INSP - Final | 9/2/1999 | 9/3/1999 | 9/3/1999 | A | PASS |
Carl Dependahl
|
|
|
09/03/99 340 - terry- ###-#### fn occ insp
|
Permanent Occupancy | | 9/3/1999 | 9/3/1999 | | DONE |
|
|
|
|
INSP - Final | 8/25/1999 | 8/26/1999 | 8/26/1999 | A | FAIL |
Carl Dependahl
|
|
|
08/26/99 340 - terry ###-####; c/n, spec insp & eng's letter; shaft, etc
|
INSP - Framing/Rough-in | 8/16/1999 | 8/16/1999 | 8/16/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/16/99 340 - conf w/ contractor; will review previous actions. rec'd a
|
INSP - Final | 7/22/1999 | 7/22/1999 | 7/22/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP-Final Inspection | 6/10/1999 | 6/14/1999 | 6/14/1999 | A | FAIL |
Joe Tawney
|
|
|
06/14/99 406 - REINSP FAIL NFPA 72 FORM
|
INSP-Final Inspection | 5/24/1999 | 5/25/1999 | 5/25/1999 | P | FAIL |
Joe Tawney
|
|
|
05/25/99 406 - REINSP FAIL ADDRESS, FIRE DOORS, EMERG LIGHTS, REFR PIPIN
|
INSP-Final Inspection | 5/7/1999 | 5/10/1999 | 5/10/1999 | P | CANC |
Joe Tawney
|
|
|
05/10/99 406 - CANCELLED TO BE RESCHED
|
INSP-Sprinkler Rough-in/Hydro | 2/3/1999 | 2/3/1999 | 2/3/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - rough in of ext canopy FAIL PROVIDE PROTECTION IN CONCEALED
|
INSP-Final Inspection | 12/4/1998 | 12/7/1998 | 12/7/1998 | A | PART |
Joe Tawney
|
|
|
12/07/98 406 - JOHN ###-#### SCHEDULED W/JOE AT 10:30 ALARM SYSTM TEST OK ON TEST
|
INSP-Final Inspection | 12/2/1998 | 12/3/1998 | 12/4/1998 | P | FAIL |
Joe Tawney
|
|
|
12/03/98 406 - Scheduled by Hello!. SPKLR ROUGH IN FAIL BAKERY FINAL FAIL SPKLR SYSTEM NOT YET TESTED SUPRV
|
INSP - Wall cover | 12/2/1998 | 12/3/1998 | 12/3/1998 | P | PART |
|
|
|
12/02/98 338 - madeok
|
INSP-Supply line flush | 11/10/1998 | 11/10/1998 | 11/10/1998 | | NR |
Joe Tawney
|
|
|
/ / 406 - SUPPLY LINE FLUSH NOT READY TO BE WITNESSED BY JOHN ANDERSON
|
INSP-Conference | 10/20/1998 | 10/20/1998 | 10/20/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF WITH JOHN ANDERSON & STAN BUESS ABOUT SHUTTING DOWM SPK
|
INSP - Framing/Rough-in | 10/8/1998 | 10/8/1998 | 10/8/1998 | P | PART |
|
|
|
10/08/98 338 - made ok to start cover at the front entry soffit
|
INSP-Conference | 9/9/1998 | 9/10/1998 | 9/10/1998 | A | PART |
Joe Tawney
|
|
|
09/10/98 406 - JOHN ANDERSON ###-####-JOHN WILL CALL CONF ON EXITING DURING CONSTR WITH JOHN ANDERSON. NEED ARCH TO CLARIFY P
|
INSP - Foundation | 8/31/1998 | 8/31/1998 | 8/31/1998 | P | PART |
|
|
|
08/31/98 338 - R-BAR PLACED OK TO POUR WITH SPP INSP APPROVAL
|