 nd floor in progess ok to rock corador walls
|
INSP-Conference | 4/22/1999 | 4/22/1999 | 4/22/1999 | A | PART |
Rick Jackson
|
|
|
issued c/n for the installation of the temp standpipe - gave deadline of 4/29 or stop work above 3rd floor
|
INSP-Conference | 3/8/1999 | 3/8/1999 | 3/8/1999 | P | PART |
Rick Jackson
|
|
|
with gen. and 301 - reviewed plans and walk through of site
|