INSP - Final | 8/3/1999 | 8/5/1999 | 8/5/1999 | A | PASS |
Jim Storey
|
|
|
08/05/99 301 - ###-#### BRIAN
|
INSP-Final Inspection | 8/3/1999 | 8/5/1999 | 8/5/1999 | A | PASS |
Rick Jackson
|
|
|
10:00 AM TALKED TO RICK. BRIAN ###-#### occ approved
|
Permanent Occupancy | | 8/5/1999 | 8/5/1999 | | DONE |
|
|
|
|
INSP-Conference | 8/3/1999 | 8/3/1999 | 8/3/1999 | A | PART |
Rick Jackson
|
|
|
requirements for final sign-off; set up final inspection for 8/5
|
INSP - Final | 7/21/1999 | 7/27/1999 | 7/27/1999 | A | FAIL |
Jim Storey
|
|
|
07/27/99 301 - c/n
|
INSP-Final Inspection | 7/21/1999 | 7/27/1999 | 7/27/1999 | A | FAIL |
Rick Jackson
|
|
|
BRIAN ###-#### LIFE SAFETY at 10:00 as per rick j. fire lanes
|
INSP-Conference | 1/26/1999 | 1/26/1999 | 1/26/1999 | | PART |
Rick Jackson
|
|
|
/ / 409 - SPRAY BOOTH APPROVED FOR USE
|
INSP-Conference | 1/25/1999 | 1/25/1999 | 1/25/1999 | A | PART |
Rick Jackson
|
|
|
discussed resubmittal on booth - they will submit info for the booth operation
|
INSP-Conference | 1/22/1999 | 1/22/1999 | 1/22/1999 | P | FAIL |
Rick Jackson
|
|
|
discussed with VP the paint booth operation. placed not to occupy sticker on unit and issued c/n to not to use the paint booth until approved.
|
INSP-Final Inspection | 1/20/1999 | 1/21/1999 | 1/21/1999 | A | FAIL |
Rick Jackson
|
|
|
mike -###-#### fn fire insp exsisting paint booth inspection - unit removed from old shop and installed in new fab building: doesn't comply with NFPA or UFC - will discuss with plan check and inspections about shutting it down
|
INSP-Alarm Testing | 1/12/1999 | 1/12/1999 | 1/12/1999 | A | PASS |
Rick Jackson
|
|
|
tested preaction system only. okay per plans. still need knox box, perm address, label annunciator
|
INSP - Final | 12/28/1998 | 12/29/1998 | 12/29/1998 | A | PART |
Jim Storey
|
|
|
12/29/98 301 - SCLG-OK SUSPENDED CEILING at main entry
|
INSP-Conference | 12/29/1998 | 12/29/1998 | 12/29/1998 | A | PART |
Rick Jackson
|
|
|
checked status for final; recheck preaction system functions
|
INSP - Framing/Rough-in | 12/21/1998 | 12/22/1998 | 12/22/1998 | A | PART |
Jim Storey
|
|
|
12/22/98 301 - TCO -TEMP C OF O ISSUED need follow up in 90 days
|
INSP - Final | 12/21/1998 | 12/21/1998 | 12/21/1998 | | NR |
Jim Storey
|
|
|
12/21/98 301 - jeff ###-#### temp occ insp
|
INSP - Final | 12/18/1998 | 12/21/1998 | 12/21/1998 | A | NR |
Jim Storey
|
|
|
12/21/98 301 - jeff ###-#### temp occ insp
|
INSP-Final Inspection | 12/18/1998 | 12/21/1998 | 12/21/1998 | A | PART |
Rick Jackson
|
|
|
12/21/98 409 - JEFF...###-#### test preaction; perm address; NFPA 72 ansd central station certificate
|
INSP-Final Inspection | 12/18/1998 | 12/18/1998 | 12/18/1998 | P | FAIL |
Rick Jackson
|
|
|
12/18/98 409 - sprinklers not complete in office area
|
INSP - Framing/Rough-in | 12/15/1998 | 12/15/1998 | 12/15/1998 | P | PART |
Jim Storey
|
|
|
12/15/98 301 - SCLG-OK SUSPENDED CEILING
|
INSP - Final | 12/14/1998 | 12/14/1998 | 12/14/1998 | P | PART |
Jim Storey
|
|
|
12/14/98 301 - TEMP OK FOR GRID LINE 1 THRU H IN F-1 OCC ONLY.
|
INSP-Final Inspection | 12/14/1998 | 12/14/1998 | 12/14/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for fab area grid lines a-h only. tested alarms, sprinklers, etc. preaction system not complete. office areas not ready
|
INSP - Final | 12/7/1998 | 12/8/1998 | 12/8/1998 | A | NR |
Jim Storey
|
|
|
12/08/98 301 - conf for temp occ. work in progess
|
INSP-Conference | 12/8/1998 | 12/8/1998 | 12/8/1998 | A | PART |
Rick Jackson
|
|
|
discussed requirements for temp occ with contractor and owners
|
INSP-Conference | 12/2/1998 | 12/2/1998 | 12/2/1998 | P | PART |
Rick Jackson
|
|
|
to determine requirements for moving in equipment and partial occupancy. off-site monitoring; extinguishers; tape on sprinkler heads; pre-action system plans; knox box; test alarms
|
INSP - Framing/Rough-in | 11/5/1998 | 11/6/1998 | 11/6/1998 | A | PART |
Tom Arcoraci
|
|
|
11/06/98 408 - JEFF--###-#### ok to cover one side of office area
|
INSP-Final Inspection | 11/5/1998 | 11/6/1998 | 11/6/1998 | P | PART |
Joe Tawney
|
|
|
11/06/98 406 - MIKE- ###-#### FIRE INSP OK ON ABOVE GROUND HYDRO TEST EXC FDC PIPING OK ON RI EXC OBSTR HEADS
|
INSP - Framing/Rough-in | 11/2/1998 | 11/2/1998 | 11/2/1998 | A | PART |
Jim Storey
|
|
|
11/02/98 301 - framing ok on a3 occ
|
INSP - Framing/Rough-in | 10/30/1998 | 10/30/1998 | 10/30/1998 | P | FAIL |
|
|
|
10/30/98 333 - ###-####
|
INSP-Supply line flush | 10/22/1998 | 10/22/1998 | 10/22/1998 | P | PASS |
Rick Jackson
|
|
|
underground flush okay
|
INSP-Sprinkler Rough-in/Hydro | 10/13/1998 | 10/13/1998 | 10/13/1998 | A | PART |
Rick Jackson
|
|
|
underground hydro okay. sway bracing needed as most areas not complete. okay to cover in 1st floor of bathroom areas (fab area)
|
INSP - Framing/Rough-in | 10/12/1998 | 10/12/1998 | 10/12/1998 | P | PART |
Jim Storey
|
|
|
10/12/98 301 - JEFF ###-#### FRAM-OK FRAMING ì
|
INSP-Sprinkler Rough-in/Hydro | 9/24/1998 | 9/24/1998 | 9/24/1998 | A | PART |
Rick Jackson
|
|
|
checked approved plans and general area, recheck riser piping for hangers
|
INSP - Concrete | 9/1/1998 | 9/1/1998 | 9/1/1998 | | PASS |
Jim Storey
|
|
|
09/01/98 301 - after lunch early afternoon terry ###-#### 2nd lift massonary restrooms ok
|
INSP - Concrete | 8/28/1998 | 8/28/1998 | 8/28/1998 | A | CANC |
Russ Owen
|
|
|
requires special insp. 08/28/98 407 - first thing in the morning terry ###-####
|
INSP - Concrete | 8/25/1998 | 8/26/1998 | 8/26/1998 | A | FAIL |
Jim Storey
|
|
|
08/26/98 301 - terry ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED arch. and engineer of record submit info. to resolve 4 idems posted on site.
|